Loading...

Messages

Proposals

Stuck in your homework and missing deadline?

Get Urgent Help In Your Essays, Assignments, Homeworks, Dissertation, Thesis Or Coursework Writing

100% Plagiarism Free Writing - Free Turnitin Report - Professional And Experienced Writers - 24/7 Online Support

Report on Project management analysis

Category: Project Management Paper Type: Academic Writing Reference: APA Words: 2100

Executive Summary of Project management analysis of ecotech company

Ecotech is an organization established in Scotland. The organization sells and manufactures a variety of EEC (Environmental Electronic Control) products in the EU. In the year 2019, the organization has decided to create a large manufacturing and logistic plant in Scotland. In the present project, different possible activities can be delayed without having an impact on the successor activity. The critical path analysis provides the longest sequence for the activities in the project to be delayed and completed in the timeframe. Considering the present situation, the European government is offering a new environmental control system for the buildings and it will be delivered in the coming days of 23rd august 2021. The process can cut activity time to the shortest possible time.

Table of Contents

Introduction. 3

Part 1: Scheduling. 4

Network diagram of project 4

Gantt chart 6

Slack time calculation. 8

Justification for European government offer 9

Part 2 Budget calculations. 9

Number of required manpower 10

Total cost of adding new manpower 10

Budget for adding hiring new manpower 11

Advantages and disadvantages of each approach. 12

Part 3 change management 13

New Gantt chart according to change. 13

Revised budget 13

Part 4 Tracking. 14

References

Introduction of Project management analysis of ecotech company

Ecotech is an organization established in Scotland. The organization sells and manufactures a variety of EEC (Environmental Electronic Control) products in the EU. In the year 2019, the organization has decided to create a large manufacturing and logistic plant in Scotland. The organization has decided to produce new high tech products so that it can capture the IoT market.

Part 1: Scheduling of Project management analysis of ecotech company
Network diagram of the project
of Project management analysis of ecotech company

The network diagram of the project is based on the time constraints and information about the time required to complete the task and predecessors of Ecotech production sites. Where unit A, unit B, and Unit C are research, manufacturing, and shipping and logistics respectively (Keathley, 2014).

Task

Description

Duration

predecessors

1

Project Approval

0

2

Concept Design

4

1

3

Detailed design

12

2

4

Site preparation

8

3

5

Project Review

1

4

6

Unit A Construction

15

4,5

7

Unit B Construction

40

4,5

8

Unit C construction

25

4,5

9

Site Testing

8

6,7,8

10

Staff Recruitment / training

6

6,7,8

11

Test production starts

4

9, 10

12

Project close out

0

11


a)      Network diagram of Project management analysis of ecotech company

The network diagram is constructed in the Microsoft Visio program. All the related components relate to each other (Keathley, 2014).


Gantt chart of Project management analysis of ecotech company

The accurate Gantt chart for the project is provided below in table 1. 


Figure 1 Gantt Chart For the Project

Slack time calculation of Project management analysis of ecotech company

Free float is the amount of time in which the project can be delayed from the early start date without having any issue in the final time of the project. in the present project, different possible activities can be delayed without having an impact on the successor activity (Kourdi, 2015). The critical path analysis provides the longest sequence for the activities in the project to be delayed and completed in the timeframe. In the project different non-critical tasks are considered and the float (free slack) calculation is provided below,


Task

Description

duration in days

Early start

Early finish

Late start

Late Finish

Total Float Time

1

Project Approval

0

 

1

0

2

1

1

2

Concept Design

4

1

1

4

2

5

1

3

Detailed design

12

2

5

16

6

17

1

4

Site preparation

8

3

17

24

18

25

1

5

Project Review

1

4

25

25

26

26

1

6

Unit A Construction

15

4,5

26

40

27

41

1

7

Unit B Construction

40

4,5

41

80

42

81

1

8

Unit C construction

25

4,5

81

105

82

106

1

9

Site Testing

8

6,7,8

106

113

107

114

1

10

Staff Recruitment / training

6

6,7,8

114

119

115

120

1

11

Test production starts

4

9, 10

120

123

121

118

1

12

Project close out

0

11

124

123

123

124

-1


Justification for a European government offer

Considering the present situation, the European government is offering a new environmental control system for the buildings and it will be delivered in the coming days of 23rd august 2021. The process can cut activity time to the shortest possible time (Campbel, et al., 2011) This condition is worthy for the company and the justification for the selection of the conditions are listed below,

