CASE19
CASE 20	Instructor Version	Copyright 2014 Health Administration Press
11/23/16
CORAL BAY HOSPITAL
Traditional Project Analysis
This case illustrates a complete capital budgeting analysis, including cash flow analysis,
and profitability measures. Note that the model extends to Column I.
The model consists of a complete base case analysis--no changes need to be made
to the existing MODEL-GENERATED DATA section. However, all values in the student
version INPUT DATA section have been replaced with zeros. Thus, students must determine
the appropriate input values and enter them into the model. These cells are colored red.
When this is done, any error cells will be corrected and the base case solution will appear.
Note that the student version does not contain any risk analyses, so students will have to
create their own if required by the case. Furthermore, students must create their own
graphics (charts) as needed to present their results.
The instructor version of the model contains an inflation table, sensitivity analysis,
and scenario analysis, which are not included in the student version. A graph of the sensitivity
analysis is contained on the second sheet.
INPUT DATA:	KEY OUTPUT:
Land initial cost	$150,000	NPV	$875,020
Land opportunity cost (and salvage value)	$200,000	IRR	12.9%
Building/equipment cost	$10,000,000	MIRR	11.8%
Build/equipment salvage value	$5,000,000	Payback	4.1
Procedures per day	20.0
Average net patient revenue per procedure	$1,000
Labor costs	$918,000
Utilities costs	$50,000
Incremental overhead	$36,000
Supply cost ($/procedure)	$200
Inflation rate on net patient revenue	3.0%
Inflation rate on costs	3.0%
Tax rate	40.0%
Revenues lost from inpatient surgeries	$1,000,000
Reduction in inpatient surgery costs	$500,000
Cost of capital	10.0%
MODEL-GENERATED DATA:
Depreciation Schedule:
MACRS	Deprec.	End of Year
Year	Factor	Expense	Book value
1	0.20	$2,000,000	$8,000,000
2	0.32	3,200,000	4,800,000
3	0.19	1,900,000	2,900,000
4	0.12	1,200,000	1,700,000
5	0.11	1,100,000	600,000
6	0.06	600,000	0
Net Cash Flows:
Project Cash Flows
0	1	2	3	4	5
Land opportunity cost	($200,000)
Building/equipment cost	(10,000,000)
Net patient revenue (including inpatient loss)	$4,000,000	$4,120,000	$4,243,600	$4,370,908	$4,502,035
Less: Labor costs	918,000	945,540	973,906	1,003,123	1,033,217
Cost savings on inpatients	(500,000)	(515,000)	(530,450)	(546,364)	(562,754)
Utilities costs	50,000	51,500	53,045	54,636	56,275
Supplies	1,000,000	1,030,000	1,060,900	1,092,727	1,125,509
Incremental overhead	36,000	37,080	38,192	39,338	40,518
Depreciation	2,000,000	3,200,000	1,900,000	1,200,000	1,100,000
Income before taxes	$496,000	($629,120)	$748,006	$1,527,447	$1,709,270
Taxes	198,400	(251,648)	299,203	610,979	683,708
Project net income	$297,600	($377,472)	$448,804	$916,468	$1,025,562
Plus: Depreciation	2,000,000	3,200,000	1,900,000	1,200,000	1,100,000
Plus: Net land salvage value	180,000
Plus: Net building/equipment salvage value	3,240,000
Net cash flow	($10,200,000)	$2,297,600	$2,822,528	$2,348,804	$2,116,468	$5,545,562
Cumulative net cash flow	($10,200,000)	($7,902,400)	($5,079,872)	($2,731,068)	($614,600)	$4,930,962
(For payback calculation)
Profitability and Breakeven Measures:
Net present value (NPV)	$875,020
Internal rate of return (IRR)	12.9%
Modified IRR (MIRR)	11.8%
Payback	4.1
Impact of Uncertain, Future Inflation on NPV:
Level of Net Patient Revenue Inflation
$875,020	0%	1%	2%	3%	4%	5%	6%
0%	557,808	724,065	893,501	1,066,160	1,242,091	1,421,339	1,603,952
1%	495,296	661,553	830,988	1,003,648	1,179,578	1,358,826	1,541,440
Level of Cost	2%	431,588	597,845	767,280	939,940	1,115,870	1,295,119	1,477,732
Inflation	3%	366,668	532,925	702,360	875,020	1,050,950	1,230,199	1,412,812
4%	300,518	466,775	636,210	808,870	984,801	1,164,049	1,346,662
5%	233,121	399,378	568,813	741,473	917,403	1,096,651	1,279,265
6%	164,458	330,715	500,150	672,810	848,741	1,027,989	1,210,602
Sensitivity Analysis:
(Note: This table does NOT automatically recalculate when input values are changed.)
