Report on PROJECT MANAGEMENT PLAN of King Khalid Hospital in Saudi Arabia

Category: Project Management Paper Type: Report Writing Reference: APA Words: 7300

 

Project Title

 

Project ID

 

Document ID

 

Version

 

Date

 

Project Manager

Name/functional area

Sponsor

Name/functional area


Document History

Revision Date

Revision

Version

Summary of Changes

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Approvals

Name

Position

Signature

Date

 

 

 

 

 

 

 

 

 

 

 

 


Distribution

Name

Title

Date of Issue

Version

 

 

 

 

 

 

 

 

 

Table of Contents

1.0  Introduction. 3

1.1. About this Document 3

1.2. Background – Problem / Opportunity Statement 3

2.0. Business Rationale. 3

2.1. Project Benefits & KPIs. 3

2.2. Strategic Alignment 3

3.0. Project Scope. 4

3.1. Deliverables. 4

3.2. Work Breakdown Structure. 4

3.3. Out of Scope. 4

3.4. Project Constraints. 4

3.5. Project Assumptions. 4

4.0. Project Time Management 4

4.1. Project Time Management - Approach. 4

4.2. Schedule. 4

5.0. Project Cost Management 5

5.1. Project Cost Management - Approach. 5

5.2. Budget 5

6.0 Project Human Resource Management 5

6.1. Project Human Resource Management - Approach. 5

6.2. Project Team Members. 5

6.3. Responsibility Assignment Matrix. 5

7.0. Project Communications Management 5

7.1. Project Communication Management - Approach. 5

7.2 Communication Plan. 5

8.0. Stakeholder Management 5

8.1. Stakeholder Management Plan. 5

9.0. Project Risk Management 6

9.1. Project Risk Management - Approach. 6

9.2. Risk Register 6

10.0. Project Quality Management 6

10.1. Project Quality Management - Approach. 6

10.2. Quality Plan. 6

11.0 Project Procurement Management 6

11.1. Project Procurement Management - Approach. 6

12.0 Project Control 6

12.1. Progress Reporting. 6

12.2.  Change Management 6

12.3. Project Completion Review. 6

APPENDIX A – Schedule. 7

APPENDIX B – Project Budget 8

APPENDIX C – Responsibility Assignment Matrix. 9

APPENDIX D – Communication Plan. 11

APPENDIX E – Stakeholder Management Plan. 12

APPENDIX F – Risk Register 13

APPENDIX G – Quality Register

1.0 Introduction of King Khalid Hospital in Saudi Arabia

The introduction section contains information regarding the project management plan document and the main areas of information covered in this document. Moreover, it throws light on the background, identified problem, and opportunities for King Khalid Hospital (KKH) by the development of statements relevant to each of these information areas.

1.1. About this Document of King Khalid Hospital in Saudi Arabia     

The document contains details about the managerial system and process of a project “The use of OPD refurbishment to increase the number of clinics at King Khalid Hospital in Tabuk, Saudi Arabia”. In this document, all information is shared which is required by the management to execute this project plan in an effective manner. In general, the document contains information about project execution process, key performance indicators, deliverables, and stakeholders’ interest in the project. Moreover, the document also entails information about project resources such as human resources, time resources, financial resources, and other operational resources. Consequently, plans include the following

·         Description of the project management process and activities to be done in the project by the project personal.

·         Project management plans

 

The operational document named “Project Management Plan” is consisting of plans and policies regarding project management and accomplishment. The project management plan will be specifically developed, handled, maintain, and implemented by the project management team such as Project Manager and Project Team to ensure supporting the delivery of the project deliverable.

Reflecting on the project management plan, it expands on the Project Proposal and Project Charter with some justifiable modifications and enrichment. Entailing information of Project Charter, it will explain how project objectives developed in project Charter will be attained without losing the interest of major stakeholders and budgetary limitations.   

1.2. Background – Problem / Opportunity Statement of King Khalid Hospital in Saudi Arabia

Background of King Khalid Hospital in Saudi Arabia

King Khalid Hospital was established in the Tabuk, a city of Saudi Arabia. Geographically hospital is located in the north west side of Saudi Arabia country. At the time of KKH hospital establishment, Tabuk had very limited healthcare facilities available to the market. The hospital was providing initial too extreme services to the patient. The patients were mostly local. And the number of patients was round about 1 million. Because the number of patients was more than the designed capacity of the hospital. The need for an additional ``Out Patient Department" became a necessity for the authorities of the hospital to build another new Outpatient Department. But the hospital does not have enough funds from the central government and all other authorities to build another department for outpatients. After all of this, the management of the hospital found another solution to this problem. The management finds a solution to refurbish the existing rooms and the spare part of the hospitals building. The idea was officially approved with the purpose of the hospital´s betterment. The spare part of the building and unused rooms will be reconstructed and will be used  as the outpatient department of the hospital