1.      The program will deliver services that will help reduce process cost and time.

2.      The operation time is only 12 weeks that is relatively short when working with other processes.

3.      Failure in taking decisions can cause a penalty of 4 million euros.

4.      The program will increase profit as it provides a reliable control system.

5.      The program will help develop public relations for Ecotech.

Part 2 Budget calculations of Project management analysis of ecotech company

a)      In the budget calculation, several options can be considered by the Ecotech board that can assist in tackling the project. The present budget calculations are based on size project management professionals and team members. The total cost per week is estimated at 48, 000 euros (Chandra, 2011). The cost for the technical team members is supposed to be 50, 000 euros per week. The total cost for design and material is illustrated in table 2. There are two possible conditions when considering agency supplied staff from CC build resources (Pandey, 2015).

1.      In this condition, every person is required to complete four tasks and they will be hired separately. The budget is considered if new members for site testing are not hired. This will cut the cost of site testing employees in completing the budget. The cost of each person was first measured in sterling and then converted to euro for complete estimation. The current rate for the conversion is as 1 sterling = 1.14 euro. From thousands to millions it is converted and then the budget is estimated. To add new workers in the construction the rate of each worker is different (Warren, et al., 2016). The rate of foremen, technicians, and laborers in sterling are 200, 120 and 80 respectively. The construction manpower is mentioned in the table below.

Number of required manpower of Project management analysis of ecotech company

Construction man power required

Column1

Column2

Column3

Taskforce

Foremen rates

technicians

laborers

Unit A construction

10

20

50

Unit B construction

30

60

100

Unit C construction

10

40

60

site testing

10

20

20

The total cost of adding new manpower of Project management analysis of ecotech company

Task

Foremen rates (200 euro each)

technicians (120 euro each)

laborers (80 euro each)

Total cost

Unit A construction

2.28

2.736

4.56

9.576

Unit B construction

6.84

8.208

9.12

24.168

Unit C construction

2.28

5.472

5.472

13.224

site testing

2.28

2.736

1.824

6.84

Total Cost

13.68

19.152

20.976

53.808

Budget for adding hiring new manpower

Adding new manpower will increase the cost beyond the previously defined budget. Before adding new manpower, the estimated total budget of Ecotech as approximately 33 million euros but after adding new manpower it will reach as double that is approximately 64.9 euros for the whole project (Simons, 2011).

fixed cost by the task

Description

fixed cost

Cost of selecting a fixed number of staff

Cost of selecting a fixed number of staff without site testing

1

Project Approval

N/a

2

Concent Design

2.6

2.6

2.6

3

Detailed design

4.8

4.8

4.8

4

Site preparation

0.8

0.8

0.8

5

Project Review

0

0

0

6

Unit A Construction

4.2

9.576

9.576

7

Unit B Construction

10.5

24.168

24.168

8

Unit C construction

6.2

13.224

13.224

9

Site Testing

1.1

6.84

1.1

10

Staff Recruitment / training

1.4

1.4

1.4

11

Test production starts

1.5

1.5

1.5

12

Project close out

0

0

0

total

33.1

64.908

59.168

 

2.      Considering the above table of budget and fixed cost by task another option is to select previously existing people to work on-site testing without hiring new people. In this situation, new hiring will be done only for unit A construction, Unit B, Construction, and Unit C construction with the cost of individual foremen, technicians, and laborers in sterling as 200, 120 and 80 respectively. Before adding new manpower, the estimated total budget of Ecotech as approximately 33 million euros but after adding new manpower with previous site testing conditions it will reach approximately 59 million euros for the whole project (Spender, 2014).

