Loading...

Messages

Proposals

Stuck in your homework and missing deadline? Get urgent help in $10/Page with 24 hours deadline

Get Urgent Writing Help In Your Essays, Assignments, Homeworks, Dissertation, Thesis Or Coursework & Achieve A+ Grades.

Privacy Guaranteed - 100% Plagiarism Free Writing - Free Turnitin Report - Professional And Experienced Writers - 24/7 Online Support

The most common circumstance for project closure is simply a

23/11/2021 Client: muhammad11 Deadline: 2 Day

1 A ________ Gantt chart is a simple and effective way to depict progress on a project.

Control

Tracking

Simple

Baseline

Variance

2 A project monitoring system involves all of the following EXCEPT

Determining what data to collect.

Adjusting the data.

Reporting current progress.

Analysis of the data.

Determining how, when, and who will collect the data.

3 An analysis carried out during and shortly after the project life cycle that attempts to capture positive and negative learning is represented in which of the following?

Performance evaluation

Lessons learned

Scenario analysis

Strategic objectives

Variance analyses

4 Jessica just received the following information on her project: PV = 200, EV = 300, AC = 250, BAC = 1500, EAC = 1208. In terms of cost at completion.

The project will currently finish under budget.

The project will currently finish on budget.

The project will currently finish over budget.

The project will currently finish behind schedule.

There is insufficient information to draw conclusions.

5 Jim receives the following information on his project: PV = 1000, EV = 1200, AC = 800, BAC = 2000, EAC = 1333. How is the project doing in terms of schedule?

The same amount of work has been done than planned

More work has been done than planned

The project has cost less than planned

Less work has been done than planned

There is not enough information to draw a conclusion

6 Nancy tells her supervisor that as of right now, $1.05 worth of work has been accomplished for each $1 worth of scheduled work. Nancy got this information from viewing the

TCPI.

CPI.

SPI.

SV.

PCIB.

7 The cost variance for a project is calculated by

EV - PV.

PV - EV.

AC - SV.

CV - EV.

EV - AC.

8 The earned value system starts with the time-phased costs that provide the project baseline, which is called the

Earned value of work scheduled.

Planned budgeted value of work scheduled.

Scheduled value of work completed.

Scheduled value of work scheduled.

Planned budgeted value of work completed.

9 The first step in the project control process for measuring and evaluating project performance is to

Review the project priority matrix.

Determine the project objectives.

Analyze the project budget.

Set a baseline plan.

Determine the project deliverables.

10 The following are general tips for conducting performance reviews EXCEPT

Be fair and consistent in your treatment of all team members.

Use other team members' performance as a method to compare and evaluate.

Begin the process by asking the individual to evaluate his or her own contributions to the project.

When you have to be critical, focus the criticism on specific examples of behavior and not on the individual personally.

Treat the review as only one point in an ongoing process.

11 The most common circumstance for project closure is simply a ________ project.

Successful

Completed

Over-budget

Underachieving

Overdue

12 The purpose of project evaluation is to assess how well

The project team and team members performed.

The project team, team members and project manager performed.

The project team performed.

The project manager performed.

The team members performed.

13 The schedule variance for a project is calculated by:

PV - EV

AC - SV

CV - EV

EV - PV

EV - AC

14 The third step in the project control process for measuring and evaluating project performance is to

Compare the plan against actual performance.

Analyze inputs to the control system.

Review spending with team members.

Review the baseline plan with top management.

Measure both progress and performance.

15 The typical mechanism for the evaluation of teams is normally

A survey completed by the team members.

A survey completed by the internal or external customers.

A survey completed by members of top management.

An analysis by an outside consultant.

A personal interview of each team member.

16 When someone familiar with each task estimates what percent of the task has been completed or how much of the task remains, they are creating a method for assigning costs to the baseline called the

0/100 percent rule.

Work complete rule.

Task complete rule.

Degree complete rule.

Percent complete rule.

17 Which of the following methods will measure the cost efficiency of the work accomplished to date?

AC/CV

SV/CV

EV/PV

EV/AC

AC/SV

18 Which of the following would NOT be appropriate to assess when evaluating team performance?

Effectiveness of group decisions

How well the team performed in terms of time, cost, and specifications

Individual strengths and weaknesses

Customer satisfaction with project deliverables

Trust among group members

19 Which performance index is the most potentially misleading?

EV

CV

EAC

CPI

SV

20 ________ of lessons learned are designed to improve performance on current and future projects.

Culminations

Retrospectives

Evolutions

Corrective action plans

Introspectives
1 A ________ Gantt chart is a simple and effective way to depict progress on a project.

Control

Tracking

Simple

Baseline

Variance

2 A project monitoring system involves all of the following EXCEPT

Determining what data to collect.

Adjusting the data.

Reporting current progress.

Analysis of the data.

Determining how, when, and who will collect the data.

3 An analysis carried out during and shortly after the project life cycle that attempts to capture positive and negative learning is represented in which of the following?

