Introduction of Thermal energy system project
In this
report, there is complete information about the Thermal energy system for the
golf course. According to the scenario, a golf course in a small town is
involved in consuming substantial amount of water. But according to that
community is increasing and its concern has been increased for long term
sustainability of water supply. For that case, there is need of an agreement
that was held between the golf course and the city in which reclaimed water is
used for the irrigation purpose of the golf course. Due to this process, it
will provide over 30 million gallons of water per year. But the main issue is
that it is not meeting the requirement of golf course and also domestic
irrigation water. According to this problem, a research facility is involved in
using significant amount of water for housing fish stocks.
Then after
this case, they are required to maintain the healthy population of fish they
chilled that water and circulated in tanks. But this water is not usable again.
This water is set to the drain just after the use. Moreover, this golf course
is completely adjacent to a Chilled water plant and made accordingly to the
requirement for its cooling tower. According to that condition, research
facility is providing opportunity for water to recover on time and also used at
the golf course and cooling water plant and also reducing the amount pumped
from the aquifer. According to this scenario, the management is looking for a
new pond on the golf course with a proper water feature and it is connected to
the lower pond and it will act like water hazard.
A complete
system will be designed in such a way that will bring water from the discharge
chilled water storage tanks located near to research facility towards the golf
course and also provide water to the cooling tower according to requirement. This
is all due to the local district energy plant that is serving the community and
also some steam tunnels are available for routing the pipe and reducing the
amount of excavation required. The discharge rate of fishery water is required
to maintain the desired level on the ponds but the cooling water contains lower
flow requirements. Due to this case, control value is suggested to ensure that
the cooling tower contains sufficient water that can easily pass through it.
According to this problem designated work area has been chosen with proper
equipment.
Tasks for the department of Thermal energy
system project
The civil
engineering team is responsible for the excavation of the desired pipe route
and pond design. Moreover, electrical engineering team is responsible for the
designing of automation control of the system with sensors and also completing
the power requirement. Furthermore, mechanical team is involved in designing
the layout of the pipe and specify required pumps and values required for the
whole system. These layout must be cost effective and also feasible for the
final design of the whole for golf course and the city.
Requirement of the system of Thermal energy
system project
Equipment space of Thermal energy system
project
The area is
suitable for the required equipment is about and its celling
height is about 15 feet. The floor is made up of smooth concrete that contains
suitable drainage. On the other hand, it first floor is set at the elevation of
2570 feet. Moreover, this area is located 62 feet west of the steam tunnel and
also connected with the building. The next thing is that this fishery water
comes in the steel pipe through the help of ceiling that is located in the
centre of the equipment room. This pipe is coming down towards the height of 10
feet where it is turning 90% towards south and also leave the building drain
towards outside. The operating speed of the pump is about 3600 rpm.
The next thing is
that fishery drainage storage tank fishery wastewater will go towards the tank
and then it will send to the drainage at the rate of 46 gpm. According to this
case, the temperature of water in the fish tank is about 68 Fahrenheit. Another
fact is that the tank located in the research facility has the capacity of
about 200 gallons and its water level is about 1.7 feet. Moreover, its drain is
about 6 inches of the floor. Due to this, the research facility is only
responsible for teeming the tank into fishery drainpipe. This tank can be
placed anywhere in the whole designated space. According to this fact, the team
will be connected from the drain on the tank to the golf course cooling tower.
Pipe of
Thermal energy system project
It can be
noted that a direct bury cold is buried in the ground but it will enters
towards the steel tunnel at such spot that is suitable for the team. Then after
this when the pipe from research facility travelled towards the steam tunnel it
will leave that tunnel and move towards the cold water plant. For that case, a
pipe tee is required when it will reach towards the plant where this flow is
directed towards the cooling tower. Moreover, after this tee the pie will head
towards the pond and it is about 580 feet. Another thing is that maps of the
cold water route with estimated linear feet of pipe is required by the team and
its depth is about 4 feet below the ground.
Space for equipment
Now for the
chilled water plant, there is requirement of area for the equipment is about and that contains a celling height of 15 feet. On the
other hand, floor elevation is present at 2675 feet. Now the makeup water will
enter in the space through the hole present in the floor at the northeast
cooling tower.
The dimension of
cooling tower is about but the main thing is that in tower there is
requirement if 33 gpm of water that will enter at the pressure of 35 psi during
normal operation. The next thing is that blow down water will leave the tower
at 16.5 gpm at pressure of 5 psi and temperature of 85 Fahrenheit. The next
thing is that the inlet and outlet of tower is arranged at 6 feet from the
floor and present in the middle of the tower at only 1 feet. After the sand
filter the pressure loss is about 20 psi. Moreover, from the working area the
north edge of the cooling tower is at 50 feet.
Now the golf
course pond will be located near the top of the hill and it is located near the
west of the chiller plant. Moreover, the surface of the pond is elevated at the
height of 2700 feet. Moreover, the discharge water involved in feeding the pond
will be exactly horizontal and it is about one feet above the surface and
allowing water to accelerate when it will leaves the pipe. On the other hand, a
complete flapper style lid is installed at one end of the gold course on the
end of the pipe and it is close it when no water is flowing. Any loss of water
in the around the lid can be ignored.
Designing of thermal energy system for the golf course
and research facility
For that
case, there is need of a methodology that is consisted of linking the storage
need of specific application and it is according to the thermal characteristics
of the thermal energy system. For that case, the complete design process is
divided into these steps.
The first
step is related to the characterization of the thermal process, the second step
is related to specification of the thermal energy system. The third step is
related to the characterization of the TES technology and last step is related
to the determination of the design of the whole system. All of these steps are
completely interlinked with each other for ideal design of the system.
