Abstract of
Critical Factors Responsible for Cost and time overruns in Pre-Construction
Planning Phase of Construction Projects in Pakistan
In
Pakistan, the construction industry has not a good reputation for the
completion of its project within cost and time. The cost and time overruns in
the preplanning phase of the construction project have become a major issue,
and the contractors and management of the construction industry are working for
analyzing the elements which are influencing the cost and time overruns of the
construction projects. The major focus of the research study is to analyze the elements influencing Cost and time
overruns in the existing construction Planning Phase of Construction Projects. Numbers of studies are reviewed on this particular
topic, and it has been observed from all these studies that Poor site management, Labor force, Project complexity, and Construction
material Shortage are major factors that can be the reason for the cost and
time overruns of the projects of construction.
The research analysis is conducted by
using the combination of a different approach in which the exploratory research
method is applied by using the theories and studies of the various authors;
meanwhile, the quantitative research methods are applied by using the
questionnaire. 200 questionnaires are distributed to the professionals of the
construction company in Pakistan. Then the data is examined by using the SPSS
(statically packages for social sciences) for measuring the relationship of the
variables and effect of the independent variable on the dependent variable. It
has been evaluated that by one percent change Poor site management, Labor
force, Project complexity, and Construction material Shortage, the cost and
time overruns of the construction project will be changed 90%. It means that
managing the project complexity and poor site management in a good way, and the
time cost overruns can be improved for the construction project. The example of
the orange line train has been discussed to justify this study.
Keywords: Poor site management, Labor force, Project complexity, Construction
material Shortage, cost and time overruns
1. Introduction of Critical Factors Responsible for Cost and time overruns in
Pre-Construction Planning Phase of Construction Projects in Pakistan
One of the major the practitioners
available by the construction industry to get the projected complete within
time. The deadline is too important for any projects either it’s related to the
construction industry or any other industry. The deadline is one important
thing that can enhance the goodwill of the company in front of the clients (Memon, et
al., 2011).
But the construction industry is the rule of the practitioners that the project
must be completed within time according to the required quality and stipulated
budgets. There are several strategies that are commonly using to identify the
factors of the Cost and time overruns in the preplan construction projects for
controlling and managing the projects (Aftab Hameed Memon, 2011). There are several projects of the numerous
countries which are facing the issues related to the problems of the cost and
time overrun, and all of these projects are required very serious attention to
finding out the solutions in order to overcome all of these problems. The
construction industry in the particular regions of the American society is also
facing the problems of the cost and time overrun. Such types of problems and
these issues can be solved out by adopting several strategies and steps. First of all and the most and most initial
step for resolving such an issue is to understand and examine the causes for
cost and time overrun for the construction industry. Therefore, there must be
particular strategies to find out the factors that are affecting the cost and
time overruns of the projects in the construction industry (Hemanta Doloi, 2012).
The construction industry is the most
fragmented and complex industry among the industries of the world that are
scheduled for particular, driven resources. The major criteria of the projects
in the construction industry are the timely perfection of the projects. The
success of any plan depends upon the timely completion of the projects (Ameh, et
al., 2010).
Cost and time overrun are referred to as particular delay away from building
the plan baseline. With respect to managing the projects of construction in
effective manners, the major goal is to reduce the time and cost of these
projects. Therefore the delay of time frequently occurs in the entry stages of
the construction projects and due to which the total duration of the
construction projects can be increased easily. There are very rare projects in
the Pakistani industry that can easily complete according to the particular
deadline (Alinaitwe, et al.,
2013).
For several countries, there are significant impacts of building projects on
the development and growth of this particular country. No doubt, the economic
growth of Pakistan is depended upon the manufacturing industry, but the
construction industry has its own scope in this region. In most of the
construction industries that major stakeholders are the supervision teams,
developers, contractors and designers who play their own role to mane the
projects in effective manners. They struggle to complete their projects with
great success, and the success of these projects depends upon the cost and time
of the projects. There are several
factors in the market that can affect the cost and time overrun of the projects
(Rahman, et al., 2013).