Performance evaluation

Lessons learned

Scenario analysis

Strategic objectives

Variance analyses

4 Jessica just received the following information on her project: PV = 200, EV = 300, AC = 250, BAC = 1500, EAC = 1208. In terms of cost at completion.

The project will currently finish under budget.

The project will currently finish on budget.

The project will currently finish over budget.

The project will currently finish behind schedule.

There is insufficient information to draw conclusions.

5 Jim receives the following information on his project: PV = 1000, EV = 1200, AC = 800, BAC = 2000, EAC = 1333. How is the project doing in terms of schedule?

The same amount of work has been done than planned

More work has been done than planned

The project has cost less than planned

Less work has been done than planned

There is not enough information to draw a conclusion

6 Nancy tells her supervisor that as of right now, $1.05 worth of work has been accomplished for each $1 worth of scheduled work. Nancy got this information from viewing the

TCPI.

CPI.

SPI.

SV.

PCIB.

7 The cost variance for a project is calculated by

EV - PV.

PV - EV.

AC - SV.

CV - EV.

EV - AC.

8 The earned value system starts with the time-phased costs that provide the project baseline, which is called the

Earned value of work scheduled.

Planned budgeted value of work scheduled.

Scheduled value of work completed.

Scheduled value of work scheduled.

Planned budgeted value of work completed.

9 The first step in the project control process for measuring and evaluating project performance is to

Review the project priority matrix.

Determine the project objectives.

Analyze the project budget.

Set a baseline plan.

Determine the project deliverables.

10 The following are general tips for conducting performance reviews EXCEPT

Be fair and consistent in your treatment of all team members.

Use other team members' performance as a method to compare and evaluate.

Begin the process by asking the individual to evaluate his or her own contributions to the project.

When you have to be critical, focus the criticism on specific examples of behavior and not on the individual personally.

Treat the review as only one point in an ongoing process.

11 The most common circumstance for project closure is simply a ________ project.

Successful

Completed

Over-budget

Underachieving

Overdue

12 The purpose of project evaluation is to assess how well

The project team and team members performed.

The project team, team members and project manager performed.

The project team performed.

The project manager performed.

The team members performed.

13 The schedule variance for a project is calculated by:

PV - EV

AC - SV

CV - EV

EV - PV

EV - AC

14 The third step in the project control process for measuring and evaluating project performance is to

Compare the plan against actual performance.

Analyze inputs to the control system.

Review spending with team members.

Review the baseline plan with top management.

Measure both progress and performance.

15 The typical mechanism for the evaluation of teams is normally

A survey completed by the team members.

A survey completed by the internal or external customers.

A survey completed by members of top management.

An analysis by an outside consultant.

A personal interview of each team member.

16 When someone familiar with each task estimates what percent of the task has been completed or how much of the task remains, they are creating a method for assigning costs to the baseline called the

0/100 percent rule.

Work complete rule.

Task complete rule.

Degree complete rule.

Percent complete rule.

17 Which of the following methods will measure the cost efficiency of the work accomplished to date?

AC/CV

SV/CV

EV/PV

EV/AC

AC/SV

18 Which of the following would NOT be appropriate to assess when evaluating team performance?

Effectiveness of group decisions

How well the team performed in terms of time, cost, and specifications

Individual strengths and weaknesses

Customer satisfaction with project deliverables

Trust among group members

19 Which performance index is the most potentially misleading?

EV

CV

EAC

CPI

SV

20 ________ of lessons learned are designed to improve performance on current and future projects.

Culminations

Retrospectives

Evolutions

Corrective action plans

Introspectives

Homework is Completed By:

Writer Writer Name Amount Client Comments & Rating
Instant Homework Helper

ONLINE

Instant Homework Helper

$36

She helped me in last minute in a very reasonable price. She is a lifesaver, I got A+ grade in my homework, I will surely hire her again for my next assignments, Thumbs Up!

Order & Get This Solution Within 3 Hours in $25/Page

Custom Original Solution And Get A+ Grades

  • 100% Plagiarism Free
  • Proper APA/MLA/Harvard Referencing
  • Delivery in 3 Hours After Placing Order
  • Free Turnitin Report
  • Unlimited Revisions
  • Privacy Guaranteed

Order & Get This Solution Within 6 Hours in $20/Page

Custom Original Solution And Get A+ Grades

  • 100% Plagiarism Free
  • Proper APA/MLA/Harvard Referencing
  • Delivery in 6 Hours After Placing Order
  • Free Turnitin Report
  • Unlimited Revisions
  • Privacy Guaranteed

Order & Get This Solution Within 12 Hours in $15/Page

Custom Original Solution And Get A+ Grades

  • 100% Plagiarism Free
  • Proper APA/MLA/Harvard Referencing
  • Delivery in 12 Hours After Placing Order
  • Free Turnitin Report
  • Unlimited Revisions
  • Privacy Guaranteed

6 writers have sent their proposals to do this homework:

Coursework Assignment Help
Pro Writer
Assignments Hut
Top Writing Guru
Professor Smith
Assignment Helper
Writer Writer Name Offer Chat
Coursework Assignment Help

ONLINE

Coursework Assignment Help

I find your project quite stimulating and related to my profession. I can surely contribute you with your project.

