Wedding wbs

19/12/2020 Client: saad24vbs Deadline: 7 Days

Running head: WBS Assignment 1


WBS Assignment 14


WBS Assignment

Wedding Plan for Mary & Justin


Xunzhen Wu – 301115184


Pawan singh sahota -301088222


Moayad Harbi- 301112470


August 15, 2020


Table of Contents 1. Introduction 3 2. Work Breakdown Structure (WBS) 3 2.1 WBS Tree Diagram 4 2.2 WBS Tabular View and Definition 4 3. List of Activities 5 3.1 Determination of Timing of Activities 5 3.2 Budget Requirement of Activities 5 3.3 Activity on Node 5 3.4 Program Evaluation Review Technique (PERT) and Critical Path 5 4. Project 5 4.1 Imitative 5 4.2 Planning 5 4.3 Execution 5 4.4 Closing 5 5. Appendix 5


1. Introduction

This report illustrates the network diagram with work breakdown structures for Mary and Justin’s wedding plan. Work Breakdown Structure (WBS) is the tool that project work breaks into small tasks to manage, which is one of most important project management documents to integrate scope, cost and schedule baselines to ensure the alignment of project plans, according to Project Management Book of Knowledge (PMBOK). Meanwhile, more activities details will be analyzed with the activity list related to the duration and variance, activity on node (AON),


program evaluation and review technique (PERT), critical path on the schedule and budget requirements based on each activity. Accordingly, the wedding for Mary and Justin could be proceeded on time and under budget in accordance with their approval.


Mary and Justin expect the whole wedding theme, schedule, venue, party, wedding preparations for the guests, materials arrangement as well as the whole wedding process in church registration and ceremony like typical Canadian style for one of their most memorable days. Thus, completion of each activity is very critical to lead to the success of the wedding plan regardless of the deliverables in the wedding day and achievements of the scope, schedule, cost and service satisfaction of the whole wedding plan.


2. Work Breakdown Structure (WBS)

WBS separates the tasks with the hierarchical structure including products, materials, services, equipment, venues, service provider, facilities and all related activities in the task. Each task under the hierarchical structure makes up the whole project elements, which contributes to the project scope and deliverables. Project team could use WBS to track the project status as well as the monitoring the project completion status, while task or workstream leader is in charge of each task. Please help refer to below WBS tree diagram and tabular diagram for Mary and Justin’s wedding, details attached in excel.


2.1 WBS Tree Diagram

The WBS tree diagram breaks down the project objective into the measurable and deliverable tasks as an outline of an integrated information system. The detailed WBS is attached excel.




2.2 WBS Tabular View and Definition

The WBS tabular view provides levels of each task based on WBS structure, and project team could use WBS tabular view to define the details of the task as well.