The demanding project is paralleled
with the Malaysian construction industry, which performs the role of the
epicenter of growth. However, it suggests a useful contribution to developing a
nation, but the construction industry is connected with delays in project
delivery. When the contract date is extended, the time overrun takes place to
execute the program to extend to the targeted date for which parties were
agreed (Endut, 2014). The ultimate
objective of the research to recognize the importance of liability overruns the
project. This prevails the significance of the level of the aspects which are
affecting the results. The projects are facing cost and time overrun problem
which is considered as the main issue in the construction problems. This is
also considered as objective to make the economic growth in the industry. There
are many other purposes of the research as;
·
To evaluate the signification of the elements on
the basis of the sector involved in the project in the public and private
sectors.
·
To examines the statistical data about the
project in order to collect the information about the audience with the
presence of the client and contractor.
·
To develop the stage where the responses are
based on a professional role in electrical and mechanical expertise working in
the project management.
·
To develop the industry internationally to
compete with the projects that already exist in the market to filter the
services and products in the industry.
·
The research study is used to reduce the
influence of the aspects of reducing the delay and cost overrun projects in
possible ways
1.1 Research Questions
·
How will the signification of the elements be
evaluated on the basis of the sector involved in the project in the public and
private sector?
·
What is the procedure to examine the statistical
data about the project in order to collect the information about the audience
with the presence of the client and contractor?
2. Literature
Review of Critical Factors Responsible for Cost and time
overruns in Pre-Construction Planning Phase of Construction Projects in
Pakistan
According to Alinatiwe et al. (2013), the main focus of the
conduction of the literature review to discover the effective strategies to
resolve the existing problems of overrun of cost for the senior leadership or
managers as well as to resolve the construction project delay issue due to time
for the managers. So it is a critical global problem which is increasing day by
day (Alinaitwe, et al., 2013).
According to Aljohani et al. (2017), the industries of the
constructing of the project may have a poor reputation to complete their
construction projects in the selected and agreed budget, so the delay in the
project or construction occurs due to their reputation. The cost overrun is
experienced normally by such kind of projects, and of these projects may nine
out of ten. There can be various causes of cost overrun. So, several kinds of
causes have also be determined by the constructors, and the researchers, as
well as some researchers, have also identified the effects of those causes. The
literature regarding the cost overrun in the project of construction is
reviewed by the research article for the identification of the main potential
causes in the different countries. (Aljohani, et al.,
2017).
According to Haseeb et al. (2011), postponed the projects is
the fact, but it is the issue. The issues of delaying in construction projects
occur mostly in the industry of construction of Pakistan. The occurrence of
delays may be critically expensive as mentioned in the study. Furthermore, the
delays in the construction projects are always measured so much expensive for
the involving parties, or the clients or the stakeholders that are related to
the particular construction projects, as well as the delays, are very often.
So, the claims, clash in the expected results, a total dissertation will be
resulted by the delays in often as well as will be complicated for the
feasibility while the delays in the construction projects show the growth for
the sector of the construction (Haseeb, et al., 2011).
Haseeb et al. (2011) stated that it conducts an appraisal on
the time of the project of the construction performance to analyze the causes
of delay. The major goal of conduction the literature is to identify all the
factors regarding the delay and to determine or measure the effects on the
completion of the project of the construction successfully. In simple words,
the researchers have conducted all the research to determine what factors and
causes can take part in the delay in a construction project as well as for the
determination of the effects that how much they can be. In Pakistan, due to
natural disasters such as flood or earth quack or rainy seasons can make a late
in the construction project (Haseeb, et al., 2011).
As stated by Hussain et al. (2017) that the industry of
construction is one of the key areas that provide the facilitation to the
justifiable social as well as the economic development in the area. Many
developed and underdeveloped nations adopt mechanisms of the development of the
community or culture in the running time. It focuses on the quality of life as
well as the economic growth for the enhancement along with the local community
of social welfare. The rural perception of the public of the residents on the
project of construction on delays is reviewed by the research article as well
as the main purpose of the study is to explore the societal and economic
challenges opposing by the residents of any region of Pakistan but especially
in the rural areas. The proposed study has examined influencing factors of the
socio-economic on the basis of 73% valid responses of rural residents (Hussain, et
al., 2017).
As stated by Ramabodu and Verster (2010), The result of the
survey gave different results, which gave a variety of expected or unexpected
factors, which were the main cause of the delay in construction projects and
the effect on the cost in the sense of cost overrun. As the studies describe
that time and cost are the direct proportion, but the manpower and cost are
inversely proportional to each other. For example, if workers' quantity
increased, the productivity will also be increased as well as time consumption
will below. However, on the other hand, if the quantity of the workers will be
increased, the cost will also be increased, but time consumption will be low,
and the chances of delay will be minimized. But the delay is still here because
of the cost overrun (Ramabodu &
Verster, 2010).