Step 1: characterization of the process
It can be
noted that the thermal process is involved in managing series of renewable
resources. For that design, water is considered as a renewable resource and
there is need of proper system that will manage it and also complete the demand
of the golf course irrigation system. Another thing is that there are some
processes that are suitable for the system and also complete the demand of
production. According to the given scenario of the problem, the chilling tower
is located above the research facility. Due to this case, the temperature of
cooling tower is considered as and on the other hand, research facility for the
fishery tank temperature is considered as
Step 2 specification of the thermal energy system
In this step,
there is complete information about the required specification for the design
of thermal energy system.
The area is
suitable for the required equipment is about and its celling
height is about 15 feet. The floor is made up of smooth concrete that contains
suitable drainage. On the other hand, it first floor is set at the elevation of
2570 feet. Moreover, this area is located 62 feet west of the steam tunnel and
also connected with the building. This pipe is coming down towards the height
of 10 feet where it is turning 90% towards south and also leave the building
drain towards outside. The operating speed of the pump is about 3600 rpm.
The next thing is
that fishery drainage storage tank fishery wastewater will go towards the tank
and then it will send to the drainage at the rate of 46 gpm. According to this
case, the temperature of water in the fish tank is about 68 Fahrenheit. Now for the
chilled water plant, there is requirement of area for the equipment is about and that contains a celling height of 15 feet. On the
other hand, floor elevation is present at 2675 feet. Now the makeup water will
enter in the space through the hole present in the floor at the northeast
cooling tower. The dimension of cooling tower is about but the main thing is that in tower there is
requirement if 33 gpm of water that will enter at the pressure of 35 psi during
normal operation.
Step 3 characterization of the thermal energy
system
It can be
noted that in each technology there is complete information about the behaviour
of the whole system. These technology will be applied according to the design
parameters of the system. The first one is related to the direct contract TES
system. It can be noted that these systems are exclusive of SHTES technologies.
Now according to this case, the operation of the thermal energy system is given
by this
According to this
equation, the V is considered as the volume of the cylindrical tower. On the
other hand, c is the storage capacity, is the cylindrical space of the towers, moreover, is considered as the temperature of the cooling tank.
On the other hand, is the temperature of the research facility.
Now working for the
capacity of water stored by the cooling tank and fishery tank. This can be done
through the help of this formula
In the above
equation, is the correction
factor of the storage tank and it must be greater than one. Moreover, m is
considered as the mass of the material present in the tank.
Direct contact thermal energy system for cold water
tank
It can be noted
that fir the chilled water, there is need of cooling tank that are used for the
industrial and domestic used. All of these system are present with the pair of
outlet ad inlet connection and they will avoid the mixing of the materials. According
to the given case, the required pressure for the cooling tank is about 35 psi
when the water is entered the cooling tower. After the water is leaving the
tower this pressure will become 5 psi. For the outer plate of the cooling tower
there is need of straight forward calculation and it is demonstrated by
In the above
equation, is considered
as the diffusivity of the material used for the construction of cooling tank. Moreover,
it is the thickness of the storage medium used for the
tank. On the other hand, the Biot number of the system is given by Bi. Now the
Stephan numbers are explained
Now work for the
number of parallel plates for the cooling tower. Through this it will be
ensured that water will stored completely cold form before use. This can be
explained through this equation
In the above
equation, it is the main power exchange between the tower, t is the viscosity constant and h is considered as
the height of the whole tower.
Step 4: determination of the TES design
In this step, there
is complete information about the determination of the thermal energy system
design.
This is showing
that the cooling water is able to take the water pressure of about 35 psi and
also when the water is moved through the tower its pressure will become 5 psi.
According to the above design it is ensured that the cooling tower is able to
tolerate such pressure of the water and also maintain cooling with perfection
Design of the research facility
According to this
tower it can be noted that it can easily send water to the cooling tower. The
temperature of this tower is maintained at 68 F. this is according to the
design parameters.
Design for the basement for the fishery
research facility
This is the
basement design of the whole area for the fishery research facility. The height
of the tower is set for about 44 feet. This tower is at 62 feet far away from
the working area. In the work area there is complete control of the system is
present.
Area for chilled water plant of Thermal energy system project
According
to the given design it can be noted that there will be four door are located in
the plant. Due to these doors it will become easy to provide proper care for
the plant. From the drawing it can be noted that there are about two cooling
towers are present and they are located at the bottom right corner of the room.
The work area is present just front of the towers.
Conclusion of Thermal energy system project
Summing up
all the discussion from above, it is concluded that there is problem of water
storage for the golf course and the city. In this report, there is complete
designing of the research facility and chilled water plant for the golf course
and city. Due to this it will become extremely simple to complete the demand of
the water. A complete system will be designed in such a way that will bring
water from the discharge chilled water storage tanks located near to research
facility towards the golf course and also provide water to the cooling tower
according to requirement.
Moreover, its
drain is about 6 inches of the floor. Due to this, the research facility is
only responsible for teeming the tank into fishery drainpipe. This tank can be
placed anywhere in the whole designated space. According to this fact, the team
will be connected from the drain on the tank to the golf course cooling tower.
References
of Thermal energy system project
Dhanasekaran
Vikraman, H.-S. K. (2018). Design, Simulation and Construction of Field
Effect Transistors. BoD – Books on Demand.
Ian Renshaw, K. D.
(2010). Motor Learning in Practice: A Constraints-Led Approach.
Routledge.
and also used at teh ter and
circulated in tak of water for housing fish stocks.
Wightman, P. M.,
& Labrador, M. A. (2011). A3Cov: a new topology construction protocol for
connected area coverage in WSN. In 2011 IEEE Wireless Communications and
Networking Conference, pp. 522-527.