Articulate and defend
three common techniques used in quantitative risk analysis
There are several common techniques which are used in the
quantitative risk analysis. The first technique that I have found for the
quantitative risk analysis is the brainstorming. The brainstorming technique is
very useful technique in the quantitative risk analysis because the project
manager can identify the significant risks verbally (Al-Samarraie & Hurmuzan, 2017).
The second technique is distribution of risk. It is effective way because by
distributing the risks into the team members as well as with the members of the
staff of different departments can make the team more effective to overcome
from that risk. By distributing, it can analyze as well as calculate the impact
of the risk (Abbassi, Bhandari, Khan, & Chai, 2016).
The third technique is the expert advice that is also quantitative risk
analysis (Purnus & Bodea, 2013).
Most of the times, the development team and the quality management team may
face some kind of issues which cannot be resolved in with the team members as
well as they are unable to understand it. In this case, the project manager
must have to take advice from the seniors or the experts (Adedokun, Ibironke, Dairo, & Aje, 2013)
Risk Response Strategies
Escalate
When you as a project manager recognize the effective
risk as well as seeking that the project manager cannot handle it on his own
risk.
Mitigate
To decrease the effect of the risk within the strategy of
risk response. The mentioned strategy minimizes the harshness of the risk.
Transfer
The transfer strategy is applied when the employees have
lack of skill or the lack of the needed resources to complete the tasks.
Avoid
The manager always try to remove the maximum effects of
the risks. The manager can do this by bring the change into the timetable or in
the complete management of the project.
A Strategy for Project
Risk Register
There
are four things mentioned in the risk register. The first thing is regarding
the project schedule, if it is not defined, then conduct schedule meetings with
staff so that they can get it. The second risk is that risk does not have any
specific purpose, and its solution is to analyze the whole business case to
come up with a considerable purpose. The third and fourth risk is related to
the completion of the project on time with the required quality. It is
important to develop a strategy of measurement and evaluation at each step so
that timely delivery and quality is ensured.
References for project
management
Abbassi, R., Bhandari, J., Khan, F.,
& Chai, V. G. (2016). Developing a quantitative risk-based methodology for
maintenance scheduling using Bayesian network. Chemical Engineering
Transactions , 235-240.
Adedokun, O. A.,
Ibironke, O. T., Dairo, D. O., & Aje, I. O. (2013). Evaluation of
qualitative risk analysis techniques in selected large construction companies
in Nigeria. Journal of Facilities Management , 11 (4).
Al-Samarraie, H., &
Hurmuzan, S. (2017). A Review of Brainstorming Techniques in Higher Education. Thinking
Skills and Creativity , 27.
Purnus, A., & Bodea,
C.-N. (2013). Considerations on Project Quantitative Risk Analysis. Procedia
- Social and Behavioral Sciences , 74, 144-153.