Loading...

Messages

Proposals

Stuck in your homework and missing deadline? Get urgent help in $10/Page with 24 hours deadline

Get Urgent Writing Help In Your Essays, Assignments, Homeworks, Dissertation, Thesis Or Coursework & Achieve A+ Grades.

Privacy Guaranteed - 100% Plagiarism Free Writing - Free Turnitin Report - Professional And Experienced Writers - 24/7 Online Support

Ms project 2010 auto adjust row height

27/11/2021 Client: muhammad11 Deadline: 2 Day

MS Project - Lesson #1A - Basics of Project Scheduling - Part 1

Objectives - MS Project 2010
· Understanding Project Scheduling

· Introduction to Microsoft Project

· Working with Project Tasks

· Basic views, time scales and reports

Whether you are a project manager or not, project management techniques are extremely helpful in meeting goals and objects. Project management techniques define a path to a specified goal and then supervise the implementation.

MS Project can help you establish your initial plan as well as monitor progress. MS Project can quickly produce reports and other information that will help keep management, customers, and your project team informed. To get the most from MS Project, not only do you need to understand project management terminology, you also need to be familiar with the software itself. Therefore, do not attempt to quickly finish the lab, but take your time and read all instructions carefully.

Understanding Project Scheduling
A typical project is composed of tasks and resources. After tasks are identified, you organize the tasks in a logical hierarchy, also called a Work Breakdown Structure (WBS). Eventually, this sequence will show the interdependencies of each task. Then each task is given a duration. In MS Project, this can be in weeks, days, hours or minutes. You can also specify a milestone, which will represent an event that marks the completion of a group of related tasks.

To accomplish any task, you need resources. Resources can include people, equipment, material or special facilities necessary to complete a task. Resource availability and scheduling are important constraints to completing a task.

Once you establish a plan, complete with tasks and resources, you will often need to refine the plan before saving it as a baseline. The baseline is your guideline to help manage the project.

MS Project Basics
When you first start MS Project, a blank project file is displayed in Gantt Chart View. (If you need to open an existing MS Project file, the file extension is .mpp.) Let's take a look at the main window:

Select All

Entry Table

Task ID

Gantt Chart

Divider

View Bar

The above image is the default screen for MS Project 2010. The right side of the screen consists of the area for the Gantt Chart. The left side of the screen is the Entry table where tasks, durations, and other task information is entered. The Entry Table and Gantt Chart are separated by a moveable Divider

Pay particular attention to this layout. The Entry table is where we enter our tasks and durations. The Gantt chart will eventually show our tasks and durations in a graphical bar chart. The other part of significance is the divider. This allows you to show more or less of the Entry table/Gantt chart.

In Project 2010 the menu bar is set up into Ribbons. To access the various ribbons, Tabs are selected across the top of the menu bar. Within the ribbon the various sections are divided into groups:

TABS

GROUPS

The above image displays the Microsoft Ribbon in the top of the window. The ribbon is navigated via Tabs. Within each tab are Groups and within each of the Groups are individual commands.

The first step in creating a project is establishing the project information.

1. Select Project Information from the Project tab and the Properties group

The Project Information is used for information that is critical to the scheduling of tasks and resources. It contains the start date and finish date of the overall project, the current date (taken from the computer), and which calendar you will be using. You must always enter this information when creating a new project.

2. Enter the starting date of this project as October 9, 2013. (Note: you can only enter the start date or the finish date, but not both!).

3. Leave the other information as is and Press OK.

4. Next we are going to define other project information. Select File on the Project Tab. Next select, Info. On the right hand side of the screen select Project Information and then Advanced Properties.

5. The Project Properties screen appears and the Summary tab should be selected.

6. In the Title box, type Maynard Furniture Company Project.

7. In the Subject box, type New System.

8. In the Author's and the Manager's box, type in your name. This information will be displayed on reports. In the Company box, enter MGMT404 followed by your professor’s name. Click OK.

9. Save the project as MyLab1a_XXX.mpp (where XXX are your initials).

Basic Setup
1. Before we start entering data there are a few setup tasks we need to do.

2. The first is to change how MS Project calculates the schedule. (We will explain this in week 5)

3. Go File, then Options. The Project Options window opens.

4. Select Schedule. The Project Options window now should be visible.

5. Under Scheduling options for this project check the box labeled "New tasks are effort driven"

6. Click OK to close the window.

7. Next, select the Gantt Chart Tools Format tab from the ribbon. Click the check box to show the tasks that will be on the Critical Path.

8. Select the Task tab. With these settings we are ready to start entering data

Entering tasks
1. Click in the first field in the Task Name column. Type Inventory current equipment.

2. Press the tab key. The information is entered and the selection moves to the Duration column for task 1. (You may need to slide the divider to the right to see the column). Also notice the task is represented on the Gantt chart.

3. Change the duration to 3 days by typing 3 and press enter. Notice the duration "days" or the letter "d" is automatically assumed. If different, you would enter m for minutes, h for hours, d for days or w for weeks after the number, such as 3w would be three weeks).

4. By default, MS Project 2010 enters tasks as Manually Scheduled. This allows the user to schedule individual dates for the tasks. We however, want MS Project to schedule the tasks for us.

5. For task 1, In the Task Mode column, select Auto Schedule. This will enable MS Project to automatically assign the start and end dates for each task.

6. To change this as the default mode, at the bottom left of the screen there is a button where you can change this default setting. Click on this and change the setting so all new tasks are set to be Auto Scheduled. You can also do this from the Task tab, Tasks group and selecting the Mode button, or from the Options screen we looked at earlier.

