Loading...

Messages

Proposals

Stuck in your homework and missing deadline?

Get Urgent Help In Your Essays, Assignments, Homeworks, Dissertation, Thesis Or Coursework Writing

100% Plagiarism Free Writing - Free Turnitin Report - Professional And Experienced Writers - 24/7 Online Support

GANTT CAHRT FOR IT PROJECT OF BIG DATA

Category: Computer Sciences Paper Type: Report Writing Reference: APA Words: 450

Grant charts detailing the project activities, personal role and responsibilities must provide to stakeholder

Grant Chart


Phase 2



Project actrivity

Milestone

Resources

Start

Duration

Research by using  Big Data

Big Data and Data Bases

11/9/2019

15

Collection of Information from experts

Experienced Team members

11/24/2019

5

Resources Planning

Paper and Software

11/29/2019

10

Scheduling

Paper and Software

12/9/2019

3

Assigned Duties to the relevant person

Paper and Software

12/12/2019

2


Milestone

Resources

Start

Duration

Phase 2 Designing

 

 

 

Designing Infrastructure of new pages

Hardware and Software

12/14/2019

20

Colour Selection

Hardware and Software

1/3/2020

1

Fonts

Hardware and Software

1/4/2020

1

Images

Hardware and Software

1/5/2020

2

Designing review

Hardware and Software

1/7/2020

3


Milestone

Resources

Start

Duration

Phase 2 Designing

 

 

 

Designing Infrastructure of new pages

Hardware and Software

12/14/2019

20

Colour Selection

Hardware and Software

1/3/2020

1

Fonts

Hardware and Software

1/4/2020

1

Images

Hardware and Software

1/5/2020

2

Designing review

Hardware and Software

1/7/2020

3


Milestone

Resources

Start

Duration

Accuracy Testing

Hardware and Software

1/16/2020

3

Functions

Devices for Testing

1/19/2020

5

User Access Testing

Laptop + mobile phone + tablets to test website responsiveness to users

1/19/2020

1

Review and Feedback

1/20/2020

2

Improvement and removal of errors

Software

1/20/2020

7

 a) Personal role and responsibilities for stakeholder

The project team will discuss all important information about time schedules, selected plans and resources for project deliverables as well as the requirement for funds to complete these requirements. Project subordinate team will have to follow up the designed plan of the project management team including Project Manager, Operation Manager, Projects Resources Manager, and Supervisor of IT team including developers and designers. However, the project team will discuss different information with project stakeholders in accordance with the plan and level of stakeholder’s interest in a particular activity in the group. In the process of communication, the project management team will participate. The project management team will discuss the project plan and schedules related information with the stakeholders particularly project investors in the meeting. Furthermore, the project management team will also present a prototype to the executive managers of the company and representatives of the client organization. The project management team will provide proof and evidence about project schedule baseline will communicating about it in front of client company thus project team would easily influence the decision of client organization and investors in the favor of their organization. All relevant documents will be sent through the use of electronic mails and the physical mail system. In short, all possible resources would be used to keep stakeholders updated with the project.              

Our Top Online Essay Writers.

Discuss your homework for free! Start chat

Top Rated Expert

ONLINE

Top Rated Expert

1869 Orders Completed

ECFX Market

ONLINE

Ecfx Market

63 Orders Completed

Assignments Hut

ONLINE

Assignments Hut

1428 Orders Completed