I Have To Do The List Activity , AON ,PERT And The Budget Of The Project
whoever know how to do this in project management course by excel and then paste it on word.. it's a small part.. the list of activities based on the WBS elements name.. thanks
Running head: WBS Assignment 1
WBS Assignment 14
WBS Assignment
Wedding Plan for Mary & Justin
Xunzhen Wu – 301115184
Pawan singh sahota -301088222
Moayad Harbi- 301112470
August 15, 2020
Table of Contents 1. Introduction 3 2. Work Breakdown Structure (WBS) 3 2.1 WBS Tree Diagram 4 2.2 WBS Tabular View and Definition 4 3. List of Activities 5 3.1 Determination of Timing of Activities 5 3.2 Budget Requirement of Activities 5 3.3 Activity on Node 5 3.4 Program Evaluation Review Technique (PERT) and Critical Path 5 4. Project 5 4.1 Imitative 5 4.2 Planning 5 4.3 Execution 5 4.4 Closing 5 5. Appendix 5
1. Introduction
This report illustrates the network diagram with work breakdown structures for Mary and Justin’s wedding plan. Work Breakdown Structure (WBS) is the tool that project work breaks into small tasks to manage, which is one of most important project management documents to integrate scope, cost and schedule baselines to ensure the alignment of project plans, according to Project Management Book of Knowledge (PMBOK). Meanwhile, more activities details will be analyzed with the activity list related to the duration and variance, activity on node (AON),
program evaluation and review technique (PERT), critical path on the schedule and budget requirements based on each activity. Accordingly, the wedding for Mary and Justin could be proceeded on time and under budget in accordance with their approval.
Mary and Justin expect the whole wedding theme, schedule, venue, party, wedding preparations for the guests, materials arrangement as well as the whole wedding process in church registration and ceremony like typical Canadian style for one of their most memorable days. Thus, completion of each activity is very critical to lead to the success of the wedding plan regardless of the deliverables in the wedding day and achievements of the scope, schedule, cost and service satisfaction of the whole wedding plan.
2. Work Breakdown Structure (WBS)
WBS separates the tasks with the hierarchical structure including products, materials, services, equipment, venues, service provider, facilities and all related activities in the task. Each task under the hierarchical structure makes up the whole project elements, which contributes to the project scope and deliverables. Project team could use WBS to track the project status as well as the monitoring the project completion status, while task or workstream leader is in charge of each task. Please help refer to below WBS tree diagram and tabular diagram for Mary and Justin’s wedding, details attached in excel.
2.1 WBS Tree Diagram
The WBS tree diagram breaks down the project objective into the measurable and deliverable tasks as an outline of an integrated information system. The detailed WBS is attached excel.
2.2 WBS Tabular View and Definition
The WBS tabular view provides levels of each task based on WBS structure, and project team could use WBS tabular view to define the details of the task as well.
Level
WBS Code
Element Name
Definition
1
1
Mary and Justin's Wedding Plan Project
Plan for the whole wedding day in church and ceremony
2
1.1
Marriage planning
Plan phase for the marriage with customer expectation
3
1.1.1
Plan wedding budget
The total budget for the marriage
3
1.1.2
Venue selection
The venues expectation for the marriage
3
1.1.3
Determine Guests list
Assess how many guests to invite
2
1.2
Inviting Guests
Invite guests for wedding
3
1.2.1
Finalize the guest list
Determine the guest list for the venue’s preparation
3
1.2.2
Design invitation letter
Pick up the style of invitation letter
3
1.2.3
Order invitation letters
Purchase the invitation letter
3
1.2.4
Send out invitation letters
Send out the invitation letter to all guests at least one month earlier
2
1.3
Venues
Determine venues
3
1.3.1
Wedding ceremony location
Pick up the ceremony location
4
1.3.1.1
Reserve ceremony hotel
Pay the deposit for ceremony hotel
4
1.3.1.2
Confirm menu
Pick up the food menu
4
1.3.1.3
Table Decoration
Request the hotel on the table decoration
4
1.3.1.4
Purchase wedding cakes
Book up the wedding cake for wedding day
4
1.3.2
Wedding church location
Pick up the wedding church location
4
1.3.2.1
Confirm wedding theme
Determine themes for church registration
4
1.3.2.2
Visits churches
Pick up the church per expectation
4
1.3.2.3
Reserve church
Pay the deposit for church and the date
4
1.3.2.4
Purchase Flowers
Book the flowers for wedding day
2
1.4
Photography and Video
Determine the photography and videographer
3
1.4.1
Choose photographer& videography
Finalize the service provider for photo and video
3
1.4.2
Discuss on the photography album and videography
Review the photo album styles
3
1.4.3
Review demos and finalize the wedding photo and video styles
Determine the photo style
3
1.4.4
Shoot photos for wedding
Take the pictures one month before wedding day
2
1.5
Entertainment
Arrange entertainment
3
1.5.1
Reserve wedding band
Finalize the wedding band
3
1.5.2
Rent audio package in hotel and DJ
Finalize the audio equipment
3
1.5.3
Book the host for ceremony
Pick up the ceremony host
2
1.6
Preparation on wedding
Prepare for the outfit, transportation and do rehearsal for the wedding day
3
1.6.1
Wedding outfit
Purchase outfit for the wedding day
4
1.6.1.1
Purchase wedding rings
Make sure customized wedding rings in place at least one week before wedding day
4
1.6.1.2
Purchase wedding jewelry
Make sure customized wedding jewelry in place at least one week before wedding day
4
1.6.1.3
Purchase wedding dress for Bride and Bridegroom
Make sure customized wedding dress in place at least one week before wedding day
3
1.6.2
Wedding Transportation
Finalize the transportation
4
1.6.2.1
Book the rental transportation for wedding
Pay the deposit of the transportation rental for guests and bride/broom
4
1.6.2.2
Book up travel agency for honeymoon
Pay the deposit for the honeymoon travel
2
1.7
Wedding day
confirm the process on wedding day
3
1.7.1
Make up and do hairiness
Brides and Broom take the makeup and hairiness
3
1.7.2
Church registration
Marriage register in church
3
1.7.3
Wedding Ceremony
Celebrate the wedding with guests
3
1.7.4
Wedding dinner
Celebrate the dinner with guests
3. List of Activities
3.1 Determination of Timing of Activities
3.2 Budget Requirement of Activities
3.3 Activity on Node
3.4 Program Evaluation Review Technique (PERT) and Critical Path
Project Initiation
Initiation is the first part of our project in which our company will arrange the meeting to make the final approval for the plan that are made for all the events .In this meeting we will discuss and let the clients know what will be the arrangements for every event and budget will be discussed in this meeting.