Problem Statement of King Khalid Hospital in Saudi Arabia

King Khalid Hospital (KKH) has currently challenged for space management. All available rooms for the OPD clinics are the located in the best location of hospital however they lack the availability of proper space. Available rooms for patients are very limited in number therefore hospital face conflicts during long term patient's stay in the hospital. Particularly, in case of disease outbreak in the country, the hospital will face challenges for space which will create a worse situation for emergency patients. Although, in such situation, King Khalid Hospital (KKH) will lose its market reputation as the advanced hospital of the Tabuk City. Additionally, space is not the only issue of King Khalid Hospital (KKH). Hospital is also having to challenge for the management of equipment and specific instrumentation. Space, equipment, and specific instruments availability are essential to ensure the promotion of efficiency and effectiveness in the operations of King Khalid Hospital (KKH) as it would enable them to meet pre-defined corporate goals and objectives of the hospital without product penetration strategy. Following the research of operational performance in King Khalid Hospital (KKH) and availability of resources, it concluded that the hospital has mainly 3 major problems that are required to be addressed by this project. The identified three problems of King Khalid Hospital (KKH) are enlisted below:

i)                    Patients have to wait for a longer time (sometimes a few hours) to get outpatient treatment in the outdoor department or clinics of King Khalid Hospital (KKH). Such a situation has raised questions on the performance of King Khalid Hospital (KKH) in the city. Apart from reputation, it also makes healthcare treatment and services difficult to attain for the patients suffering from several diseases. Thus, taking the concern of patients is essential for the King Khalid Hospital (KKH) to ensure easy and quick availability of healthcare treatment in the hospital for the patients visiting for a check-up and regular treatment,

ii)                  Healthcare services are having a delay in the delivery because of delay in the provision of outpatient services before the delivery of actual treatment services.

iii)                The third major problem of King Khalid Hospital (KKH) is not concerned with patients, it relates to the business performance and success in the competitive market. Apparently, King Khalid Hospital (KKH) is alleged to serve the community of Tabuk with the best possible healthcare services however it had some business objectives and interest as well. For instance, space issues and delay in services are reducing the competitive strength of the hospital. Although, such challenges create tensions and cramped conditions for the staff working in the clinics of King Khalid Hospital (KKH). Tension and work stress can influence performance outcomes and satisfaction of employees which is a highly undesirable fact.

Summarizing these concerning problems for King Khalid Hospital (KKH) the following statement will be perceived as problem statement for this project.

“The current level of facilities available in the OPD of the hospital is not sufficient to provide the necessary level of high-quality services in a timely and effective manner”

Opportunity Statement of King Khalid Hospital in Saudi Arabia

The project “The use of OPD refurbishment to increase the number of clinics at King Khalid Hospital in Tabuk, Saudi Arabia” is aimed to resolve issues and problems of hospitals in the selected regions of Saudi Arabia. Increasing population and limited health facilities in Saudi Arabia are causing challenges for proper health services in the country. King Khalid Hospital is among the famous and most developed hospitals of the locality therefore hospital has higher pressure from the targeted market to deliver improved and quality services to all patients visiting this hospital. Although, the hospital is required to take into consideration the contemporary economic issues concerning the public health budgets of Saudi Arabia. Regarding market analysis we have identified the potential of risk growth in the health care sector, diseases outbreak is expected in the global scope which may have devasting impact on the performance outcomes of the King Khalid Hospital (KKH).  Considering this situation an opportunity is identified for the King Khalid Hospital to increase its healthcare services and improve resources utilization in various departments of KKH hospital. King Khalid Hospital (KKH) need to become more performance effective, cost efficient, and innovative for its offered and delivered treatment services in Tabuk. The identified needs and challenges in the targeted market of Tabuk can be addressed by the OPD refurbishment project at King Khalid Hospital. Successful implementation of OPD refurbishment will consequently result in the increase of the total number of clinics and healthcare facilities made available to patients in the King Khalid Hospital. Although, implementation of OPD refurbishment project will ensure the advancement of technology employed at clinics of KKH hospital.

2.0. Business Rationale of King Khalid Hospital in Saudi Arabia

The business rationale section is containing information about the project benefits and key performance indicators. Furthermore, it also includes details about the strategic alignment of the project.