Number of	Avg Revenue	Bldg/Equip
Procedures	per Procedure	Salvage Value
-30%	(2,006,852)	(2,727,320)	$316,191
-20%	(1,046,228)	(1,526,540)	502,467
-10%	(85,604)	(325,760)	688,744
0%	875,020	875,020	875,020
10%	1,835,644	2,075,800	1,061,296
20%	2,796,268	3,276,580	1,247,573
30%	3,756,892	4,477,360	1,433,849
Scenario Analysis:
(Note: This section does NOT automatically recalculate when values in the INPUT DATA section are
changed. However, the probabilities within the section can be changed and the resulting values
will automatically be recalculated.)
Number of	Avg Revenue	Bldg/Equip
Case	Probability	Procedures	per Procedure	Salvage Value	NPV
Worst	25.0%	10	$800	$4,000,000	($5,501,433)
Most Likely	50.0%	20	1,000	5,000,000	875,020
Best	25.0%	25	1,200	6,000,000	6,651,083
100.0%
Expected NPV	$724,922
Standard Deviation	$4,299,184
Coefficient of Variation	5.9
END
equipment salvage value
CASE 20	Instructor Version	Copyright 2014 Health Administration Press
11/23/16
CORAL BAY HOSPITAL
Traditional Project Analysis
This case illustrates a complete capital budgeting analysis, including cash flow analysis,
and profitability measures. Note that the model extends to Column I.
The model consists of a complete base case analysis--no changes need to be made
to the existing MODEL-GENERATED DATA section. However, all values in the student
version INPUT DATA section have been replaced with zeros. Thus, students must determine
the appropriate input values and enter them into the model. These cells are colored red.
When this is done, any error cells will be corrected and the base case solution will appear.
Note that the student version does not contain any risk analyses, so students will have to
create their own if required by the case. Furthermore, students must create their own
graphics (charts) as needed to present their results.
The instructor version of the model contains an inflation table, sensitivity analysis,
and scenario analysis, which are not included in the student version. A graph of the sensitivity
analysis is contained on the second sheet.
INPUT DATA:	KEY OUTPUT:
Land initial cost	$150,000	NPV	$0
Land opportunity cost (and salvage value)	$200,000	IRR	10.0%
Building/equipment cost	$10,000,000	MIRR	10.0%
Build/equipment salvage value	$2,651,286	Payback	4.1
Procedures per day	20.0
Average net patient revenue per procedure	$1,000
Labor costs	$918,000
Utilities costs	$50,000
Incremental overhead	$36,000
Supply cost ($/procedure)	$200
Inflation rate on net patient revenue	3.0%
Inflation rate on costs	3.0%
Tax rate	40.0%
Revenues lost from inpatient surgeries	$1,000,000
Reduction in inpatient surgery costs	$500,000
Cost of capital	10.0%
MODEL-GENERATED DATA:
Depreciation Schedule:
MACRS	Deprec.	End of Year
Year	Factor	Expense	Book value
1	0.20	$2,000,000	$8,000,000
2	0.32	3,200,000	4,800,000
3	0.19	1,900,000	2,900,000
4	0.12	1,200,000	1,700,000
5	0.11	1,100,000	600,000
6	0.06	600,000	0
Net Cash Flows:
Project Cash Flows
0	1	2	3	4	5
Land opportunity cost	($200,000)
Building/equipment cost	(10,000,000)
Net patient revenue (including inpatient loss)	$4,000,000	$4,120,000	$4,243,600	$4,370,908	$4,502,035
Less: Labor costs	918,000	945,540	973,906	1,003,123	1,033,217
Cost savings on inpatients	(500,000)	(515,000)	(530,450)	(546,364)	(562,754)
Utilities costs	50,000	51,500	53,045	54,636	56,275
Supplies	1,000,000	1,030,000	1,060,900	1,092,727	1,125,509
Incremental overhead	36,000	37,080	38,192	39,338	40,518
Depreciation	2,000,000	3,200,000	1,900,000	1,200,000	1,100,000
Income before taxes	$496,000	($629,120)	$748,006	$1,527,447	$1,709,270
Taxes	198,400	(251,648)	299,203	610,979	683,708
Project net income	$297,600	($377,472)	$448,804	$916,468	$1,025,562
Plus: Depreciation	2,000,000	3,200,000	1,900,000	1,200,000	1,100,000
Plus: Net land salvage value	180,000
Plus: Net building/equipment salvage value	1,830,772
Net cash flow	($10,200,000)	$2,297,600	$2,822,528	$2,348,804	$2,116,468	$4,136,334
Cumulative net cash flow	($10,200,000)	($7,902,400)	($5,079,872)	($2,731,068)	($614,600)	$3,521,733
(For payback calculation)
Profitability and Breakeven Measures:
Net present value (NPV)	$0
Internal rate of return (IRR)	10.0%
Modified IRR (MIRR)	10.0%
Payback	4.1
Impact of Uncertain, Future Inflation on NPV:
Level of Net Patient Revenue Inflation
$0