Can you help me understand this Business question?
DELIVERABLE:
Resource Allocation (30 points)
In the Week 4 Lesson Getta Byte Software video, Resource Allocation, you observed how Ima assigned resources to tasks. Imagine that the project sponsors requested that this project be completed by August 1 instead of September 1.
Answer and submit the following questions in a one- to two-page paper.
What would you do?
How would you crash or fast-track the schedule?
Could this project be an Agile project? What would be different about it?
VIDEO TRANSCIPT:
Getta Byte Software
Resource Allocation
Now that we have a schedule, we better decide who does what.
Let's see...
There's me... project manager.
Our developers:
Don Testit
Kurt Anser
Hugh Duitt is our data architect.
Nonia is the data specialist.
We have to buy the software and that's $50,000.
Resources (Image was added.)
Now I need to assign them to the right tasks.
Finalize Requirements
Gather requirements from users.
Gather requirements from customers.
Assigned to: Ima Payne
Purchase software
Select vendor.