2.1. Project Benefits & KPIs

The project “The use of OPD refurbishment to increase the number of clinics at King Khalid Hospital in Tabuk, Saudi Arabia” will bring several benefits to the targeted audience and community. The project will also ensure delivery of operational benefits in the King Khalid Hospital (KKH). The following table contains information regarding project benefits and key performance indicators (KPIs).

BENEFITS

KPIs

1)      The first benefit of this project is associated with the performance outcomes of King Khalid Hospital (KKH). According to the feasibility analysis of the project, King Khalid Hospital (KKH) will have an improvement in its operational performance by reducing the waiting time of patients in OPD of the hospital.

The key performance indicator (KPI) is a reduction in the waiting time of patients. The project team will monitor and record the waiting time of patients in the hospital to measure the performance outcomes of the project. Successful completion will result in a 25% reduction in the waiting time for the OPD patients.

2)      The second major benefit of this project is linked with the improvement of operational flow in the hospital. The analysis represents that after the successful implementation of this OPD refurbishment project, the hospital will be capable to improve its patients flow in the clinics of hospital.

The second benefit of this OPD refurbishment will be measured by using the key performance indicator (KPI) concerning with reduction in lost time. According to the plan, the project will be considered successful if it results in the reduction of 20% lost time for other departments whilst waiting for OPD in the King Khalid Hospital (KKH).

3)      The third expected benefit of this project is to improve the quality of healthcare services offered by King Khalid Hospital (KKH). The patient services offered to the patients of different clinics in King Khalid Hospital (KKH) will be improved as quality and performance will be increased in the hospital.

The third major key performance indicator to measure the benefits of this project is concerned with the improvement in patient satisfaction level. The project team will collect information from patients regarding their satisfaction with offered and delivered healthcare services in the OPD and other departments of King Khalid Hospital (KKH). The project will be considered as a successful project if it results in an increase in patient satisfaction by at least 15% after the completion of this project. Furthermore, at least 10% future improvement is required in long term outcomes of the King Khalid Hospital (KKH) in Saudi Arabia.

 

 


2.2. Strategic Alignment
of King Khalid Hospital in Saudi Arabia

The project strategic alignment is discussed in detail in this section of the project management plan. The King Khalid Hospital (KKH) is striving to earn its goals and aims regarding the provision of high quality services in the healthcare sector of Saudi Arabia and specifically the city of Tabuk. To ensure the accomplishment of patient needs and requirements in the selected geographical region the project managers are required to align the project aims and objectives with the overall country vision entitled “ Saudi Arabia Vision 2030”.The country is aimed to improve its healthcare services to reduce reliance on foreign facilities and healthcare services as well as to encourage healthcare independence in the country. Bringing forward to this national vision, King Khalid Hospital (KKH) is developing plans to ensure strategic alignment with the national vision and contribute to its achievement in the country. Although, the major aim of this project is to hamper the limitation of available OPD clinics in the city of Tabuk. The project aims to handle such issues by promoting the use of new technologies and systems in the hospital. In result, the hospital is expecting the achievement of its corporate goals strategically aligned with the vision 2030 of Saudi Arabia.  Hospital has developed a plan of addressing these issues and challenges by providing new facilities and departments needed to meet its objectives and support the wider region. Outpatients are healthcare and technologies in the hospital to treat its core patients with improvement healthcare services and processes in all the clinics of King Khalid Hospital (KKH) including OPD.  The individual patients getting treatment by the King Khalid Hospital will get serious attention of medical staff without any delay in treatment and check-up. Although, only patients with critical conditions and emergency situations will be kept in the hospital rooms. Thus, room space related issues will be resolved in the hospital. Hereafter, the project is also strategically focused on the improvement of customer satisfaction (patient satisfaction) therefore medical staff will be restricted to deal with patients in a respectable way and giving priority to their satisfaction regarding offered treatment and healthcare services in the clinics of King Khalid Hospital (KKH).

Note for the next writer: Continue from the following heading “Project Scope”.
3.0. Project Scope of King Khalid Hospital in Saudi Arabia

The main scope of this project is to measure the capacity and of the newly constructed Outpatient department. The other purpose is to make sure that the capacity of patients increases. The management of the hospital named King Khalid Hospital is finding and focusing on as much as space or area they could refurbish to develop the new Outpatient department.

3.1. Deliverables of King Khalid Hospital in Saudi Arabia

Product Deliverables - Description & Requirements

The product deliverables include the material and labor which will be required for the construction of the new OPD in the hospital. The material such as concrete. Cement, piles, steel beams, bricks and lot of other materials will be procured for the construction of the building. In the construction team there will be civil engineers, construction experts, chemical engineer and electricians for creating the new building according to the best construction standards.   There are many activities which are going to be performed in the project execution phase so that the building can be prepared within the time set by the project manager.

