Conveyor Belt Project
Part 1
Project Description
The new computer-controlled conveyor belt is an exciting project that moves and positions items on the conveyor belt within <1 millimeter. The project will produce a new system for future installations, and for replacement of those in the field, at a low cost. The computer-controlled conveyor belt has the potential to be a critical unit in 30 percent of the systems installed in factories. The new system is also easier to update with future technologies.
The Project Priority Matrix for the Conveyor Belt Project (CBP) is:
Time
Scope
Cost
Constrain
X
Enhance
X
Accept
X
Table A2.9 has been developed for you to use in completing the project exercises.
TABLE A2.9 Conveyor Belt Project; WBS
Conveyor Belt Project
Hardware
Hardware specifications
Hardware design
Hardware documentation
Prototypes
Order circuit boards
Assemble preproduction models
Operating system
Kernel specifications
Drivers
Disk drivers
Serial I/O drivers
Memory management
Operating system documentation
Network interface
Utilities
Utilities specifications
Routine utilities
Complex utilities
Utilities documentation
Shell
System integration
Architectural decisions
Integration first phase
System hard/software test
Project documentation
Integration acceptance testing
Assignment
Develop the WBS outline using the software available to you.
Question
Does this information (WBS) allow you to define any milestones of the project? Why or why not? What are they?
Remember: Save your file for future exercises!
Page 627
Part 2
Use your file from Part 1 and the information provided below to complete this exercise. (See Table A2.10 .)
TABLE A2.10 Conveyor Belt Project; Schedule
Activity
Description
Resource
Duration (days)
Preceding Activity
1
Architectural decisions
Design
25
—
2
Hardware specifications
Development, design
50
1
3
Kernel specifications
Design
20
1
4
Utilities specifications
Development, design
15
1
5
Hardware design
Design, development
70
2
6
Disk drivers
Assembly, development
100
3
7
Memory management
Development
90
3
8
Operating system documentation
Design, documentation
25
3
9
Routine utilities
Development
60
4
10
Complex utilities
Development
80
4
11
Utilities documentation
Documentation, design
20
4
12
Hardware documentation
Documentation, design
30
5
13
Integration first phase
Assembly, development
50
6,7,8,9,10,11,12
14
Prototypes
Assembly, development
80
13
15
Serial I/O drivers
Development
130
13
16
System hard/software test
Assembly
25
14,15
17
Order circuit boards
Purchasing
5
16
18
Network interface
Development
90
16
19
Shell
Development
60
16
20
Project documentation
Documentation, development
50
16
21
Assemble preproduction models
Assembly, development
30
17F-S, lag 50 days
22
Integrated acceptance testing
Assembly, development
60
18,19,20,21
Note: F-S refers to a Finish-to-Start lag.
1. Each work package will represent an activity.
2. The project begins January 4, 2010.
3. The following holidays are observed: January 1, Memorial Day (last Monday in May), July 4th, Labor Day (first Monday in September), Thanksgiving Day (4th Thursday in November), December 25 and 26.
4. If a holiday falls on a Saturday then Friday will be given as an extra day off, and if it falls on a Sunday, then Monday will be given as a day off.
5. The project teams work eight-hour days, Monday through Friday.
Warning: Experience has taught students to frequently make separate backup files for each exercise. The software is never as friendly as users expect!
Construct a network schedule for the conveyor belt project and prepare a memo that addresses the following questions:
1. When is the project estimated to be completed? How long will the project take?
2. What is the critical path(s) for the project?
3. Which activity has the greatest amount of slack?
4. How sensitive is this network?
5. Identify two sensible milestones and explain your choices.
6. Compare the advantages/disadvantages of displaying the schedule as a network versus a Gantt chart.
Page 628
Include the following printouts:
· A Gantt chart.
· A network diagram highlighting the critical path.
· A schedule table reporting ES, LS, EF, LF, and slack for each activity.
Hint: the project should be completed in 530 days.
Remember: Save your file for future exercises!
Part 3
Remember the old saying, “A project plan is not a schedule until resources are committed.” This exercise illustrates this subtle, but very important, difference.
Part A
Using your files from Part 2 input resources and their costs if you have not already done so. All information is found in Tables A2.10 and A2.11 .
TABLE A2.11 Organization Resources
Name
Group
Cost ($/hr)
Design
R&D (2 teams)
$100
Development
R&D (2 teams)
70
Documentation
R&D (1 team)
60
Assembly/test
R&D (1 team)
70
Purchasing
Procurement (1 team)
40
Page 629
Prepare a memo that addresses the following questions:
1. Which if any of the resources are overallocated?
2. Assume that the project is time constrained and try to resolve any overallocation problems by leveling within slack. What happens?
3. What is the impact of leveling within slack on the sensitivity of the network?
Include a Gantt chart with the schedule table after leveling within slack.
4. Assume the project is resource constrained and resolve any overallocation problems by leveling outside of slack. What happens? What are the managerial implications?
5. What options are available at this point in time?
Include a Gantt chart with the schedule table after leveling outside of slack.
Note: No splitting of activities is allowed.
Note: No partial assignments (e.g., 50 percent). All resources must be assigned 100 percent.
Part B
When you show the resource-constrained network to top management, they are visibly shaken. After some explanation and negotiation they make the following compromise with you:
· The project must be completed no later than February 2, 2012 (530 days).
· You may assign two additional development teams.
· If this does not suffice, you may hire other development teams from the outside. Hire as few external teams as possible because they cost $50 more per hour than your inside development people.
Internal Development
Add as many development units (teams) as needed to stay within the 530 days. If you need more than two internal development units, then hire as few external teams as necessary. Select the cheapest possibility! Change as few activities as possible. It is recommended you keep work packages which require cooperation of several organizational units inside your company. You decide how best to do this.
Hint: Undo leveling prior to adding new resources.
Once you have obtained a schedule that meets the time and resource constraints, prepare a memo that addresses the following questions:
1. What changes did you make and why?
2. How long will the project take?
3. How did these changes affect the sensitivity of the network?
Include a Gantt chart with a schedule table presenting the new schedule.
Applied Sciences
Architecture and Design
Biology
Business & Finance
Chemistry
Computer Science
Geography
Geology
Education
Engineering
English
Environmental science
Spanish
Government
History
Human Resource Management
Information Systems
Law
Literature
Mathematics
Nursing
Physics
Political Science
Psychology
Reading
Science
Social Science
Home
Blog
Archive
Contact
google+twitterfacebook
Copyright © 2019 HomeworkMarket.com