$15 Chat With Writer
Pro Writer

ONLINE

Pro Writer

I am a professional and experienced writer and I have written research reports, proposals, essays, thesis and dissertations on a variety of topics.

$36 Chat With Writer
Assignments Hut

ONLINE

Assignments Hut

Being a Ph.D. in the Business field, I have been doing academic writing for the past 7 years and have a good command over writing research papers, essay, dissertations and all kinds of academic writing and proofreading.

$23 Chat With Writer
Top Writing Guru

ONLINE

Top Writing Guru

I am an academic and research writer with having an MBA degree in business and finance. I have written many business reports on several topics and am well aware of all academic referencing styles.

$48 Chat With Writer
Professor Smith

ONLINE

Professor Smith

This project is my strength and I can fulfill your requirements properly within your given deadline. I always give plagiarism-free work to my clients at very competitive prices.

$38 Chat With Writer
Assignment Helper

ONLINE

Assignment Helper

I can assist you in plagiarism free writing as I have already done several related projects of writing. I have a master qualification with 5 years’ experience in; Essay Writing, Case Study Writing, Report Writing.

$28 Chat With Writer

Let our expert academic writers to help you in achieving a+ grades in your homework, assignment, quiz or exam.

Similar Homework Questions

Ethics - Bxt 90t5 590 replacement - Java program for rolling two dice - Vector addition experiment lab report - An inspector calls knowledge organiser - Paulina adler stop breathing lyrics - Unsuccessful http response betfred - Harvey norman bennetts green - Discussion social influence - Business math powerpoint presentations - Importance of establishing credibility in business communications - California pizza kitchen case study - 4/24 weatherly close nelson bay - Jb hi fi receipts - Radioactive dating game phet answers - Water affecting activity permit - Diana v state board of education 1970 - Working principle of lathe machine ppt - Marketing myopia examples in sports - Food web of the great barrier reef - Analyzing Graph And Summarizing - Was the titanic poorly built - Job Design - Toyota troop carrier dimensions - Lg electronics usa englewood cliffs nj - Man's search for meaning download - Discussion 8 - Astrand rhyming cycle ergometer test - Fennec fox behavioral adaptations - The art - Green computing research project 1 - Caregiver medical consent form - 100 best road trip songs - Swagelok heat trace tubing - Damaged care full movie - How is jem courageous in to kill a mockingbird - Virus explorer student worksheet answers - Prentice hall online textbook - The secret tapes of lucky boo - Voices of freedom eric foner volume 2 3rd edition pdf - Edi separator adapter in sap pi - Barry manilow t shirt study - Blazenet belhaven - Nursing Discussion - Bart starr commemorative celebration rawhide inc september 14 - How to calculate expected monetary value in excel - Lean production is a management philosophy and a pull system throughout the plant. - Malaysia target market - Week 4 Part 1 - Nucor corporation in case analysis - Usgovinfo about com blorgs htm - 100 sit ups a day canteen - Postmodern frame in art - Aboriginal australia jack davis poem analysis - Separation of the components of a mixture lab report answers - Get out essay analysis - Degree of curve formula in surveying - Financial entertainment bite club - Astrazeneca pty ltd v glaxosmithkline australia pty ltd - Cabaniss psychodynamic psychotherapy pdf - Trader joe's case study harvard analysis - Medication dosage calculation worksheets - Industrial and Hazardous Waste Management - Topic 4 DQ 1 and 2 - Comparing e1 and e2 - Module 08 Pre-Lab Assignment - COVID 19 discussion - MK405 Unit 7 Discussion - Elevation of privilege eop card game - Thomson reuters investor presentation - Cis report - Ccs uc 200 kit - Phi slama jama song lyrics - Innovative E-Business -- Business Canvas Model - Harley oil temp sensor - , identify and explain what exo-system and macro-system factors affect access to child care? - Ti 92 plus manual - Marketing tutor - Warehouse manager alternative titles - Discounting factoring and forfaiting - Basic algebra cheat sheet - Practical Connection Assignment - Explain what the barriers are to interpersonal communications - If he hollers let him go chapter summary - Is sunita williams dead - Week 2 Assignment - Advanced Skills Transcript Counseling Session Transcript - 961 hindmarsh tiers road - Advantages and disadvantages of student politics - European History Assignment 1 - Clinical Field Experience B: Student Needs and Instructional Planning - How have economic forecasts for this country evolved - What is authoring system - Difference between japanese and american management style - Islamic scarf controversy in france - In mead's theory of development, the "me" is the "object of action" or the "self as object." - Fred wilson mining the museum maryland - Spc in automotive industry - Short Essay - Hu2000 week 2 assignment the good samaritan - 5 page work