Project Management Deliverables

The project management include various phases in which different activities are performed so that the project can be completed efficiently. The phase of the project is the planning phase in which the project plan is created. In the beginning of the project the project charter is going to be developed than the project scope statement and complete project plan is going to be developed. In the planning phase work breakdown structure and the project budget are also developed. The budget of the project is one of the most important document because it provides brief information about resources which are required for completing the project effectively.

3.2. Work Breakdown Structure of King Khalid Hospital in Saudi Arabia

TASK ID

Activity

1

Initial study

1.1

construction requirement

1.1.1

brief technical requirement

1.1.2

review construction material required

1.1.3

develop design & planning

1.1.4

identify process

2

construction phase

2.1

material procurement

2.1.1

identify material requirement

2.1.2

verified and correct material and labor needs

2.1.3

identify team members required

2.1.4

collect planning and procurement

2.1.5

collect construction resources

3

initiate construction

3.1

constructing the building

3.1.1

notify planning & result & schedule

3.1.2

end user delivery

3.1.3

monitor & control scope quality time and cost

3.1.4

verify construction process

3.1.5

perform material quality test

3.1.6

perform construction quality test

3.2

conduct construction review

3.2.1

documentation

finalize review

4

document process

4.1

end user delivery

4.1.1

project completion


3.3. Out of Scope
of King Khalid Hospital in Saudi Arabia

As this is a construction project which include the refurbishment of the current OPD building of the hospital there are many things which does on come under the scope of the project. The activities such as improving the quality of the healthcare services in the hospital or providing new management approaches in the hospital does not come under the scope of the project. Improving the performance of the hospital apart from construction activities does not include in the scope of the project. The aim of this project is to improve the current OPD building and resolving the problems that are emerging from lack of capacity of this building.

3.4. Project Constraints of King Khalid Hospital in Saudi Arabia

 There are many project constraints which the project team will have to face. The first constraint is regarding the OPD healthcare services during the construction phase. During the execution phase of project hospital will have to provide alternative location where OPD services can be given to the health care customers. Another constrain is regarding the external environment factors that impact the project delivery. The sudden economic changes can increase the price of the materials which are required for the completion of the project. If this happens than the project cost can increase up to lot of extent and will cause problem for the completion of the project on time.

3.5. Project Assumptions of King Khalid Hospital in Saudi Arabia

There are different assumptions which have been made regarding the completion and delivery of the project. The first main assumption regarding the project is that during the execution phase of the project the external environment factors which include political factors, social factors and legal factors will remain constant. It means that the project team is assuming that there will be no change in the above discussed economic factors. Another major assumption is that no project team member will leave the project before the completion of the project.

4.0. Project Time Management of King Khalid Hospital in Saudi Arabia

The project time management is an effective method and refers to every single activity of the project. The project time management approach is compulsory in every project because it is most effective approach that estimates project completion. Furthermore, the project time management approach is the best management activity which is providing the information on every project activity time. Every area of the construction consumes the time to complete but without this time estimation technique, no one can tell the owner how much time is required to complete the project. If the construction company did not give lowest project construction time to the owners of the hospital, it might possible that the owner will never make agreement with the company. Although, the construction team of this project can never complete the project on time until they plan for every activity as well as plan for every component or area of the hospital completion. The project manager of this construction project has made the project and apply the project time management approach to handle every employee as well as their activities to complete the construction timely. The project approach is given below in this document that is telling how the project manager is managing the time by using some steps as well as every activity is also planned in this project. For the better management of the time and activity control, the project manager of this project conducted the meeting in which the project management team of this project are asked about their activity, efforts as well as estimated time for their activities. When they finalize everything, then the schedule or Gantt chart for this project is created which is given below and illustrating every activity of the employees including managers activities along with the estimated time for those activities.

4.1. Project Time Management - Approach of King Khalid Hospital in Saudi Arabia

The project time management has huge significance in the success and on time delivery of the project. Different project activities have different completion time which can affect the overall delivery of the project. That is why it is very important for the project manager to keep record of each project activity and make sure that the activity gets completed within the set time period. There are different project manage software and tools through which scheduling of the project deliverables can be done. One of the most commonly used approach for managing the project time is to create Gantt chart.

