Following the case study, the
project will be completed after the painting of the whole building. Following
the case scenario, each activity in the project requires different time
duration for the completion. While most of these activities are linked with
each other. Managers and workers are required to complete one activity prior to
the start of the second activity. For instance, drainage cannot be installed
until the completion of clearing the site activity. Similarly, walls need to be
constructed before starting construction of the roof. Other than these, workers
are also bound to work only on 5 days a week (from Monday to Friday). Considering
all these conditions and requirements of this construction project estimation
for the project completion date is 4 February 2022 if the project starts on 2
March 2020. See the following work plan with dates and required weeks.
Activities
|
Weeks
|
Start Date
|
End Date
|
Month
|
Penalty
|
Clearing
the site,
|
8
|
2-Mar-20
|
24-Apr-20
|
April
|
|
Installing
drainage
|
8
|
27-Apr-20
|
19-Jun-20
|
June
|
|
Earth-filling
and levelling
|
14
|
22-Jun-20
|
25-Sep-20
|
September
|
|
Installing
turf
|
12
|
28-Sep-20
|
18-Dec-20
|
December
|
|
Excavating
|
4
|
21-Dec-20
|
15-Jan-21
|
January
|
$
30,000
|
Pouring
concrete for basement
|
4
|
18-Jan-21
|
12-Feb-21
|
Feb
|
$
40,000
|
Construction
of the walls
|
12
|
15-Feb-21
|
7-May-21
|
May
|
$
120,000
|
Constructing
the roof
|
13
|
10-May-21
|
6-Aug-21
|
August
|
$
130,000
|
Interior
work
|
5
|
6-Aug-21
|
10-Sep-21
|
September
|
$
50,000
|
Approval
|
4
|
13-Sep-21
|
8-Oct-21
|
October
|
$
40,000
|
Power
lines
|
8
|
11-Oct-21
|
3-Dec-21
|
December
|
$
80,000
|
Electrical
work
|
5
|
6-Dec-21
|
7-Jan-22
|
January
|
$
50,000
|
Internal
painting
|
4
|
10-Jan-22
|
4-Feb-22
|
Feb
|
$
40,000
|
|
|
|
|
|
$ 580,000
|
Based on the estimation (as
presented by the above table) it can be said that the company would have to pay
the penalty of $580.000. the penalty amount is calculated by multiplying the
total working weeks with the penalty amount per week (58 weeks * $10000 =
$580,000). This huge amount is required to be paid as a penalty because the
company would not be able to complete its project in 8-month duration (Starting
from March and Ending in December) as stated in the case study. Following the case
study, the company will have time from march to December to complete these
activities. However, these activities cannot be completed in this short time
duration as the majority of activities are directly linked with the completion
of relevant activities. For instance, workers cannot paint walls and building
areas unless electricians have completed their task of installing wires in the
whole building. In the above stated table, penalty schedule is presented in
detail. However, this amount can be reduced by the following strategies:
1)
Increasing the total number of workers can
reduce the time duration for the completion of each activity (Blocher,
2006).
2)
Working part-time on some projects can also
reduce this time duration and penalty amount.
3)
Project management can also bring down this
penalty amount by reducing the unnecessary time required by some activities.
For instance, approval requires 4 weeks (as stated in the case study). Project
managers can reduce this approval time.
Question: 2
Analyze the three proposals. Indicate which, if any, you
would apply and why.
There are three proposals suggested in a case study. Each
proposal is stated below in brief detail.
Proposal One:
Reduce six-week duration by expediting overall construction
work. It will require at least $20,000 additional amount. As a result of this
proposal company would be able to save the following amount of penalty:
Thus, calculation represents that
proposal one would generate the net profit of $40,000 for the company by
reducing 6 weeks penalty at the cost of $20, 000.
Proposal Two: Now the second proposal available to
the company is about the double shift. In case, the company avail this
opportunity of double shift on filling the earth, as a result, they would be
able to save 5 weeks duration. The reduction of 5 weeks activity will also require
an additional cost of $10, 000. Now calculating its possible net profit for the
company:
Now to calculate net benefit we will
deduct the total cost amount from the possible benefit for the penalty. The
total amount of saved penalty is around $50,000. From this amount, we will
subtract the total cost of this proposal ($10,000 as stated in the case study).
