The
report is about the Codelfa construction PTY LTD V State rail Authority of NSW(
1982)HCA 24, which was the construction contract of the railway and it was very
famous. It can also be referred to the modern construction throughout the
world. The contract is basically a court trial which was started because of seven
days working and three shifts per day, as well as the work, was so noisy and
vibrant that made the disturbance in the surrounding. This report is providing a
brief overview of the contract in which its history along with some significant
background related things are discussed which tells that the contract was
approved for 130 days. After the overview, the important facts and some issues
related to this project are provided in the relevant facts and legal issues in the
case section. The proceedings and sayings are also discussed and at the end of
this report, the case was dismissed after giving briefing by Justice Brennan.
Cordelia
Construction Pty Ltd v State Rail Authority
The
Cordelia construction is an Australian contact law case that is now become the
most valuable contact in Australia and gives as the authority for the modern
approach to the contractual construction. The case is related to the
construction company whose works had been held by the order as well as highly
influenced the eastern suburbs railway line’s development. The questions of the
frustration, parol evidence rule as well as the construction are addressed into
the terms of contract law. From the well-established English method related to
the extrinsic evidence user, the case diverged in the contractual
interpretation. Further on the overview of this contract, a tender was accepted
by the commissioner of railways through Codelfa to excavate the tunnels for
railway in New South Wales.
The
contract or the project was provided for Codelfa by certain dates to complete
the work in only 130 weeks. It was a very difficult and hard task which was
provided for Codelfa but the work had been started on this contract. The work
was commenced by Codelfa and stared three shifts in the day in the whole week
without taking any leave. The project work was heavy and the very noisy that produced
the vibrations. Furthermore, the local residents and the council led to many
applications for the injunction. With the result that Codelfa was decreased to
continue work in the tunnel for the six days of the week, it granted the
injunction. The construction teams were allowed to perform their work in only
six-day and their Sunday will be off including they are also restricted to
perform three shifts a day. It was a piece of faulty advice and common
assumption that the work will not be disturbed and restricted. To cover the cost
as well as lost profits, the additional sums were claimed by Codelfa from the
commissioner and the labor was not able to work for twenty-four hours as
estimated.
Relevant
Facts and legal Issues in case
In
this section, some important facts, as well as the legal issues with this case,
are discussed that will provide brief information that what they were difficulties
and what were the consequences in the contract. First of all, this research
report on the selected contract discusses the relevant facts as well as the
legal issues in the case. Justice Brennan had set out some significant facts
which are leading to such an argument in the judgment he made.
The
first fact is that the new south wales parliament created a corporation which
was the commissioner for the railways. The commissioner for railways was
appointed for the eastern suburb’s railway in Sydney as the construction
authority. Furthermore, it was associated with the construction by of the
contract for the two single-track tunnels excavation, the concrete lining of
tunnels, an underground excavation at the Bondi Junction station site, an open
cut excavation at the Woollahra station site, commencing at the Edgecliff and
running through Woollhara to Bondi Junction, as well as some escalator shafts
and concrete roadbed construction (Caspersz, 2012).
The tender of Codelfa for this
project was successful as well as the agreement was accomplished among Codelfa
and commissioner which subsequently state the rail authority of NSW took more than
the commission functions. Although, several types of documents including
general conditions, drawing of the project as well as construction
specification were incorporated by the contract. The agreement needed Codelfa
to begin the work on the project. The related information is given below.
According to the contract, Codelfa was
required by the contract to begin the work into sixty days after receiving
notice to proceed with the work on the project. The specific dates further
required to complete the confirm stages of work as well as to complete all of
the construction works including construction and fixing the railway tracks
into the 130 weeks. The construction program had to make as well as approve the
revision which had to adhere. Further information was also provided on this
contract that the time should be of the contract essence while the measure of
the protection was given to Codelfa if it should delay in making and approving
the contract. Some other facts are also provided in the contract that it shall
not entitle the commissioner to cancel the contract due to any kind of delays
in the project completion or the separable parts having to the reasons outside
of the contract or without the negligence of the contractor.
If
the engineer shall be notified by the contractor the cause of any kind of
defaults or the delays into the beginning of ten days in writing or into this
kind of the more period as it shall be granted by the engineer for the receipt
of the notice or the copy of the notice having the information of the causes of
delay. Furthermore, the facts, as well as the extent of the delay, shall be
ascertained by the engineer as well as extend the time of the contract to
complete the construction works when the fact results justify the extension on
the receipt of this notice form the contractor in the opinion of the engineer. Furthermore, the contract is also providing
information that the factual findings of the engineer will be final, binding as
well as conclusive on the contractor.
The
work was begun by Codelfa under the following notice for this project to proceed
with the operating shifts for three times in a single day and a total of seven days’
work or full day work. Although, the considerable noise as well as vibrations were
generated due this work and including the debris and stones blasted out of the
area at the time. The injunction was sought by the resident of Woollahra soon
after the beginning of the work as well as including the local council the
subsequently. Although, it granted injunctions that controlled the working of
Codelfa between 10 in the morning and 6 in the evening every day. While the
undertaking not to carry out the work excavation on Sunday was also given by
Codelfa subsequently. It was claimed by Codelfa from the commissioner further to
cover up the costs consumed on the project incurred as the result of not become
able to work in the three shifts in the single day or grant permission to work
on the Sunday for recovery instead of going in the loss in the contract as the
change result. The argument was made on this situation or claim discussed (Brennan, 1982).