4.2. Schedule of King Khalid Hospital in Saudi Arabia

5.0. Project Cost Management of King Khalid Hospital in Saudi Arabia

The project cost management is very essential method in every type of project to estimate as well as measure the cost on the project. Furthermore, the project management team can easily identify that how much monetary resources are required to complete the tasks as well as to reduce the cost on every project activity. Furthermore, the project management team of the construction project of Kind Khalid hospital can easily measure the constructive performance by using the full life cycle of the enterprise level projects. The project cost management technique is proposed for this construction project because it is able to encompass many particular functions the project management. There are many functions of the project management in this project monitored and handled such as job control, measuring and estimation, design of the building, accounting, the scheduling as well as the data collection. The main goal of project cost management activity in this project is to construct the hospital withing given time as well as complete the construction in the assigned the budget. The effective project cost management approach is proposed for this project which is given and explain below. The project cost management approach section is telling how this approach is used as well as the brief budget plan for the construction is also given in this document that is illustrating all of the estimated costs in this project.

5.1. Project Cost Management - Approach of King Khalid Hospital in Saudi Arabia

Management of the project cost is highly significant for making the project successful and completing the project within the allocated resources. If the project costs are not management appropriately than the cost of the overall project can increase and more funding will be required for finishing the project. Due to inefficient use of resources not only the project can experience delay but also the overall benefit of the project will decline. The effective cost management of the project can be done through establishing accurate project budget and managing the resources of the project.

5.2. Budget of King Khalid Hospital in Saudi Arabia

budget

amount

amount

fixed costs

965476

concrete

40000

steel beams

667342

hardware maintenance

78678

pipes, fittings and other equipment

34234

misc. equipment

89787

management expenses

55435

variable costs

421127

direct Labor (wages)

255843

site manager

87977

procurement & planning manager

67868

civil engineer

54343

financial manager

45655

direct material

165284

transportation

4564

tracking layout

34535

office supplies

98776

electricity & water

9877

direct expenses

8766

cable

8766

contingency expenses

78868

investment expenses

decrees in inventory

88658

increase in operation efficiency

88234

headcount reduction

333668

gain from investment

510560

 6.0 Project Human Resource Management of King Khalid Hospital in Saudi Arabia

There are different project team members who work in the project so that project can be delivered on time successfully. The successful management of the project team members is important for successful delivery of the project. In this project different team members are working which include project manager who is responsible for the management of the whole project. Other project team members include civil engineers, construction site supervisors, electricians, plumbers and other construction experts who will going to construct the new OPD building of the hospital. The project manager has created a human resource management plan through which the needs and issues of the project team members will be addressed.

6.1. Project Human Resource Management - Approach of King Khalid Hospital in Saudi Arabia

The project manager has established a human resource management plan through which the needs and issues of the project team members are going to be addressed. The project manager will hold meeting on weekly basis in which the progress of the project is going to be discussed. The project team members will report to the project manager regarding the progress in the project and notify any problem which will occur in the project. The project team member will keep on taking feedback from the team members so that it can stay updated regarding project activities.

6.2. Project Team Members of King Khalid Hospital in Saudi Arabi

In this project different team members are working which include project manager who is responsible for the management of the whole project. Other project team members include civil engineers, construction site supervisors, electricians, plumbers and other construction experts who will going to construct the new OPD building of the hospital. The project team members will report to the project manager regarding the progress in the project and notify any problem which will occur in the project. The project team member will keep on taking feedback from the team members so that it can stay updated regarding project activities.

6.3. Responsibility Assignment Matrix of King Khalid Hospital in Saudi Arabia

TASK ID

Activity

responsible

accountable

consulted

informed

1

Initial study

cv

PRM

PROC

ST

1.1

construction requirement

cv

PRM

PROC

ST

1.1.1

brief technical requirement

cv

PRM

PROC

ST

1.1.2

review construction material required

cv

PRM

PROC

ST

1.1.3

develop design & planning

cv

PRM

PROC

ST

1.1.4

identify process

cv

PRM

PROC

ST

2

construction phase

cv

PRM

PROC

ST

2.1

material procurement

cv

PRM

PROC

ST

2.1.1

identify material requirement

cv

PRM

PROC

ST

2.1.2

verified and correct material and labor needs

cv

PRM

PROC

ST

2.1.3

identify team members required

cv

PRM

PROC

ST

2.1.4

collect planning and procurement

cv

PRM

PROC

ST

2.1.5

collect construction resources

cv

PRM

PROC

ST

3

initiate construction

cv

PRM

cv

ST

3.1

constructing the building

cv

PRM

cv

ST

3.1.1

notify planning & result & schedule

Con.

PRM

cv

ST

3.1.2

end user delivery

Con.

