GanttChart
Gantt Chart Version 1.7.3 © 2006-2014 Vertex42 LLC
Vertex42: Terms of Use and Copyright: See the Terms Of Use worksheet and the license agreement on Vertex42.com. Copyright notices may not be removed. 0
HELP
[Automation of Supply Chain Management System]
Ray & Young Inc. Today's Date: 10/22/15 Thursday
(vertical red line)
Project Lead: Rodney Wheeler [42]
Start Date: 10/22/15 Thursday
[42] First Day of Week (Mon=2): 2 10/19/15 10/20/15 10/21/15 10/22/15 10/23/15 10/24/15 10/25/15 10/26/15 10/27/15 10/28/15 10/29/15 10/30/15 10/31/15 11/1/15 11/2/15 11/3/15 11/4/15 11/5/15 11/6/15 11/7/15 11/8/15 11/9/15 11/10/15 11/11/15 11/12/15 11/13/15 11/14/15 11/15/15 11/16/15 11/17/15 11/18/15 11/19/15 11/20/15 11/21/15 11/22/15 11/23/15 11/24/15 11/25/15 11/26/15 11/27/15 11/28/15 11/29/15 11/30/15 12/1/15 12/2/15 12/3/15 12/4/15 12/5/15 12/6/15 12/7/15 12/8/15 12/9/15 12/10/15 12/11/15 12/12/15 12/13/15 12/14/15 12/15/15 12/16/15 12/17/15 12/18/15 12/19/15 12/20/15 12/21/15 12/22/15 12/23/15 12/24/15 12/25/15 12/26/15 12/27/15 12/28/15 12/29/15 12/30/15 12/31/15 1/1/16 1/2/16 1/3/16 1/4/16 1/5/16 1/6/16 1/7/16 1/8/16 1/9/16 1/10/16 1/11/16 1/12/16 1/13/16 1/14/16 1/15/16 1/16/16 1/17/16 1/18/16 1/19/16 1/20/16 1/21/16 1/22/16 1/23/16 1/24/16 1/25/16 1/26/16 1/27/16 1/28/16 1/29/16 1/30/16 1/31/16 2/1/16 2/2/16 2/3/16 2/4/16 2/5/16 2/6/16 2/7/16 2/8/16 2/9/16 2/10/16 2/11/16 2/12/16 2/13/16 2/14/16 2/15/16 2/16/16 2/17/16 2/18/16 2/19/16 2/20/16 2/21/16 2/22/16 2/23/16 2/24/16 2/25/16 2/26/16 2/27/16 2/28/16 2/29/16 3/1/16 3/2/16 3/3/16 3/4/16 3/5/16 3/6/16 3/7/16 3/8/16 3/9/16 3/10/16 3/11/16 3/12/16 3/13/16 3/14/16 3/15/16 3/16/16 3/17/16 3/18/16 3/19/16 3/20/16 3/21/16 3/22/16 3/23/16 3/24/16 3/25/16 3/26/16 3/27/16 3/28/16 3/29/16 3/30/16 3/31/16 4/1/16 4/2/16 4/3/16 4/4/16 4/5/16 4/6/16 4/7/16 4/8/16 4/9/16 4/10/16 4/11/16 4/12/16 4/13/16 4/14/16 4/15/16 4/16/16 4/17/16 4/18/16 4/19/16 4/20/16 4/21/16 4/22/16 4/23/16 4/24/16 4/25/16 4/26/16 4/27/16 4/28/16 4/29/16 4/30/16 5/1/16 5/2/16 5/3/16 5/4/16 5/5/16 5/6/16 5/7/16 5/8/16 5/9/16 5/10/16 5/11/16 5/12/16 5/13/16 5/14/16 5/15/16 5/16/16 5/17/16 5/18/16 5/19/16 5/20/16 5/21/16 5/22/16 5/23/16 5/24/16 5/25/16 5/26/16 5/27/16 5/28/16 5/29/16 5/30/16 5/31/16 6/1/16 6/2/16 6/3/16 6/4/16 6/5/16 6/6/16 6/7/16 6/8/16 6/9/16 6/10/16 6/11/16 6/12/16
WBS
Jon: Work Breakdown Structure Level 1: 1, 2, 3, ... Level 2: 1.1, 1.2, 1.3, ... Level 3: 1.1.1, 1.1.2, 1.1.3, … The WBS is automatically entered, but the formulas are different for different levels. Tasks Task Lead Start
Jon: Start Date Enter the starting date for this task. To associate the start date with the end of another task, enter a formula in the start date that refers to the end date of that task. End
Jon: End Date The ending date is calculated by adding the Duration (calendar days) to the Start date minus 1 day, because the task duration is from the beginning of the Start day to the end of the End day. Duration (Days)
Jon: Duration (Calendar Days) Enter the number of calendar days for the given task. Refer to the Working Days column or use a calendar to determine the corresponding working days. The duration is from the beginning of the Start date to the ending of the End Date. When the duration is calculated, it is calculated as End Date minus the Start Date plus 1 day, so that a task starting and ending on the same day has a duration of 1 day. % Complete
Jon: Percent Complete Update the status of this task by entering the percent complete (between 0% and 100%). Working Days
Jon: Working Days Counts the number of working days using the NETWORKDAYS() formula, which excludes weekends. When planning work based upon the number of working days, adjust the Duration until the desired # of working days is reached. Days Complete
Jon: Calendar Days Complete This column is calculated by multiplying the Duration by the %Complete and rounding down to the nearest integer. Days Remaining
Jon: Calendar Days Remaining This column is calculated by subtracting the Days Complete from the Duration. 19 - Oct - 15 26 - Oct - 15 02 - Nov - 15 09 - Nov - 15 16 - Nov - 15 23 - Nov - 15 30 - Nov - 15 07 - Dec - 15 14 - Dec - 15 21 - Dec - 15 28 - Dec - 15 04 - Jan - 16 11 - Jan - 16 18 - Jan - 16 25 - Jan - 16 01 - Feb - 16 08 - Feb - 16 15 - Feb - 16 22 - Feb - 16 29 - Feb - 16 07 - Mar - 16 14 - Mar - 16 21 - Mar - 16 28 - Mar - 16 04 - Apr - 16 11 - Apr - 16 18 - Apr - 16 25 - Apr - 16 02 - May - 16 09 - May - 16 16 - May - 16 23 - May - 16 30 - May - 16 06 - Jun - 16
1 Initiation Andrew Ray 1/2/15 1/16/15 15 0% 11 0 15
1.1 Charter Development 1/2/15 1/5/15 4 0% 2 0 4
1.2 Scope Definition 1/2/15 1/4/15 3 0% 1 0 3
1.2.1 Preliminary definition 1/4/15 1/5/15 2 0% 1 0 2
1.2.2 Final definition 1/6/15 1/7/15 2 0% 2 0 2
1.3 Defining objectives 1/7/15 1/7/15 1 0% 1 0 1
1.4 Mission statements 1/11/15 1/11/15 1 0% 0 0 1
2 Planning Andrew Ray 1/1/15 1/24/15 24 25% 17 6 18
2.1 Setting up the project 1/1/15 1/5/15 5 25% 3 1 4
2.2 Scope Definition 1/4/15 1/8/15 5 25% 4 1 4
2.3 Develop Project schedule 1/9/15 1/13/15 5 25% 3 1 4
2.4 Develop risk plan 1/14/15 1/22/15 9 2