As stated by Shah (2016), the
researcher has discovered the most influencing factors that affect the
construction projects as well as the cause of delay and cost overrun to
overcome this kind of issue effectively. There are many influencing factors are
identified such as deficiency of knowledge, reduction of experience, lack of
equipment, lack of manpower, lack of material or any kind of raw material which
is required the completion `of the project, mismanagement in the materials,
costs, time, assigning tasks to the workers as well as the lack of interest to
complete the construction project in the given time. The other reasons are also enlightened which
can take part in the delay of construction projects and cause for the cost
overrun. The other critical factors are as follows; any governmental
legislation, any political or religious actions or pressure, or any other
factors can disturb the productivity and cause for delay or cause for the cost
overrun (Shah, 2016 ).
3. Methodology of Critical Factors
Responsible for Cost and time overruns in Pre-Construction Planning Phase of
Construction Projects in Pakistan
This section of the research study discusses the materials and methods
that are used in this particular study for analyzing the data in effective
manners. This part of the research study explores the details about the methods
that are used for research purposes. It includes the methods that are required
to explore the factors that are affecting the time and cost overrun of the
construction projects. This chapter discussed the research methodology,
research design that is contained in the (Research approach, Research
philosophy, Research methods, and types of data and instruments of the study).
This part of the research study also includes sampling and population. The tools for data analysis are a mandatory
part of this research study. All of these above-given points are explores in
this paper in an effective manner with an expectation that this research
methodology will provide us with the preferred outputs (Larsen, et al., 2015)
The research study is conducted by using the Positivism paradigm
because this is the approach that is used for explaining describing the
strategies of the social studies which rely on particular scientific evidence.
It includes statics and various experiments in order to reveal the true nature
of the hypothesis. In this study, the
scientific and static approach is used to measure the effectiveness of the
several factors that affection on time and cost overruns of the construction
projects. The particular statics will be conducted by using the software of the
static to obtain the specific outcomes of the hypothesis (Memon, et al., 2010). This paradigm is
based upon the idea that is required to gaining a better understanding of the
particular topic as it includes the observations and critical analysis for
examining the various factors that are affecting the time and cost overrun of
the construction project in the Pakistani construction industry. Under this
philosophy, true knowledge is explored according to the senses of experiences (Ali &
Kamaruzzaman, 2010).
The deductive approach is leading towards the development of the
hypothesis that is based on the existing theories. Than research strategies are
designed in this approach for testing the hypothesis. In common words, it is
also known as the reasoning study from the specific to general (Yehiel
Rosenfeld, 2013).
4. Data
Collection Methods of Critical Factors Responsible for Cost and time overruns
in Pre-Construction Planning Phase of Construction Projects in Pakistan
This section of the research study discusses the materials and methods
that are used in this particular study for analyzing the data in effective
manners. This part of the research study explores the details about the methods
that are used for research purposes. It includes the methods that are required
to explore the factors that are influencing the cost and time overruns of the
construction projects. This chapter discussed the research methodology, a
research design that is contained in the (Research approach, Research
philosophy, Research methods, and types of data and instruments of the study).
This part of the research study also includes sampling and population. The tools for data analysis are a mandatory
part of this research study. All of these above-given points are explores in
this paper in an effective manner with an expectation that this research
methodology will provide us with the preferred outputs.
In the quantitative research, method data is collected by using the
questionnaire which was design by analyzing several studies on this particular
topic. This questionnaire is used to measuring factors that are affecting the
time and cost overruns. The questionnaire is used as an instrument because it’s
cheaper and easier ways to collect the data as well as it has required less
time and consider as effective and efficient source to conducting answers to
the question. In the qualitative research, method data is collected by using
the Interviews because it is considered an efficient way to getting the answer
about the specific question and this source is also used to gaining the good
ideas related to the services and products. This source is also useful for
availing of the general ideas related to the factors by which the preplanning
phase of the construction project is affected. The questionnaire is designed by
considering the five-point liker ranging scales from strongly disagree to
strongly agree. It contains the two parts, and the first parts explain the
demographic profile of the respondents and another part of the questionnaire is
explains the construct that is used in this study.