PRM

cv

ST

3.1.3

monitor & control scope quality time and cost

Con.

PRM

cv

ST

3.1.4

verify construction process

Con.

PRM

cv

ST

3.1.5

perform material quality test

Con.

PRM

cv

ST

3.1.6

perform construction quality test

Con.

PRM

cv

ST

3.2

conduct construction review

Con.

PRM

cv

ST

3.2.1

documentation

Con.

PRM

cv

ST

finalize review

Con.

PRM

cv

ST

4

document process

Con.

PRM

cv

ST

4.1

end user delivery

Con.

PRM

cv

ST

4.1.1

project completion

Con.

PRM

cv

ST

 

7.0. Project Communications Management of King Khalid Hospital in Saudi Arabia

The project communication management is also an effective approach to manage the communication into the project. The project communication management makes sure that every stakeholder that is related to the construction project engaged with each other and they can effectively communicate with the related functional lines to increase the workability as well as progress of the construction. Furthermore, the project manager wants to perform and get effective reports on the construction progress and performance of employees on daily basis. So, the project communication management approach is proposed for this project. In this approach, all of the stakeholders including project manager of the construction project are using the online website communication portal where they can communicate with each other as well as provide the project related documents and project reports. Furthermore, the managers can also assign duties to labors as well as can also check their performances and other employees’ feedbacks. The project manager of this project appreciates this technique because it makes him able to see every single activity related to project as well as read the documents and reports including financial statement reports of this project to analyze the progress and performance. By applying this technique, the project manager is able to make further new effective and efficient strategies for the project which will be beneficial in the project completion timely. The project communication management approach which is proposed for this project is given below and providing a lot of information on how the it will work for the success of the project. In the last of this section a project management plan is also provided in this document.

7.1. Project Communication Management - Approach of King Khalid Hospital in Saudi Arabia

In this section, the project communication management approach is discussed that will be beneficial for the engagement of all of the stakeholders by the development of the bi-directional as well as the controlled flow of information among all stakeholders of this project. Furthermore, the project cannot afford any kind of the miscommunication or communication gap because of heavy investment and it is a big project. To remove all types of communication gaps, the project communication management approach is embedded in which the proper communication plan is created to engage all employees and other stakeholders related to the project. In the approach of project communication management, the project management is the responsible for each internal communication as well as he will responsible to report every week to project board by using the highlight report. Although, other related documents as well as the reports will be used for this purpose according to condition. Some kind of tools and techniques are also used in the project communication management approach in which the project manager of the construction project of King Khalid Hospital will use online website portal to communicate with other stakeholders internally as well as to see save and read the project documentation. The online website portal is very effective for the communication because the online portal will give the facility to the project manager to see internal activities of the project. For example, he can observe the supply chain, resources management, as well as the relevant documents and reports. Although, all stakeholders can easily communicate with each other by the use of the website portal.

7.2 Communication Plan of King Khalid Hospital in Saudi Arabia 

In the project communication plan, there are some inputs, tools and techniques as well as output of those inputs are mentioned which are also mentioned and explained in the project communication management approach section. The communication management plan is given below;

 

Communication

Format

Frequency / time

Distribution

Team Briefing

Restricted intranet

Daily at 9:00 am

Team and Stakeholders with access to secure the construction project information area.

Weekly Web portal Bulletin

Internal Intranet

Weekly (mail or notification will be sent)

Team Sponsor as well as senior management of the hospital and top project team member

Technical incident reporting

Emailing

Immediately after occurring the technical incident

The Senior Civil Engineer and Civil engineering including sub engineers

Detail provision on the budget of project and schedule for activities

Spreadsheets and Detail time Schedule or Gantt chart

After Every two Weeks

Sponsor, Top management

Achievements and Setbacks

Email and Intranet

Weekly

All internal Stakeholders in working on the project

Schedule Milestones

Email and Intranet

Weekly

All internal Stakeholders in working on the project

Cost-to-date Milestones

Email and Intranet

Weekly

All internal Stakeholders in working on the project

Current Top 5 Risks

Email and Intranet

Weekly

All internal Stakeholders in working on the project


 

8.0. Stakeholder Management of King Khalid Hospital in Saudi Arabia

In this project, the stakeholder management is also performed to build and maintain the strong relationships with every person who is related to the King Khalid Hospital’s construction project. It is because every stakeholder of this project has directly and indirectly impact on the construction work and they are influential on this project. To manage and engage every stakeholder, the stakeholder’s management plan. The detailed stakeholder’s management strategy is used to plan the management which will be very effective in the project and every stakeholder will have the knowledge about their responsibilities.