Level


WBS Code


Element Name


Definition


1


1


Mary and Justin's Wedding Plan Project


Plan for the whole wedding day in church and ceremony


2


1.1


Marriage planning


Plan phase for the marriage with customer expectation


3


1.1.1


Plan wedding budget


The total budget for the marriage


3


1.1.2


Venue selection


The venues expectation for the marriage


3


1.1.3


Determine Guests list


Assess how many guests to invite


2


1.2


Inviting Guests


Invite guests for wedding


3


1.2.1


Finalize the guest list


Determine the guest list for the venue’s preparation


3


1.2.2


Design invitation letter


Pick up the style of invitation letter


3


1.2.3


Order invitation letters


Purchase the invitation letter


3


1.2.4


Send out invitation letters


Send out the invitation letter to all guests at least one month earlier


2


1.3


Venues


Determine venues


3


1.3.1


Wedding ceremony location


Pick up the ceremony location


4


1.3.1.1


Reserve ceremony hotel


Pay the deposit for ceremony hotel


4


1.3.1.2


Confirm menu


Pick up the food menu


4


1.3.1.3


Table Decoration


Request the hotel on the table decoration


4


1.3.1.4


Purchase wedding cakes


Book up the wedding cake for wedding day


4


1.3.2


Wedding church location


Pick up the wedding church location


4


1.3.2.1


Confirm wedding theme


Determine themes for church registration


4


1.3.2.2


Visits churches


Pick up the church per expectation


4


1.3.2.3


Reserve church


Pay the deposit for church and the date


4


1.3.2.4


Purchase Flowers


Book the flowers for wedding day


2


1.4


Photography and Video


Determine the photography and videographer


3


1.4.1


Choose photographer& videography


Finalize the service provider for photo and video


3


1.4.2


Discuss on the photography album and videography


Review the photo album styles


3


1.4.3


Review demos and finalize the wedding photo and video styles


Determine the photo style


3


1.4.4


Shoot photos for wedding


Take the pictures one month before wedding day


2


1.5


Entertainment


Arrange entertainment


3


1.5.1


Reserve wedding band


Finalize the wedding band


3


1.5.2


Rent audio package in hotel and DJ


Finalize the audio equipment


3


1.5.3


Book the host for ceremony


Pick up the ceremony host


2


1.6


Preparation on wedding


Prepare for the outfit, transportation and do rehearsal for the wedding day


3


1.6.1


Wedding outfit


Purchase outfit for the wedding day


4


1.6.1.1


Purchase wedding rings


Make sure customized wedding rings in place at least one week before wedding day


4


1.6.1.2


Purchase wedding jewelry


Make sure customized wedding jewelry in place at least one week before wedding day


4


1.6.1.3


Purchase wedding dress for Bride and Bridegroom


Make sure customized wedding dress in place at least one week before wedding day


3


1.6.2


Wedding Transportation


Finalize the transportation


4


1.6.2.1


Book the rental transportation for wedding


Pay the deposit of the transportation rental for guests and bride/broom


4


1.6.2.2


Book up travel agency for honeymoon


Pay the deposit for the honeymoon travel


2


1.7


Wedding day


confirm the process on wedding day


3


1.7.1


Make up and do hairiness


Brides and Broom take the makeup and hairiness


3


1.7.2


Church registration


Marriage register in church


3


1.7.3


Wedding Ceremony


Celebrate the wedding with guests


3


1.7.4


Wedding dinner


Celebrate the dinner with guests


3. List of Activities

3.1 Determination of Timing of Activities

3.2 Budget Requirement of Activities

3.3 Activity on Node

3.4 Program Evaluation Review Technique (PERT) and Critical Path

Project Initiation


Initiation is the first part of our project in which our company will arrange the meeting to make the final approval for the plan that are made for all the events .In this meeting we will discuss and let the clients know what will be the arrangements for every event and budget will be discussed in this meeting.


1. Evaluations and Recommendations: - In this part our company will evaluate all resources that are needed for the events and also recommend to the customers new ideas related their events.


2. Developing the charter for clients and group: - Next part after evaluation part is developing the charter that will help the staff of wedding planning company to look on each task for the events. In this charter we will add the terms and conditions for the client and get the sign from the clients from trustworthy point. Moreover, tasks and duties will be written in this charter for the wedding planners to be followed.


3. Project charter signed and approval: - This is time to get the final approval and getting the signs from the clients on the contract that we will make for all tasks. We will submit our charter to the client for review so that they can let us know if they need any changes in it.


Planning


1.Create Preliminary scope statement: - This is kind of contract between sponsors and clients for completing the work on time. This statement consists of objectives and all deliverables that company needs to perform on given time and within given budget. This contract works as a mutual understanding and the trustworthiness among the parties.


2. Develop project plan: - this is the paramount part of the project planning in this part plans and ideas related project needs to be developed by the sponsor and if there is needs to change something that can be done and new ideas can be developed.


3.Submit project plan: - once the final project plan got approved by all staff members and the directors its time to submit the plan for final approval for all the activities and this is approved by authority and the party for whom all events.


4. Booking the items: - This is time when our company will decide all the elements that are needed to complete the project successfully like catering, sound, security, liquor certificate, photographer, makeup artist, fashion designer and marriage hall.


Execution


1 Meeting with vendors: - Now this is time to execute the plans that are above mentioned in the WBS. First of all, we will check our budget then will be starting to spend the money. then we will meet with banquet hall manager for the booking of hall for all events. Then we will go to the garment shops and to the fashion designer and any agency that will be good in decorating the halls for events.


