Procurement
Management Plan for “Destination: Australia”
1.
Planning
Procurement
1.1. Main policies and
procedures
There are
enormous policies and procedures in any organization that can be utilized for
planning the procurement. All of these policies are differs according to the
nature of the business. But there are a few common policies that can be
utilized in any organization.
Hiring
Procedures and policies
It includes who
the staff, as well as personnel, will be hired in an organization in order to
work in the company.
Selling
and purchasing of policies:
It includes the
suppliers to whom the company will buy as well as the particular policies
that are followed by several other companies.
Polices
of rewards and Benefits
This is one of
the most important and good strategies that is adopted by the NAA (National
Archives of Australia) in order to encourage and motivated their staff and
make them realize it.
Feedback
and claim policies
This policy is
related to the procedure in which the claim filed by company ‘clients, and it
also includes the reaction of the company against this claim.
|
1.2.Identify the policy gaps
and suggest an action required to fill the gaps
There are two
major and most important gaps that have been occurred in these policies. The
first one is related to that one action is done and there are no particular consequences
in which the policies can regulate these procedures. The outcomes must be evaluated
by the company when it occurs. The company must define the policy in order to
make sure that this action or mistake will not happen again. It includes the
particular procedure that requires for making this policy that how this
policy will be applied and it mandatory in order to get established as well
as for the standard outcome.
Another gap is
related to; when any kinds of procedures and policies will disagree within
another company that is working in the same line of products and services. If
this will occurs, there are two enormous policies that must be redefined and evaluated in
order to establish in that company that was going to be modified and
preserved.
|
1.3.Method to plan when to
acquire the required products and services
When the
procedures come at for acquiring the services and products inside the company;
It is mandatory to make the request to attain such services or products. The
entire specifications must be presented in the detailed. Hence; it can be
easy to find out the correct service provider for obtaining and negotiation in the various processes.
In charge of
purchasing the services for these particular projects of the website, the
person must do whatever that is required for attaining the particular item
for website maintenance on the particular time and date that is required.
Hence; it depends on that particular person for managing and negotiating the
logistics.
It doesn’t
matter the arrival of the services is early or late when the product does not
come on time. It can be sum up that the key consequences are related to the
money only. The cost differs according to the various perspectives such as
late delivery cost storage cost and it also depends upon the nature of the
services that are acquired by a particular person or company. The reputation and
loss of the contract are not
taking in the consideration for these particular procedures.
|
2.
Market
Analysis
2.1.Delegate responsibility for
conducting a market analysis
2.1.1 Sourced products or
services
The companies
are seeking for the new suppliers at any time in order to develop new
services as well as reduce their cost. For this particular real case in which
I am involved; the company is seeking for delivering services for web
development as they have particular consignments for this and it is not enough
in order to manage the particular demands. The services of the web developments
depend upon the human skill that’s it has not potentially go off as well as
the logistics in order to acquire it.
|
2.1.2
How
well did the team member conduct the supplier analysis? Mention the gaps if
any?
The production
factory’s specifications that the production factory released were clear and
complete, the team member in charge of providing this specific item had
everything under the request, and from the exact quantity to the accurate
quality of the Web development services to be had. After looking for the
right supplier, the person found one and the delivery was perfect, thanks to
all the specifications. Not particular gaps have been observed in the
supplier analysis of the “Destination: Australia.”
Online
server
Apache
server
Tools;
Editors/ Compilers; Programming languages, MVC,
Web
services; Google APIs,
|
2.1.3. How could the
project team member have performed the analysis better?
There
are the numbers of the suppliers that are seeking for providing the services
in the categories of the raw materials for developing and maintaining the
website. It includes Online server that is required to hosting the domain of
the website and in order to make the web site live. Apache Server; this is
the servers that are required during the maintenance of the website. But the project team member will
perform the analysis better in effective manners by selecting the most cost-effective
suppliers for his company that can provide the services to their company in
effective manners.
Tools; Editors/ Compilers; Programming
languages, MVC,
Web services; Google APIs,
|
3.
Planning
to procure
3.1
Describe the methods adopted to procure the products and services for a
project. List the documents that were prepared to distribute to prospective
sellers.
As it has been
discussed earlier; there must procure various services for the necessity of
the “Destination: Australia” project. The buying request must be filled by
the department inside the company for the requirements of the new services.
It must be following the correct procedure and policies attached to obtaining
a new service. After filling that particular documents, the person who is
accountable to seeks for the suppliers; who has the responsibility to look
for the correct. He is also known as the best suppliers who can easily mange’s
the demands of the services in effective manners. If any kinds of problems
will occur with that particular new services the company can refer to the
purchase document to see who commit a mistake.
|
3.2
Discuss the type and the need for the contract selected to procure the product
or service for the project.