8.1. Stakeholder Management Plan of King Khalid Hospital in Saudi Arabia

In this section, the stakeholder management plan is described to develop. There are different types of stakeholders in this project as well as indirectly related to this project. Because of the significant responsibilities and many activities in the project, the project managers have to establish a project management plan. For this purpose, the project managers have to go through the fiver steps to develop the stakeholder management plan and then have to develop the matrix for the stakeholders which will show how every listed stakeholder will be managed. Every stakeholder is interrelated to each other and every activity is based on other stakeholders’ activities. The labor supervisor will supervise the labor and assign the tasks to the labor and at the end of the day he has to report to civil engineer, sub engineer as well as site manager. Some kind of tools and techniques are also used in the project communication management approach in which the project manager of the construction project of King Khalid Hospital will use online website portal to communicate with other stakeholders internally as well as to see save and read the project documentation. The resource planner will the planner will plan the resources and allocated them to the project management team and report to the project manager and the financial manager. Every stakeholder in this project is responsible to perform their activities and have to report to appropriate professional and every report will be transferred to the project manager.

List of all Stakeholders

·         Labor Supervisor

·         site manager

·         procurement & planning manager

·         civil engineer

·         Sub engineer

·         financial manager

·         Supply Chain manager

·         Resource Planner

·         Quality Control Manager

·         Quality Assurance Manager

·         Project Manager

·         Team Members of construction project

·         Contractors

·         Subcontractors

·         Equipment suppliers

·         Resources Suppliers

·         Service Providers

9.0. Project Risk Management of King Khalid Hospital in Saudi Arabia
9.1. Project Risk Management - Approach

In the construction project of the Kind Khalid Hospital, the risk management approach is also needed because the civil engineers as well as the project manager including the owners do not want any kind of mistake or any kind of threat in the construction because those threats can be very dangerous and harmful for whole project. Because of occurrence of heavy risk or threat, there can be various problems occur in the project as well as can damage the structure of the hospital. So, the project risk management process is proposed for this project that contains six main steps which are given below;

·         Risk management planning

In this step, the project manager and the team of the construction project will have to plan that how much effort will be required to resolve that risk. They will also plan how they have to implement divergence to complete the project without stopping the project. So, every aspect is planned in this step.

·         Risk determination

In this step, the project manager along with the project management team will brainstorm and try to identify every single risks and every they will also identity those risks which can remain in the project and the performance and work will be not affected by those risks.

·         Analysis of risk Qualitatively and Quantitatively

It is the very significant step of the risk management processes in which project manager and the assistant project manager and other stakeholders will analyze the identified risks and threats in both qualitatively and qualitatively to measure the impact of every risk and measure actual number of the risks.

·         Risk response planning

If the civil engineers will identify and face any risk, they project managers and engineers have respond to that risk to resolve them. But they will have to plan for this purpose. So, the plan is also made in this step and planned a second team having experienced engineers to respond those risks.

·         Risk Monitoring and controlling

When the risk management team will work on the risks, they will again monitor the risks and control them. On the other side, the construction team is also advised to monitors and control the risks during the project.

9.2. Risk Register

In this step, the risks which are identified by the project management team are recorded and documented whose detail will be entered and inserted into the project documents, reports as well as the online portal to make everything clear. It is because the project manager of the construction project will have the evidence that how the risks came into shaped and how the team has managed as well as how much cost came on those activities to resolve those issues.

10.0. Project Quality Management of King Khalid Hospital in Saudi Arabia

10.1. Project Quality Management - Approach of King Khalid Hospital in Saudi Arabia

The project needs to be monitored as well as every completed area of the hospital should meet the standards of the quality. But areas can also be constructed as the low quality and meet the standards. So, every construction project needs the project quality management. The project quality management approach is also used in this project to measure and control the quality which is very effective for the construction tasks. In this project, the total quality management approach is proposed for this construction project in which almost all of the aspects are tackled and managed to control the quality of the project. There are several types of the management principles included in the project quality management. The quality managers of this project focus on the requirements of the owner of King Khalid Hospital and the quality engineers always focus to construct as per requirements. The whole process focuses on the leadership driven. In this this approach, the quality managers must ensure every member’s work in the teamwork. To meet with the quality and bring the high accuracy into the construction tasks, the project quality managers have to train and educate every project team member to complete the construction tasks. furthermore, they will also ensure the statistical methods and also manage the information. The quality managers also focus to align the whole activities as well as to improve customer service. The main function of the project quality manager is that they completely focus on increase the quality of the construction as well as effectively focus on the cost of quality. It is because the project is already very expensive and needs to be cost effective.