1. Evaluations and Recommendations: - In this part our company will evaluate all resources that are needed for the events and also recommend to the customers new ideas related their events.
2. Developing the charter for clients and group: - Next part after evaluation part is developing the charter that will help the staff of wedding planning company to look on each task for the events. In this charter we will add the terms and conditions for the client and get the sign from the clients from trustworthy point. Moreover, tasks and duties will be written in this charter for the wedding planners to be followed.
3. Project charter signed and approval: - This is time to get the final approval and getting the signs from the clients on the contract that we will make for all tasks. We will submit our charter to the client for review so that they can let us know if they need any changes in it.
Planning
1.Create Preliminary scope statement: - This is kind of contract between sponsors and clients for completing the work on time. This statement consists of objectives and all deliverables that company needs to perform on given time and within given budget. This contract works as a mutual understanding and the trustworthiness among the parties.
2. Develop project plan: - this is the paramount part of the project planning in this part plans and ideas related project needs to be developed by the sponsor and if there is needs to change something that can be done and new ideas can be developed.
3.Submit project plan: - once the final project plan got approved by all staff members and the directors its time to submit the plan for final approval for all the activities and this is approved by authority and the party for whom all events.
4. Booking the items: - This is time when our company will decide all the elements that are needed to complete the project successfully like catering, sound, security, liquor certificate, photographer, makeup artist, fashion designer and marriage hall.
Execution
1 Meeting with vendors: - Now this is time to execute the plans that are above mentioned in the WBS. First of all, we will check our budget then will be starting to spend the money. then we will meet with banquet hall manager for the booking of hall for all events. Then we will go to the garment shops and to the fashion designer and any agency that will be good in decorating the halls for events.
2.Design system :- Designing the whole decoration is also needed to show to clients by making the demos if this will not work then we will make graphics for the designs so that clients can see and let us know if they need any addition in it and we will have book of designs for clients.
3. Procure hardware and software:- This is main part of all events arrangements of hardware objects are crucial such as catering , cutleries , tables and chairs, stage for live concert, decoration and for software objects we will arrange some LEDs in marriage that will show pictures and pre wedding shoot and without music marriage is more like conference hall .
4.Arranging the fashioner designer and make up artist for bride and bridegroom: - As on the day of wedding day both couples have to look attractive as it is special day for them in order to make their day special, we will arrange top class artist for makeup and best designers for clothes.
5. Setting up beverages and bar stations: - in all events our company will arrange two station for the drinks one will be of all drinks that consist of alcohol and other one will be for soft drinks and for all tropical and other juices or for refreshments.
Closeout
The actual purpose of closing part in the project is to check the actual performance with standard set and other thing that can checked and does the whole project completed as it was planned. Even with this step our company can get feedbacks too and tasks can be redesigned as per the staff. At last we will handover the reports related budget closing activities and personal identification to the customers.
1. Audit Procurement :- In this step our company will audit means will check all financial balances and look after all expenses we did and the purpose of doing this is not only to make the trust with clients its good for the company to know that how much we are spending and how we can control that.
2. Document lesson learned: - This document will be proof of feedback from the clients and with this feedback from clients and with this feedback we can find out our negative and positive elements for our project. After this, this document will be available to all team members so that they can refer to it and can do as per the needs.
3. Update files and records :- we can use the feedback of customers as a primary record because the reviews of customers matter a lot and what else we need to do is update all the balance and make the hard and soft copy so that our company can use in future to show our service standard to the customers.
4. Financial Reports closeout: - At last our company will take help of accounting to balance all financial records that will show the actual financial condition of our company and for proof each receipt will be attached with financial records. At last contract will sign the contract and will do payment if any and then its time to close financial accounts.
4. Appendix