2.Design system :- Designing the whole decoration is also needed to show to clients by making the demos if this will not work then we will make graphics for the designs so that clients can see and let us know if they need any addition in it and we will have book of designs for clients.


3. Procure hardware and software:- This is main part of all events arrangements of hardware objects are crucial such as catering , cutleries , tables and chairs, stage for live concert, decoration and for software objects we will arrange some LEDs in marriage that will show pictures and pre wedding shoot and without music marriage is more like conference hall .


4.Arranging the fashioner designer and make up artist for bride and bridegroom: - As on the day of wedding day both couples have to look attractive as it is special day for them in order to make their day special, we will arrange top class artist for makeup and best designers for clothes.


5. Setting up beverages and bar stations: - in all events our company will arrange two station for the drinks one will be of all drinks that consist of alcohol and other one will be for soft drinks and for all tropical and other juices or for refreshments.


Closeout


The actual purpose of closing part in the project is to check the actual performance with standard set and other thing that can checked and does the whole project completed as it was planned. Even with this step our company can get feedbacks too and tasks can be redesigned as per the staff. At last we will handover the reports related budget closing activities and personal identification to the customers.


1. Audit Procurement :- In this step our company will audit means will check all financial balances and look after all expenses we did and the purpose of doing this is not only to make the trust with clients its good for the company to know that how much we are spending and how we can control that.


2. Document lesson learned: - This document will be proof of feedback from the clients and with this feedback from clients and with this feedback we can find out our negative and positive elements for our project. After this, this document will be available to all team members so that they can refer to it and can do as per the needs.


3. Update files and records :- we can use the feedback of customers as a primary record because the reviews of customers matter a lot and what else we need to do is update all the balance and make the hard and soft copy so that our company can use in future to show our service standard to the customers.


4. Financial Reports closeout: - At last our company will take help of accounting to balance all financial records that will show the actual financial condition of our company and for proof each receipt will be attached with financial records. At last contract will sign the contract and will do payment if any and then its time to close financial accounts.


4. Appendix

Applied Sciences

Architecture and Design

Biology

Business & Finance

Chemistry

Computer Science

Geography

Geology

Education

Engineering

English

Environmental science

Spanish

Government

History

Human Resource Management

Information Systems

Law

Literature

Mathematics

Nursing

Physics

Political Science

Psychology

Reading

Science

Social Science

Home

Blog

Archive

Contact

google+twitterfacebook

Copyright © 2019 HomeworkMarket.com

Homework is Completed By:

Writer Writer Name Amount Client Comments & Rating
Instant Homework Helper

ONLINE

Instant Homework Helper

$36

She helped me in last minute in a very reasonable price. She is a lifesaver, I got A+ grade in my homework, I will surely hire her again for my next assignments, Thumbs Up!

Order & Get This Solution Within 3 Hours in $25/Page

Custom Original Solution And Get A+ Grades

  • 100% Plagiarism Free
  • Proper APA/MLA/Harvard Referencing
  • Delivery in 3 Hours After Placing Order
  • Free Turnitin Report
  • Unlimited Revisions
  • Privacy Guaranteed

Order & Get This Solution Within 6 Hours in $20/Page

Custom Original Solution And Get A+ Grades

  • 100% Plagiarism Free
  • Proper APA/MLA/Harvard Referencing
  • Delivery in 6 Hours After Placing Order
  • Free Turnitin Report
  • Unlimited Revisions
  • Privacy Guaranteed

Order & Get This Solution Within 12 Hours in $15/Page

Custom Original Solution And Get A+ Grades

  • 100% Plagiarism Free
  • Proper APA/MLA/Harvard Referencing
  • Delivery in 12 Hours After Placing Order
  • Free Turnitin Report
  • Unlimited Revisions
  • Privacy Guaranteed

6 writers have sent their proposals to do this homework:

University Coursework Help
Helping Hand
Homework Guru
Top Essay Tutor
Writer Writer Name Offer Chat
University Coursework Help

ONLINE

University Coursework Help

Hi dear, I am ready to do your homework in a reasonable price.