Advantages and disadvantages of each approach of Project management analysis of ecotech company

Approach

Advantages and disadvantages

1

Considering the purely freelance agency staffing will reduce the cost of the project. it will cut the monthly salary of workers. the company will pay only in case the workers are working and it will pay as daily wages.

2

Implementing this creative recruiting strategy will help in finding experienced new roles that will make the process faster and fewer efforts are required.

3

We don’t need a high-quality lead for the monthly working conditions. Besides that company is not required to accommodate that candidate.

4

The potential cost will decrease with increasing benefits and it will figure out the full picture of the reduced cost of the project.

5

The number of freelancers will jump at the opportunity and we will be provided with a great startup.

6

Freelancers can navigate a fast-changing system with simple instruction. They will work as an automatic team.

7

They will strengthen the company with content marketing also.

8

They will work with new creative techniques.

9

They will not require office space to work in.

10

They will have not access to the work structure of the company.


Part 3 change management
of Project management analysis of ecotech company
Revised budget

fixed cost by the task

Description

fixed cost

Cost of selecting a fixed number of staff

Cost of selecting a fixed number of staff without site testing

1

Project Approval

N/a

2

Concept Design

2.6

2.6

2.6

3

Detailed design

4.8

4.8

4.8

4

Site preparation

0.8

0.8

0.8

5

Project Review

0

0

0

6

Unit A Construction

4.2

9.576

9.576

7

contract with AWB

14.5

0

0

8

legal cost

0.2

24.168

24.168

9

Unit C construction

6.2

13.224

13.224

10

Site Testing

1.1

6.84

1.1

11

Staff Recruitment / training

1.4

1.4

1.4

12

Test production starts

1.5

1.5

1.5

13

Project close out

0

0

0

total

37.3

64.908

59.168

 

According to the recent changes in the project, the timing and the costs of the project have changed. These changes are included in the project schedule and project budget for the effective completion of the project (Warren, et al., 2016).

Part 4 Tracking of Project management analysis of ecotech company

no.

Details

completion %

1

Project Approval

100%

2

Concept Design

100%

3

Detailed design

100%

4

Site preparation

100%

5

Project Review

100%

6

Unit A Construction

84%

7

Unit B construction

46%

8

Unit C construction

36%

9

Site Testing

0%

10

Staff Recruitment / training

0%

11

Test production starts

0%

12

Project close out

0%

 

The traffic light system is providing detail regarding which projects are completed and which projects are behind the schedule.

References of Project management analysis of ecotech company

Campbel, D., Edgar, D. & Stonehouse, G., 2011. Business Strategy: An Introduction. s.l. Macmillan International Higher Education.

Chandra, P., 2011. Financial Management. s.l. Tata McGraw-Hill Education.

Keathley, E., 2014. Digital Asset Management: Content Architectures, Project Management, and Creating Order out of Media Chaos. s.l. Apress.

Kourdi, J., 2015. The Economist: Business Strategy 3rd edition: A guide to effective decision-making. s.l.: Profile Books.

Pandey, I., 2015. Financial Management. s.l. Vikas Publishing House.

Simons, R., ed., 2011. Human Resource Management: Issues, Challenges, and Opportunities. s.l. CRC Press.

Spender, J.-C., 2014. Business Strategy: Managing Uncertainty, Opportunity, and Enterprise. s.l. OUP Oxford.

Warren, C., Reeve, J. M. & Duchac, J., 2016. Financial & Managerial Accounting. s.l. Cengage Learning.

Our Top Online Essay Writers.

Discuss your homework for free! Start chat

Engineering Exam Guru

ONLINE

Engineering Exam Guru

1176 Orders Completed

WRITING LAND

ONLINE

Writing Land

924 Orders Completed

Instant Assignment Writer

ONLINE

Instant Assignment Writer

1722 Orders Completed