After deducting additional cost required
by this proposal the net profit would be around $40, 000.
The above calculations represent that proposal
A and proposal B have almost the same net benefit for the company.
Proposal Three: The third proposal for a reduction in
time duration is concerned with the roof construction activity. In this
activity, the company was requiring 13 weeks. However, after employing
additional labour at roof construction site company can complete this activity
earlier than plan. Employing extra labour will cost $9,000 however it will
reduce original roof activity duration by 6 weeks. As a result of this, the company
would be able to save the following penalty amount.
Calculations suggest that proposal three
will generate a net benefit of $51, 000 for the company.
Proposal Selection: Considering
the above calculation work and other case scenario information, it can be said
that the company will have more monetary benefits if they select the proposal
three. By selecting this proposal company can save $11000 more than the other
proposals (proposal A and Proposal B). Both of these proposals can save only
$40,000 for the company after deducting the cost of the proposal. Conclusively,
it can be said that after analyzing I would apply proposal 3 because of higher
benefits associated with this proposal in comparison to other available
proposals. The proposal 3 not only reduce the penalty amount by a higher
percentage but also require cost lower than other available proposals. Thus,
the selection of proposal 3 is a wise decision.
Question: 3
How would your analysis change if the company factors in
the possibility of a cold-weather no-work period in the month of December?
The project is a construction based
project in which projects workers will start work from clearing the area of
construction and end after the painting of the whole constructed building on 7th
January 2022. The analysis of time duration will get change in case company
give official holidays to their employees in the month of December. According
to the developed time plan, in the month of December, workers have to work on several
activities including installation of turf and power lines installation in the
constructed building. However, according to the case study, December will have
cold weather in which employees would not be able to work properly and come to
the workplace (Kloppenborg, 2014).
Thus, in such an extreme weather
condition company would give off to their employees. While in the month of
December, project management will hold on all project-related activities. In
case, the company give official off and hold on all activities then all
activities planned to be done in the month of December will be shifted on next
month. Somehow, it would not generate impact one month activities. In fact, all
activities after the month of December will have an impact. Each activity to be
done in the month of December will be started in the month of January.
Consequently, activities due in the month of January will be started in the
month of February. Thus, the overall project will have delays and shifted one
month ahead of pre-developed time schedule. The no-work period of December will
generate a delay of 8.5 weeks for the overall project. See the following table
in which possible delays for the activities are stated in the delay column.
Activities
|
Weeks
|
Start Date
|
End Date
|
Month
|
Delay
|
Installing
turf
|
12
|
28-Sep-20
|
18-Dec-20
|
December
|
3
weeks
|
Excavating
|
4
|
21-Dec-20
|
15-Jan-21
|
January
|
1.5
weeks
|
Pouring
concrete for basement
|
4
|
18-Jan-21
|
12-Feb-21
|
Feb
|
|
construction
of the walls
|
12
|
15-Feb-21
|
7-May-21
|
May
|
|
Constructing
the roof
|
13
|
10-May-21
|
6-Aug-21
|
August
|
|
Interior
work
|
5
|
6-Aug-21
|
10-Sep-21
|
September
|
|
Approval
|
4
|
13-Sep-21
|
8-Oct-21
|
October
|
|
Power
lines
|
8
|
11-Oct-21
|
3-Dec-21
|
December
|
|
electrical
work
|
5
|
6-Dec-21
|
7-Jan-22
|
January
|
4
weeks
|
Thus, based on the above presented table it can be said that
all activities after installing turf will be shifted to the next month
respectively. The overall project completion date will be also changed from 7th
January 2022 to 8.5 weeks after it. However, the overall penalty amount will
also rise for the company. See the following calculation for the increase in
penalty:
Conclusively, it can be
said that no work period in the month of December will not be beneficial for
the company. In short, it will increase the total time duration for the project
completion. While on the other hand, it will also increase the penalty cost for
the company which is not desirable for the company. The overall analysis for
the project time duration and cost is changed as a result of this little change
of no-work period in the month of December.
Blocher. (2006). Cost Management: A Strategic
Emphasis. Tata McGraw-Hill Education.
Kloppenborg, T. J. (2014). Contemporary Project
Management. Cengage Learning.