Moreover,
it should imply the warranty in the contract for the breach in which the
damages should be recovered by Cordelia. In the other sense, the contract which
is approved for Codelfa must be held and injunction issues have frustrated including
Codelfa must recover the quantum meruit that expectedly be greater and over the
payable dues according to this contract.
Discussion on Issue of Implied
Term
All
of the high court members agreed upon the term that there was no kind of
implied term even though, it can suppose that the term was required to provide
the efficacy of the business to the contract. But it was not clearly written or
mentioned in the contract that what the parties should have agreed and the had
they changed their minds on this matter. Thus, there was no term mentioned in
the contract that might be indicated. So, it was clear that it was going
without any saying. In the discussion of the criteria for the term’s
implication, Justice Brannan did refer it with the approval to the judgment of
the high court in paragraph 20 insecure income real estate v St Martin’s
investments Pty Ltd [1979].
·
It should be equitable as well as reasonable
·
It should also be essential to provide the
efficacy of the business to the contract. That’s why no any kind of term will
be implied if the contract is active without it.
·
It must also be very obvious that it also goes
without any saying
·
Should also have the ability for the clear
expression
·
And, it should not express any contract term on
the contrary context.
Discussion on the Issue of
Frustration
The
majority of the high court members thought considered that the Codelfa contract
has been frustrated as dissented on this point by Justice Brennan. The main
question or problem in this contract whether the resulting condition forms the
injunctions were different fundamentally from the expected by the contract. So,
Justice Mason also state on paragraph 55 on the basis of the arbitrator factual
findings that;
“The contract performance in the
occurred even was is fundamentally different than the contract performance in
the circumstance as well as it interpreted and contemplated in the surrounding
circumstances.”
On
the law of the frustration, it was referred by his honor to the variety of
authorities as well as also highlighted that he did also agree and satisfied with
the adopted the approach by Lord the Redcliffe and Lord Reid in the Devis
contractors. At the paragraph number 40, Lord Redcliffe (1956) AC said at page
729 that; “ Frustration happens at whatever point the law perceives that
without default of either party a legally binding commitment has gotten
unequipped for being performed in light of the fact that the conditions wherein
execution is called for would render it a thing fundamentally not the same as
that which was embraced by the agreement. It was not this that I vowed to do”
The cases were proceeding in the
court where Judges were attentively listening to the whole case saying. Justice
Brennan was very strong in his point because he has given several reasons for
frustrations and other reasons for restrictions in the working of the project.
He also highlighted another important point that the engineer who is hired to
proceed with the construction work did not cease the work in the tunnels
because he had no kind of instructions of law or order in the written from the
contractor. So, the engineer had not stopped the work into the tunnels.
Furthermore, due to the problem in the working shifts, Codelfa did claim again
that there is not any kind of implication in the contract. Thus, in the
proceeding of this case, his honor continued on the issue criteria.
In
response to the claim from the party that the contract was frustrated at the
time of ordering the injunction. Into the further proceeding, it was also
referred then by his honor at the page of 30 to Lord Radcliffe's judgment in
the “ Davis
Contractors Ltd v Fareham Urban District Council [1956] UKHL 3 (1956) AC 696,
at p 729,” that highlighted and mentioned that the frustration will happen or
generated; “ At the time of the law perceives that without default of either
party a legally binding commitment has gotten unequipped for being performed because
the conditions wherein execution is called for would render it a thing
fundamentally not the same as that which was attempted by the agreement. Non
haec in foedera veni. It was not this that I vowed to do.”
After the proceeding, his honor
concluded by the judges listening to his saying and analyzing his pieces of
evidence on the frustrations and the frustrative actions. They rightly
dismissed.
Conclusion of Codelfa
construction PTY LTD V State rail Authority of NSW (1982) HCA 24
It is concluded that the Cordelia
construction is an Australian contact law case that is now become the most
valuable contact in Australia and gives as the authority for the modern
approach to the contractual construction. The work was commenced by Codelfa and
stared three shifts in the day in the whole week without taking any leave. To
cover the cost as well as lost profits, the additional sums were claimed by
Codelfa from the commissioner and the labor was not able to work for
twenty-four hours as estimated. The new south wales parliament created a
corporation which was the commissioner for the railways. The tender of Codelfa
for this project was successful as well as the agreement was accomplished among
Codelfa and commissioner which subsequently state the rail authority of NSW
took more than the commission functions. Codelfa was required by the contract
to begin the work into sixty days after receiving notice to proceed with the
work on the project. While the undertaking not to carry out the work excavation
on Sunday was also given by Codelfa subsequently. It should imply the warranty
in the contract for the breach in which the damages should be recovered by
Cordelia. The main question or problem in this contract whether the resulting
condition forms the injunctions were different fundamentally from the expected
by the contract. Due to the problem in the working shifts, Codelfa did claim
again that there is not any kind of implication in the contract.
References of Codelfa construction PTY LTD V State
rail Authority of NSW (1982) HCA 24
Brennan, J. (1982). Codelfa Construction Pty Ltd v
State Rail Authority of NSW [1982] HCA 24; (1982) 149 CLR 337 (11 May 1982). CODELFA
CONSTRUCTION PTY. LTD. v. STATE RAIL AUTHORITY OF N.S.W.
Caspersz, T. (2012). Do contracts mean what they say? This
article was first published in the June 2012 issue of the Australian Corporate
Lawyer, 26.