In this research study, the population is the professionals of the 5
famous construction companies in Pakistan. The sample is a subset of the
population. The simple random sampling
method has been employed in this study to get accurate data. In the
quantitative research method, the sampling size consists of the 200respondents
for collecting the data. The entire respondent would be professionals of these
constructions who are engaged in performing their duties as part of their
companies at least for months. During the last 6 months and the sampling frame
is the same for both research methods. The simple random sampling technique is
used in this research method. The data is collected by using personal contact
and email. The questionnaire has been sent out to the mangers of the company
and then personally visited construction companies after taking appointments
from the mangers of the various organizations. To visiting all of this company
the authority/ reference letter has been provided by the university along with
confidentiality statements.
The data is analyzed by using the SPSS for the quantitative research
method. This software is also used to analyzing and interpreting the data which
is generated from the administrated questionnaire. This software is used for
minimizing data manipulation chances. SPSS is a specific software which is used
for generating charts, graph, and tables. It is also used to describing
presenting and exploring the relationships and trends for the numeric data.
After applying this software the data can be summarized in the main data types,
tables and graphs and this research is also involved in the nominal, ordinal,
interval and ratios.
A few of the important ethical concerns are discussed in the research
study. The research paper has various roles for conducting this work. The
research study must be carried out by following the few points as;
·
The
data of the customers must be confidential
·
Nobody
will be distracting due to this study
·
Authority
letter permission letter is necessary for collecting the data.
·
The
role of the adroit must be well defined.
Every respondent who have to
participate in this research he must be agreeing for the following;
·
To
ensure that research is conducted by ethical means.
·
The
participant doesn’t be less than 18 years old.
·
The
answers of the question doesn’t be bias
·
It
doesn’t include the international harm for the project.
·
Withdraw
is free for the participant at any time
The impact of the researcher’s potential on participant and informed
consent are the biggest parts of the ethical consideration for conducting the
research study. For collecting data from primary resources researcher must be
collected, the data most relevant to the aims and objectives of the research
study. In the construction industry, the participant will value the time of
each other, and the concepts of sustainability will be kept in mind.
4.1. Descriptive analysis
Data has been analyzed by using the SPSS software. This software is used
for analyzing the data because it reduces the chances of data manipulation. The
risk of the mistakes and missing data can be minimizing by using this software.
There are two types of analysis are conducted by using the software for both
parts of the questioner. The first part is related to the descriptive analysis
that is conducted for the demographic profile of the respondents. Another one
is the inferential analysis that is conducted to measure the linearity and
colinearity of the dependent variables with independent variables.
The descriptive analysis provides the data for the demographics of the
variables which impact the study that describes what his education was and how
old he or she is. There are four major questions that are analyzed in this
analysis, and these are; age, gender, education level, and designation of the
professionals of the constriction company who are the participants of this
study. The first question is about the ages of the respondents.
|
Age
|
Frequency
|
Percent
|
Valid
Percent
|
Cumulative
Percent
|
Valid
|
Less than 25 years
|
38
|
18.1
|
19.0
|
19.0
|
25-35 years
|
127
|
60.5
|
63.5
|
82.5
|
35-45 years
|
23
|
11.0
|
11.5
|
94.0
|
45 years plus
|
3
|
1.4
|
1.5
|
95.5
|
55 years plus
|
9
|
4.3
|
4.5
|
100.0
|
Total
|
200
|
95.2
|
100.0
|
|
Missing
|
System
|
10
|
4.8
|
|
|
Total
|
210
|
100.0
|
|
|
4.2. Data reliability & validity
Construct
|
Valid No
|
Item in each F.V
|
Chronbach’s Alpha
|
Poor site management
|
200
|
4
|
0.748
|
`Labor force
|
200
|
4
|
.861
|
Project complexity
|
200
|
4
|
.627
|
Construction material Shortage
|
200
|
4
|
.805
|
Time and Cost overrun
|
200
|
4
|
.718
|
4.2.1. Data Interpretation
The data reliability is analyzed by the user test of the Cronbach's
Alpha. Questions for each variable can be analyzed by using the test, and this
test is implementing for evaluating the reliability and validity of the data.