The particular
contract that used for procuring the new services is referred to as one of the
essential documents as the details of the requirements is also attached to
the contract. In this contract, all the selected suppliers are narrow down
that is applied for tender. Such
contract is considered as the legitimate document which will ensure the
services and products that is beings acquired correctly. This document is
part of a purchasing process that all companies must have. During the
purchasing process, after the right provider is found, a contract with the
supplier must be signed. This contract will specify the logistics and terms
and conditions that must be agreed upon. If anything goes wrong with the
delivery or the web development services itself the contract is the document,
the companies must refer to identify the fault.
|
4.
Contract
Administration Planning4.1.Explain the steps
involved in the process of planning the contract administration process.
The steps
involved in the contract administration planning must be a person working
with the human resources department. This will ensure that the process is
aligned with the administration process. Like several other processes,
especially when it comes to administration, all the angles and alternatives
must be evaluated in order to guarantee that the process flows and there are
no gaps or loops like the ones mentioned before. If it is related to the administration
process in the contract, all terms and agreements must be discussed and
agreed before signing the contract. The entire parties are involved must
follow the contract to the letter. This will assure that future negotiations
with providers are conducted in a professional and easy way.
|
4.2.Discuss the key
performance indicators developed by the project team for the contract. Also,
explain the
process involved in determining the contractor’s performance throughout the project. List the types of reports required in
administering the contract.
The key
performance indicators involved in a contract are basically if the contract
has been respected and all the terms accomplished. After the product/process
has been delivered, it is necessary to evaluate if the contract needs to be
resigned or changed. This will help future negotiations and help determine if
it’s necessary to find another supplier or contract. The reports needed for
administrating the contract are all the reports that might emerge in the
process, the reports that say if the contractor is doing a good job and if
the KPI of the project is going well.
|
5.
Establishing
procurement processes
5.1.What
documented procedures do you normally follow in your organisation for:
There
are the various processes and documents that are particularly utilized in the organization
in order to offer the services of the web development and these processes are
included as;
Going
to the market with a request for tender:
·
The document that specifies the
requirements for the tender and the expected deliveries.
·
Procedure for delivering the requested service.
·
In some cases, the budget assigned for
obtaining the product or service (this will narrow down the companies
applying to provide)
|
Evaluating
responses:
·
Offer letters from possible suppliers.
·
Cost analysis from the purchasing
department.
·
An approval document from the branch
within the company requesting the product/service.
·
Terms and conditions on the contracts
offered.
|
Selecting
preferred contractors:
·
Possible contracts from all suppliers
interested in the tender.
·
An approval document from the branch
within the company saying that the contracts that had been selected are aligned
with the requested product/service.
·
A letter with the discarded contractors
and the reason why they had been put aside.
|
Developing
key performance indicators for a contract:
·
Work in progress reports. In this case,
evaluating a contract.
·
KPIs were specifying how well the
contract is taking care. This will help evaluate at the end of the contract
if it’s necessary to find a new supplier or it it’s the case renegotiate the
contract with new terms.
|
Monitoring
contractor performance:
Work
in progress reports (aligned with purchases department)
|
5.2.What will be the
consequences (in relation to the ease) if your organisation does not have these
documents?
·
There will be the various consequences
that can occur in an organization in the case if the organization does not have these documents and these can
be; there will not be a responsible party if something goes wrong. This will
cost money and of course, will be a negative situation at the time of looking
for new clients/suppliers.
·
If something goes wrong, there will be
money implied, and without a responsible party and documents to refer to the
cost of these mistakes will be absorbed by the organization. Every action,
procedure, policy, contract inside the organization must have a document that
backs up the decision that has been made.
·
If there are not KPIs for these, there
will be no justifications for the organization to evaluate the performance of
the evaluated situation. Therefore, the company will have two options to
carry on with the actual contract/procedure or discard that one and look for
another one, with the risk of making a bad decision.
·
This is the main reason why KPIs and
contracts are so important in a company, and they basically help you make the
correct decision and save you money or help you get more.
|
6.
Evaluation
Criteria
Name of the product acquired
|
Description of the product
|
Web
development services
|
The
contract for the development of the web site for a particular site of the
“Destination: Australia” It needs particular redeveloping services for this
website along with its maintenance and development.
|
EVALUATION OF SUCCESSFUL CONTRACTOR:
·
Bidder must submit proof of valid
accreditation certification with the following approved Authorities; NAA
(National Archives of Australia ), various other legal authority.
·
Bidder must submit a company profile
showing the number of years’ experience in the web development services along
with the three written contactable References
·
Provide a list of team members that will
be assigned to this contract, showing their reporting lines, structure or organogram
·
Service Provider must confirm that they
will be able to start work on the contract commencement date
|
Four
points mentioned before must be fulfilled
Developed by:
Purchases Manager
Human Resources
|
Documents referred
Code of conduct
Cleaning procedures and standards
Risk matrix
|
If
doubts are going to emerge than refer it to the human resource department
|
7.
