Question 1
If the schedule variance is positive and the cost variance is negative, the project’s status is:
a.
Under budget and behind schedule
b.
Under budget and ahead of schedule
c.
Over budget and behind schedule
d.
Over budget and ahead of schedule
Question 2
If PV = $100, EV = $200, and AC = $300, the status is:
a.
Over budget and ahead of schedule
b.
Under budget and ahead of schedule
c.
Under budget and behind schedule
d.
Over budget and behind schedule
Question 3
Consider the following: BAC = $1000, VAC = <$200>, and AC = $400. Therefore, SV = _____.
a.
$480
b.
$600
c.
$800
d.
cannot be determined
Question 4
The form that is used to establish charge numbers is the:
a.
Cost account change notice
b.
Work package
c.
Work authorization form
d.
Responsibility assignment matrix
Question 5
The best method to price out a work package is to use the:
a.
Statistical data from the Payroll Department
b.
Actual salaries of the workers, assuming they are known
c.
Average departmental labor rate
d.
Average pay grade labor rate
Question 6
Earned value measurement systems must be capable of:
a.
Measuring resources consumed
b.
Measuring status and accomplishment
c.
Provide a basis for diagnosis and replanning
d.
All of the above
Question 7
The 50-50 rule is a technique used to determine:
a.
CPI
b.
EAC
c.
EV
d.
VAC
Question 8
Work that does not lend itself to subdivision into discrete scheduled increments of work, such as project support, is called:
a.
Work package effort
b.
Measurable effort
c.
Level of effort
d.
Discrete estimates
Question 9
The person or group with greatest ability to influence cost at project initiation is:
a.
The project manager
b.
The project team
c.
The customer/owner
d.
The users