How many cars a production sector will produce in a given
shift time (8-hours) directly depends upon the time spent on each stage or
process in the production. For instance, how much time was required at the
first stage and how much time the second stage took in the completion. Moreover,
it also depends upon the selection of the processing system. For instance,
process batch takes less time in completion as compared to transfer batch. In
case a production sector set-up different stages for the production of cars
with the following specifications then the total of 214 cars will be
produced in an 8-hour shift.
Stage: A
Around 20-cars per hour are expected to have changed in the
model during 20min.
Stage: B
Around 20 cars maintenance and cleaning require time 30min
after each 90-min operation.
Stage: C
18 per hour of customization without set-up.
Then total cars went through these stages will be as
following:
|
Per Hour
|
8 hour
|
Production
|
20
|
107
|
Changing the model
|
60
|
321
|
M&C
|
40
|
214
|
Customization
|
18
|
96.3
|
The values of 8 hours are adjusted with the time-break of 30
minutes after each 90 minute operations at production sector.
Question: 2
The second question from the case study is about the total
available idle time during the stages of selected shift time. Considering the
shared information, the total idle time during this shift is 30 minute
which will be taken after every 90 minutes. During this idle time, the company
will not run its production machines for the assembling and manufacturing of
car parts.
Question: 3
Capacity building can be beneficial for the production
sector and a specific stage of this production system. In accordance with the
case study, stage A need to require capacity increasing as the second stage
does not need an increase in capacity. We will add capacity of 50 more cars in
the stage A. However, in customization stage, we also need to add capacity for
better performance and alignment with the production capacity of other stages
in the production sector. Focusing on stage A we can say that capacity would
cost:
In this car production system, set-up
times are unproductive therefore we will reduce these set-up times in stage A
to increase system capacity in the production sector.
Question: 4
Would we need to reduce the setup time? Regarding this
question, the following considerations are presented.
For instance, if we reduce the time for 10
min then we will have to pay $10,000 more in the cost of production. While
$20,000 cost allocation is required for the downtime of 15 min from 30. The
reduction is favourable for the set-up stage as it only cost $10,000 but might
be resulted in the increase of production at stage A (which was already less
than stage B). Although, in case of reduction option 2 we will have 50%
reduction at cost of $20,000 which does not seem a suitable option in respect
to the shared case scenario.
Question: 5
As stated above 50% reduction will be
made in stage A with $10,000 cost. The time reduction will bring changes in the
overall outcomes and capacity of this production system. See the following
table representing the system impact of time reduction on the overall production
of stage A.
|
per hour
|
8 hour
|
Production
|
40
|
214
|
Changing the model
|
60
|
321
|
M&C
|
40
|
214
|
Customization
|
18
|
96.3
|
Before reduction stage A was capable to
produce 20 cars per hour. Thus, by reducing 50% (20 min to 10 min) in stage A
production system now almost double cars can be produced. Therefore, 20 cars
are jumped to 40 cars per hour of production. As a result, the total system
capacity for the 8-hours shift is also inclined to 214 from 107 cars.
Question: 6
The two given options are adding buffers
and reducing setup time. Based on the
analysis, the most favourable and better option is reducing set-up time. Adding
buffer for 50 more cars will cost around $250,000. While selecting the 50% time
reduction option for stage A will cost around $10,000 only. Thus, reducing time
at a specific stage of the production process is more cost effective as
compared to the options one of adding buffers for capacity building. Thus,
conclusively the time reduction option is a better option for the company.
Question: 7
In case, we combine both available
options for the given case study them, the total cost of operations will
increase for the production sector. However, at the same time, increased
capacity and production output will reduce cost per unit. Adding buffers and
reducing set-ups will cost as:
While the expected increase in the system
cost is $260,000 for the addition of both options, However, the total number of
increase in the cars per shift of 8-hour represent the system capacity for the
production sector. Considering this, the total increase in capacity of the
production system would be around 157 cars. The following calculations are used
to calculate the total increase in system capacity.
Question: 8
In case, we consider all available (3
options) for the same production system them overall capacity and cost of
production will again get changed. In such a situation, three options will generate
the following cost:
Thus, the calculated cost for the
implementation of all three available options in the production system is
limited to $280, 000. While the best option from all three available options is
a reduction in the set-up time at stage A.
Part B
Question: 9
A 6 day per week operations with 8-hour
shift would be as:
|
per hour
|
8 hour
|
6 Days
|
Production
|
40
|
214
|
1284
|
Changing the model
|
60
|
321
|
1926
|
M&C
|
40
|
214
|
1284
|
Customization
|
18
|
96.3
|
577.8
|
The above-presented table is based on the
implementation of the time reduction system at the set-up stage of the
production system. However, if we consider a simple production system without
buffering and reduction options then total production in 6 days would be
limited to 642 cars per weeks.
Question: 10
The
batch sequence for the three models during the week will be processed as:
Question: 11
In case, we had another model "w" then the whole
process could get an effect. At the same production set-up, we cannot build so
many car models because each time when we start production of a new car model
we need to make changes in the model sizes and other specifications which
require more than 20 minutes each time.
Question: 12
In order to incorporate with this additional model, we need
to develop capacity in the production system of each stage including production
stage, assembling stage, and customization stage. Furthermore, more buffers and
reduction plans would be required to control the cost of operations while
boosting its efficiency and capacity of production.