This research study is conducted by using the three main scales variables from
which four are the independent, and one is the dependent, Time and Cost overrun
is taken as the independent variable in this research study, and the Cronbach
alpha values for this variable are.718 respectively.
The value of the Cronbach alpha for the Construction material Shortage is
.805. These values show that the data is reliable for all variables because the
value of the Chronbach alpha is greater than .7 for all variables. The value of
the Cronbach alpha for the Project complexity is .627. These values show that
the data is reliable for all variables because the value of the Chronbach alpha
is less than .7 for all variables. The value of the Cronbach alpha for the
Labor force is .861. These values show that the data is reliable for all
variables because the value of the Chronbach alpha is greater than .7 for all
variables. The value of the Cronbach alpha for Poor site management is .748.
These values show that the data is reliable for all variables because the value
of the Chronbach alpha is greater than .7 for all variables
4.2.2. Data Correlation
Correlations of
Critical Factors Responsible for Cost and time overruns in Pre-Construction
Planning Phase of Construction Projects in Pakistan
|
|
Poor site management
|
Labor force
|
Project complexity
|
Construction material Shortage
|
Time
and Cost overrun
|
Poor site management
|
Pearson Correlation
|
1
|
.795**
|
.777**
|
.899**
|
.625**
|
Sig. (2-tailed)
|
|
.000
|
.000
|
.000
|
.000
|
N
|
200
|
200
|
200
|
200
|
200
|
Labor force
|
Pearson Correlation
|
.795**
|
1
|
.680**
|
.852**
|
.777**
|
Sig. (2-tailed)
|
.000
|
|
.000
|
.000
|
.000
|
N
|
200
|
200
|
200
|
200
|
200
|
Project complexity
|
Pearson Correlation
|
.777**
|
.680**
|
1
|
.646**
|
.870**
|
Sig. (2-tailed)
|
.000
|
.000
|
|
.000
|
.000
|
N
|
200
|
200
|
200
|
200
|
200
|
Construction material Shortage
|
Pearson Correlation
|
.899**
|
.852**
|
.646**
|
1
|
.622**
|
Sig. (2-tailed)
|
.000
|
.000
|
.000
|
|
.000
|
N
|
200
|
200
|
200
|
200
|
200
|
Time and Cost overrun
|
Pearson Correlation
|
.625**
|
.777**
|
.870**
|
.622**
|
1
|
Sig. (2-tailed)
|
.000
|
.000
|
.000
|
.000
|
|
N
|
200
|
200
|
200
|
200
|
200
|
**. Correlation is significant at the
0.01 level (2-tailed).
|
The correlation analysis shows the
relationship of the variable either these variables have a relationship with
each other. Thus, the Pearson correlation statistic is calculated 0.625** for
Time and Cost overrun which means the relationship between effective Time and Cost overrun and
several other variables is good and satisfactory. The Pearson correlation for
the Labor force is .795 which means the relationship of the Labor force and
Time and Cost overrun is quite good and it also shows the Labor force is .795
percent correlated with the Time and Cost overrun. The correlation value of the
Project complexity is .777 which shows the good relationship of the variables.
The significant level for all variables is 0.89 and 1.00 respectively which
shows these all variables have a significant positive relationship with each
other. Because the correlation is significant at the 0.01 level and the values
of significant correlation for all variable is less than 0.01 which shows these
all variables have a positive significant relationship with the other
variables.
Coefficients
|
Model
|
Un
standardized Coefficients
|
Standardized Coefficients
|
t
|
Sig.
|
B
|
Std. Error
|
Beta
|
1
|
(Constant)
|
.188
|
.105
|
|
1.792
|
.075
|
Poor site management
|
.611
|
.058
|
-.669
|
-10.591
|
.000
|
Labor force
|
.506
|
.042
|
.544
|
12.040
|
.000
|
Project complexity
|
.913
|
.038
|
.909
|
23.927
|
.000
|
Construction
material Shortage
|
.150
|
.055
|
.172
|
2.736
|
.007
|
a. Dependent Variable: Time and Cost
overrun
|
Model
Summary of
Critical Factors Responsible for Cost and time overruns in Pre-Construction
Planning Phase of Construction Projects in Pakistan
|
Model
|
R
|
R Square
|
Adjusted R Square
|
Std. The error of the Estimate
|
1
|
.950a
|
.903
|
.901
|
.18072
|
a. Predictors: (Constant), Construction
material shortage, Project complexity, Labor force, Poor site management
|
4.3. Qualitative Analysis of Critical Factors Responsible for Cost and time overruns in
Pre-Construction Planning Phase of Construction Projects in Pakistan
According to the qualitative analysis, the data has been analyzed by
using the real based example of the project of the Orange Line train. The
orange line train which is one the largest project of the country has been
delayed. It has been failed to compete with its given time and according to its
deadline in the year 2017. Therefore due to its particular delays, the cost of
the project is increased. Due to the delay in this project, the residents also
remained affected. For the project of the orange line train, the estimated
budget was set out or formally launched the RS 164 billion in 2015. This
project was proved as the criticism for its civil society and it also needs the
appreciation according to its circles in initiating stages of the project.