$232 Chat With Writer
Helping Hand

ONLINE

Helping Hand

I am an Academic writer with 10 years of experience. As an Academic writer, my aim is to generate unique content without Plagiarism as per the client’s requirements.

$230 Chat With Writer
Homework Guru

ONLINE

Homework Guru

Hi dear, I am ready to do your homework in a reasonable price and in a timely manner.

$232 Chat With Writer
Top Essay Tutor

ONLINE

Top Essay Tutor

I have more than 12 years of experience in managing online classes, exams, and quizzes on different websites like; Connect, McGraw-Hill, and Blackboard. I always provide a guarantee to my clients for their grades.

$235 Chat With Writer

Let our expert academic writers to help you in achieving a+ grades in your homework, assignment, quiz or exam.

Similar Homework Questions

The management of shatner manufacturing company - Triage assessment form - Why is theoretical orientation important in counseling - Coreldraw for screen printing - Intercultural communication exam - Pop and mentos rocket - Cleveland state university transcripts - Alchemy all metal fabricators - Psy 315 week 1 practice worksheet - Costco business model analysis - Teach writing as a process not product - Nahco3 hcl net ionic equation - Youth allowance not living at home - By the waters of babylon setting - The proverbs tell us how to live life successfully - Medical practice problem - Week 6 Final Project Peer Review - 1.130 kg to lbs - Martina cole's lady killers - Globalization - I need 420 words in international business to answers my questions - Transfer vehicle ownership online wa - Essay - ACCT 221 HW 4 ASSIGNMENT - Wolfram alpha row reduce augmented matrix - Selling agents perform every wholesaling activity except - Match the terms below with their correct definitions - 6061 t6 hardness chart - Text to text connections books examples - What a whimsical glam band plays crossword - Industrial engineering and operations research - Cpu scheduling algorithms questions and answers - Improving mapreduce performance in heterogeneous environments - Cap - Notting hill spike goggles - Are psychopaths more likely to exhibit criminal behavior - Extra linguistic elements of communication - What are exclusive concurrent and residual powers - Deutsch connector how to - Case study myasthenia gravis patient - Clive peeters richmond store - The way to rainy mountain annotations - BUSINESS - Banking and finance course outline - Health policy in the us - Exegetical paper on ephesians 6 10 20 - Psychology - A sickeningly sweet baby boy - Cloward and ohlin 1960 - Does ethical governance guarantee organizational viability - Physical map of russia with key - Cessna 182p v speeds - Bianca villanueva jailbirds - Homework - Soil moisture detector mini project report pdf - Remember the titans julius campbell character analysis - Flextime pros and cons - Ji bi hi fi brighton - Naturally weight loss - Thinking critically about ethical issues 8th edition - Different biomes in canada - Diffusivity equation for radial flow - Http www pbs org wgbh pages frontline storm view - At the airport dialogue - Walmart cvp analysis - Consider the following uneven cash flow stream - How does social media make the world bigger - Making hotplates case study answers - Flour Substitutions With Baking of Cakes - Journal article discussing on electronic innovation and the government - James hay partnership sipp - Fahrenheit 451 green bullet - Coral cay conservation philippines - The great chain of being hamlet - You will be using 8 test tubes for this experiment - Closed loop mrp system - Ol 125 personal development plan swot analysis milestone two - The great person theory - Zappos case study questions and answers - IT incident response - Switched mode power supplies rmit - Resistance and resistivity mastering physics - Hooke's law experiment graph - Jordan university of science and technology dentistry - Internal environment of an organization - Child development theories chart - Practice of leadership lululemon - Dr klinghardt parasite protocol - Nurse logic 2.0 nursing concepts - Metric system lab answer key - Actress fisher whose name is an anagram of lisa - How to save network diagram as pdf - Disaster Management - Prayer of st richard of chichester - Marking Criteria: A marking rubric will be made available in the Moodle site in Week 1. Length: 2000 words (± 10% excluding bibliography) - Environmental science scavenger hunt - It's all about the climb - Coca cola manufacturing process ppt - Asic moneysmart teaching resources - Business intelligence