Tender
selection process
Interviewing
the senior Project manager
What
were the key stages or milestones and the timeframe for the tender? Who was
on the tender selection panel and why?
When entering a tender is important to
define the stages of the tender. There must be an opening date and a closing
date. All interested suppliers must apply during this stage (no exceptions
granted). After the applying phase, the evaluation takes place, in this stage
all the key factors or the contract must be evaluated to see if the applying
suppliers can cope with the process/product that is required. A process of
narrowing down proceeds until the one contractor is selected. A renegotiation
of the contract can be held to fit external points.
|
What
documentation was involved in the process from the organisation seeking
tenders and the tenderers?
All documents that can help narrow down
the applicants must be provided. Obviously, a contract where it states what
product/service is going to be delivered and how is the main document in the
tender. However, there must be an opening field to submit referral letters
from previous clients. With these referral letters, HR can contact to seek
feedback on the supplier.
|
What
are the important things to consider while running a competitive tender?
Mention the pitfalls that needed to be avoided.
·
When running a competitive tender, the
most important thing to consider is to let the applicants know what exactly
is what the company needs, what and how it’s needed.
·
An agreed starting offer (moneywise)
must be provided by the applicant with the option of renegotiating if it
passes to the second round of the tender after most of the applicants had
been narrowed down.
·
The most important pitfall to avoid is
when the specification lacks information and its open to the supplier’s side.
This will evolve to a more difficult selection process and waste of time
during the process
|
8.
Contracts
8.1.Outline the important
characteristics of a good contract and mention the assistance required when
writing contracts. What are the common
problems that occur during the contract writing process?
A good contract is the one that doesn’t
leave anything for granted or aside. To cope with a good contract, we must be
sure that we make ourselves clear on what, when and how we need the
product/service. To do this, we must take into consideration:
·
Clarity: The
provisions of the document are clear to the reader.
·
Efficiency: The
text is “long enough and not one word longer.
·
Simplicity: The
text is simple to read and comprehend.
·
Resonance: The
text strikes a balance between being too pompous and too casual; it resonates
with its intended audience.
If
some of these variables are not well done, problems and misunderstood might
come up following to cancellations and disagreements; even loopholes and
gaps.
|
8.2.Methods to monitors the
contractor performance
There
must be particular methods that must employ in order to measure the performance
of contractors. It includes the numerous strategies that can be utilized as a scale
set for measuring the performances of the organization. It includes the scales
and level of work that is holding by the contractors that are engaged in
working in the various phases of the projects of the web development of the
“Destination: Australia”.
Dispute
with the contractor
Reason
for the dispute and the person involved:
If the required standards of the clients
will not fulfil according to his particular requirements, then it can be the
cause of the disputes in the organization. When heading to the contractor and
asking the reason why the work was not done as it was required so. He stated
the timeframe assigned to work on this site was not enough. Therefore, the development
process becomes slower.
|
Policies
and procedures available for assistance in handling the dispute:
The particular points of the work in
milestone have been referred by the contractors in order to work by
discussing with clients. The work must be according to the requirements that
are given by the client. It also says that if the supplier doesn’t cope with
the standard, the time involved in the development will not be paid, as the
contractor might need to use resources to improve this work in effective
manners.
|
Actions are taken
by the project team members
The particular points that are linked
with the procedures of the milestone that has become one of the most
important issues for this work.
|
Outcome
The
supplier agreed on the actions taken. He implied that after the conclusion of
the project, the time gap must be renegotiated
|
9.
Reviewing
Contracting and procurement
9.1.Describe the methods used
to review the contracting and procurement activities (example procurement
audits, review meetings, project team interviews…etc.). What was the type of
the project?
The best way to
review contracts is by determining if the requirements and standards
specified in the contract. The first breaking point must be if the supplier
copes with all the requirements of course. The second point to evaluate is
the KPIs established for the contract went well. To do this, working progress
reports can be referred to. If the company and the supplier does not have KPIs
that are measuring the contract, meeting reviews, external comments and
interviews can be done to determine the efficiency of the contract
|
9.2.What issues or
difficulties were identified in the review process? How satisfactory was the….?
One
of the issues and difficulties identified in the review process was that
there were not ways of measuring the performance of the contract. The
supplier and the contractor did not agree on KPIs on how to measure the
contract. In this case, the supplier only must fulfil the requirements
necessary to cope with the standard. If this is the case, the contractor will
not have a starting point to see if it’s convenient to carry on with the same
contract / renegotiate the current contract or change the supplier and start
a tender process.
|
Recommendations
made for future contracting
·
Always make sure to leave space for
renegotiation.
·
Define a standard if it’s a process that
must be done.
·
Define a way to measure the contract
(besides standards). Like KPIs
·
Make sure that everything is clear and
outline in the contract before its signed
·
Solve all the questions and doubts that
come up when evaluating the possible contracts
·
Make sure to follow the points in
question 8.1 to make it a good contract
|