There are several people who thought the cause of the time cost overruns of the
project of the Orange Line train is the political instability but the most
accurate truth is that this project is facing the time and cost overruns but
due to the shortage of construction materials and the poor site management. As the
kit has been stated in the literature review by several studies the major
reason for the time overruns is the cost overruns and the cost runs are occur
in the construction project due to the complexity of the project. As, Orange
Line train is contained on they several complexities particularly the
disturbance of the roads, personal property of the people. There were several
points of the Orange Line train that are passing from the residential areas and
to clear it is too tough. Due to these all complexities the cost of the project
was rapidly increased because for acquiring the place of the houses of people
it is necessary to provide them accurate alternate. The increase in the cost of
these projects is discussed in the Appendix in video (Dunya news tv, 2017). The below-given link can be view as reference
5. Conclusion of
Critical Factors Responsible for Cost and time overruns in Pre-Construction
Planning Phase of Construction Projects in Pakistan
It has been analyzed in several studies that the project of
the construction around the world has a record of very poor performance in
order to be completed within time, quality objective and cost. In this study,
the factors are analyzed, which are influencing the preplanning phase projects
of the construction. The factors are also analyzed that are affecting the cost
and time overruns of the construction projects. There are several tests that
are employed to ascertain the factors which are contributed immensely in order
in late completion of plans. The significant element of the research are
observed in this study by analyzing the literature of the several authors on
this particular topic, and theses factor are; Poor site management, Labor
force, Project complexity, and deficiency of the material. The linear
regression is also applied to measure the effects of variables. It has been
measured that the value if the adjusted R square is 0.901 it means due to the 1
percent change in independent variables, the dependent variable will be
changing 90%. The particular statics will be conducted by using the software of
the static to obtain the specific outcomes of the hypothesis
In this research study, the population is the professionals
of the 5 famous construction companies in Pakistan. The sample is a subset of
the population. The simple random
sampling method has been employed in this study to get accurate data. In the
quantitative research method, the sampling size consists of the 200respondents
for collecting the data.
The risk of the mistakes and missing data can be minimizing
by using this software. There are two types of analysis are conducted by using
the software for both parts of the questioner. The first part is related to the
descriptive analysis that is conducted for the demographic profile of the
respondents. Another one is the inferential analysis that is conducted to
measure the linearity and colinearity of the dependent variables with
independent variables
The data reliability is analyzed by the user test of the Cronbach's
Alpha. Questions for each variable can be analyzed by using the test, and this test
is implementing for evaluating the reliability and validity of the data. This
research study is conducted by using the three main scales variables from which
four are the independent, and one is the dependent, Time and Cost overrun is
taken as the independent variable in this research study, and the Cronbach
alpha values for this variable are.718 respectively.
Therefore due to its particular delays, the cost of the
project is increased. Due to the delay in this project, the residents also
remained affected. For the project of the orange line train, the estimated
budget was set out or formally launched the RS 164 billion in 2015
5.1. Limitations of Critical Factors
Responsible for Cost and time overruns in Pre-Construction Planning Phase of Construction
Projects in Pakistan
Although this research will be
carefully conducted, Researchers are still aware of its limitations and
shortcomings. This research is conducted only in Pakistan. The data is
collected only from the employees of the construction companies. For this
research, only 200 questionnaires are distributed or send out to the
participants of the research. There is a specification of time for this
research. The research is conducted through a mixed-method and deductive
approach. The qualitative research method is just used to observing the
theories of several authors. The research study is limited to the construction
companies and projects of Pakistan, and it will be helpful for the betterment
in the construction companies.