11.0 Project Procurement Management

11.1. Project Procurement Management - Approach of King Khalid Hospital in Saudi Arabia

In this project step, the project procurement management process is performed to find the final building results. In this process, there are five steps are included which are very significant procurement management approach. First of all, the specification step is started in which all of the specifications are studied. Furthermore, the specification step involves purchasing department which will communicate with the project manager to approve and the develop the list of items to the construction. After this step, the selection step is started in which the project manager conduct meeting with the team member and select the prior resources and equipment for the construction. They will critically analyze every thing that what thing will be constructed and what will not be constructed. After this, the contract step is started in which both ends the owner of the hospital and the construction project team will agreed upon the contract and sign on the agreement papers.

TASK ID

Activity

1

Initial study

1.1

construction requirement

1.1.1

brief technical requirement

1.1.2

review construction material required

1.1.3

develop design & planning

1.1.4

identify process

2

construction phase

2.1

material procurement

2.1.1

identify material requirement

2.1.2

verified and correct material and labor needs

2.1.3

identify team members required

2.1.4

collect planning and procurement

2.1.5

collect construction resources

3

initiate construction

3.1

constructing the building

3.1.1

notify planning & result & schedule

3.1.2

end user delivery

3.1.3

monitor & control scope quality time and cost

3.1.4

verify construction process

3.1.5

perform material quality test

3.1.6

perform construction quality test

3.2

conduct construction review

3.2.1

documentation

finalize review

4

document process

4.1

end user delivery

4.1.1

project completion


12.0 Project Control of King Khalid Hospital in Saudi Arabia

 
12.1. Progress Reporting
of King Khalid Hospital in Saudi Arabia

The progress reporting is the very effective technique to control the quality of the work as well as by having this reporting technique, the managers working in the project construction can easily measure the progress as well as analyze the progress speedy and effective way. The project manager always want to have the progress report to see either the project is going in the right way or wrong way. So, every supervisor and the manager is responsible to report to its appropriate senior supervisor

12.2.  Change Management of King Khalid Hospital in Saudi Arabia

The construction company in the project of King Khalid Hospital’s construction have also implemented and used the change management to deal with the changes as well as bring improvements in the performance and the progress of the construction. The mangers and engineers who are working on the sites, they applied for change because of interruption in the working and performance of the employees. The project management team of the construction company did analyze first and approve the change. By implementing the change, progress of the construction team was improved.

12.3. Project Completion Review of King Khalid Hospital in Saudi Arabia

In the end of the project, a project completion review report is created which is telling all of the constructed component sand area of the hospital as well as review report is also telling that what is the quality of the building is. Furthermore, the feedback is also provided. 

APPENDIX A – Schedule of King Khalid Hospital in Saudi Arabia

(return)

Full Schedule in embedded attachment
<Embed full schedule as a PDF file (instructions on how by double clicking on the icon below)>

Also, show a High Level Schedule of Activities (below is an example – replace with your project)

APPENDIX B – Project Budget   of King Khalid Hospital in Saudi Arabia

(return)

ID

WBS TASKS

Total

$

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

BUDGET – TOTAL

 


 

 

APPENDIX C – Responsibility Assignment Matrix

(return)

 

ID

WBS TASKS

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

LEGEND

R – Responsible (for executing activity)                           A – Accountable (buck stops here)                   I – Informed (FYI)                 C – Consult (must)

                                               

Add to the legend to suit your project

 

 



Date:                                                                                     


APPENDIX D – Communication Plan          

(return)

 

Key Reports / meetings 

Who to receive

Frequency

Method

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

APPENDIX E – Stakeholder Management Plan              

(retur

 

Stakeholder

Stake/Interest

Action

Responsibility

By When

Status

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

APPENDIX F – Risk Register

(return)

 

#

Risk Event

Likelihd

Conseqce

Rating

Treatment

Responsible

Officer

By Date

Status

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

`

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


APPENDIX G – Quality Register  

(return)

 

 

WBS #

Product Name

Quality Acceptance Criteria

Quality Check Method

Quality Checker

Quality Checker

Result of Quality check

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

END OF
PROJECT MANAGEMENT PLAN

 

Our Top Online Essay Writers.

Discuss your homework for free! Start chat

Top Rated Expert

ONLINE

Top Rated Expert

1869 Orders Completed

ECFX Market

ONLINE

Ecfx Market

63 Orders Completed

Assignments Hut

ONLINE

Assignments Hut

1428 Orders Completed