References of Critical Factors Responsible for
Cost and time overruns in Pre-Construction Planning Phase of Construction
Projects in Pakistan
ADUGNA, N. T., 2015. A study of
causes of delay and cost overrun inoffice construction projects in the
eThekwini Municipal Area, South Africa. Durban University of Technology,
Durban, South Africa.
Aftab Hameed Memon, I. a. R. M. R. a.
A. A. A. A., 2011. Time Overrun in Construction Projects from the Perspective
of Project Management Consultant (PMC. Journal of Surveying, Construction &
Property , 2(1).
Ali, A. S. & Kamaruzzaman, S. N.,
2010. Cost performance for building construction projects in Klang Valley.
Journal of Building Performance .
Alinaitwe, H., Apolot, R. &
Tindiwensi, D., 2013. Investigation into the causes of delays and cost overruns
in Uganda's public sector construction projects. Journal of Construction in
Developing Countries .
Aljohani, A., Ahiaga-Dagbui, D. &
Moore, D., 2017. Construction Projects Cost Overrun: What Does the Literature
Tell Us?. International Journal of Innovation, Management and Technology,
Volume 8, pp. 137-143.
Al-Keim, A., 2017. Strategies to
Reduce Cost Overruns and Schedule Delays in Construction Projects. Walden
University.
Ameh, O. J., Soyingbe, A. A. &
Odusami, K. T., 2010. Significant factors causing cost overruns in
telecommunication projects in Nigeria. Journal of Construction in Developing
Countries.
Dunya news tv, 2017. Year 2017:
Delays in the Orange Line train project. [Online]
Available at:
http://dunyanews.tv/en/Pakistan/421236-Year-2017-Delays-in-the-Orange-Line-train-project-
Endut, Z. S. a. I. R., 2014. Factors
contributing to projecttime and hence cost overrun in theMalaysian construction
industry. Journal of Financial Management ofProperty and Construction, 19(21),
pp. 55-75.
Haseeb, M. et al., 2011. PROBLEMS OF
PROJECTS AND EFFECTS OF DELAYS IN THE CONSTRUCTION INDUSTRY OF PAKISTAN.
Australian Journal of Business and Management Research, Volume 1, pp. 41-50.
Hemanta Doloi, 2012. Cost overruns
and failure in project management: Understanding the roles of key stakeholders
in construction projects.. Journal of construction engineering and management.
Hussain, S., Zhu, F., Al, Z. &
Xu, X., 2017. Rural Residents’ Perception of Construction Project Delays in
Pakistan. Rural Residents’ Perception of Construction Project Delays in
Pakistan, pp. 2-16.
Larsen, J. K., Shen, G. Q., Lindhard,
S. M. & Brunoe, T. D., 2015. Factors affecting schedule delay, cost
overrun, and quality level in public construction projects. Journal of
Management in Engineering.
Memon, A. H., Rahman, I. A.,
Abdullah, M. R. & Azis, A. A. A., 2010. Factors affecting construction cost
in Mara large construction project: perspective of project management
consultant. International Journal of Sustainable Construction Engineering and
Technology.
Memon, A. H., Rahman, I. A. &
Azis, A. A. A., 2011. Preliminary study on causative factors leading to
construction. s.l.:s.n.
Rahman, I. A., Memon, A. H. &
Karim, A. T. A., 2013. Significant factors causing cost overruns in large
construction projects in Malaysia. Journal of Applied Sciences .
Ramabodu, M. & Verster, J., 2010.
Factors Contributing to Cost Overruns of Construction Projects. Factors
contributing to cost overruns of construction projects, pp. 131-143.
Shah, R. K., 2016 . AN EXPLORATION OF
CAUSES FOR DELAY AND COST OVERRUNS IN CONSTRUCTION PROJECTS: CASE STUDY OF
AUSTRALIA, MALAYSIA &GHANA. Journal of Advanced College of Engineering and
Management, 2(1).
Ubani, E. C. O. K. A. &. E. S.
C., 2013. Analysis of factors influencing time and cost overruns on
construction projects in South Eastern Nigeria. International Journal of
Management Sciences and Business Research, 2(2).
Yehiel Rosenfeld, 2013. Root-cause
analysis of construction-cost overruns. Journal of Construction Engineering and
Management.