7. Enter the following tasks and durations for this project:

Assess current department needs 2 days

Design and diagram new system 5 days

Proposal to accounting 3 days

Research products and services 7 days

Issue RFPs 7 days

Evaluate bids 5 days

Award contract 1 day

Meet with vendor 1 day

Purchase equipment 4 days

Install wiring 3 days

Install hardware 2 days

Install software 2 days

(Note: it is very important that you make any changes to these durations prior to assigning resources. If you need to change duration after assigning resources, you should unassign all resources, change the duration and then re-assign the resources!)

8. When you enter tasks, note that “1 Day?” is the automatic default for duration. (You may need to slide the divider to the right to see the column). Also notice the task is represented on the Gantt chart. For durations that are only 1 day, make sure to manually type 1 and then the key to remove the “?”.

9. Next make sure each task is "Auto Scheduled" when you are finished.

10. Notice as you enter each task and the duration, how the tasks are presented on the Gantt chart.

(Tip: By default MS Project 2010 automatically wraps the text on the task names. Some readers may find this not very clear. To see the entire task name on one line, position your cursor on the vertical line between the Task Name column header and the Duration column header. When the cursor turns to a double arrow, either drag the line to the right to increase the column width or double-click. Another method is to double click on the Task Name column header and select Best Fit. To see the Duration column, move the divider between the tasks and the Gantt chart. When you are done, then also adjust row height).

11. The text wrap can be toggled on and off from the Gantt Chart Tools Format tab, in the Columns group and the Wrap Text icon. Please turn this off now.

12. Change the duration of the task Award contract to 0 days. Notice the symbol on the Gantt chart. This is a milestone task, which has no duration but is used to mark progress in a project.

13. What if you need to insert a task later? Easy. For example, select task #13 Install software and Right click and select click Insert Task. A new task row will now be inserted above the current task.

14. Type Test system as your new task and duration of 1 day. (Remember next to select "Auto Scheduled".

15. Since “Test system” actually should be our last task, we need to move it. Therefore click (but do not hold down the mouse button) the task ID for task #13 - Test system. The entire row should be selected.

Task ID
16. With the pointer still positioned on the task ID, drag down until a horizontal gray bar is displayed after task #14. Then release. Test system should now be your last task.

17. What if you want to delete a task? Click anywhere in the row for the task Meet with vendor. Right click and select click Delete Task.

Another type of task you may want to enter is a recurring task, such as a team meeting, etc. Generally recurring tasks are not included on a project, but it helps in resource scheduling.

18. Below the last task (task #13: Test System), click in the Task Name Column, but do not type anything.

19. From the Task tab in the Insert group, click Select the arrow under Task and choose Recurring Task.

20. The Recurring Task Information Box appears.

21. In the Name box, type Project Meeting.

22. Press the tab key and enter 2h for duration of 2 hours. Select Weekly for "Recurrence pattern" and check the box for Friday. Leave "Recur every" as is. We have scheduled a weekly 2-hour meeting every Friday for the duration of the project. Click OK. (Notice the circular arrows in the indicator column next to the task name).

19. Save the project before continuing.

Displaying Project Information in Views
Before closing out this project, we need to spend a little time with views. A view is a format in which you can enter and/or display information in MS Project. Your default view is known as the Gantt view: it is made up of the Entry table on the left, used to enter task information, and the Gantt chart on the right, which graphically represents the task information on a timescale.

Task and resource views in MS Project fall into three categories: sheet views, chart and graph views, and form views. Each view displays combinations of project information in different ways. Understanding what is your current view and changing views is critical in mastering MS Project.

Sheet views display task or resource information in a row and column format (similar to MS Excel). Chart and graph views provide a graphical representation of task or resource information. Form views display task or resource information in a format that displays a single task or single resource at a time. You use a form view when you want to focus on detailed information about a specific task or resource.

MS Project comes with 27 (MS Project 2010) predefined views.

1. From the Task tab and the View group, click Calendar. What do you see?

2. Now click on Task Usage. How is this different?

3. Finally, click on Network Diagram. Graphical view of tasks…

4. Return to the Gantt Chart view.

5. Another item to explore is the timescale for the Gantt chart.

On longer projects, you may not be able to see all the tasks on the Gantt chart. You can use the scroll bars to the right and on the bottom of the Gantt chart or you can adjust the timescale of the chart (shown above). The top line of the timescale is referred to as the Major timescale (Oct 6, ‘13, etc.) and the bottom line as the Minor timescale (SMTWTFS). To adjust the timescale, you can use the Zoom In and Zoom Out buttons on the View toolbar under Zoom:

6. Click the Zoom In button (the one with the + sign). Notice the Major timescale changes to a day and the Minor timescale changes to 6-hour increments.

7. Now click on the Zoom Out button (the one with the - sign). The Major timescale returns to a week and the Minor timescale changes to day increments.

8. Click on the Zoom Out button again. Notice the Major timescale changes to a month and the Minor timescale changes to 3-day increments.

9. Click the Zoom In button again to return to the default of a week and one-day increments.

You can also specify your own timescale by selecting the Timescale dialog box on the View tab, Zoom group and the down arrow under "Timescale:" or by right clicking on the time scale on the Gantt chart.

Printing Project Schedules and Reports
To manage a project effectively, you will need to communicate project information to a variety of people, therefore it is important the reports printed are understandable by the readers.

You can print views and reports that meet the needs of a specific person or group. MS Project comes with 27 predefined views and 22 Visual reports and 29 standard reports. Before you print a view or report, it should be previewed to determine the number of pages that will be printed and if any additional information needs to be added.

Using the Page Setup dialog box, you can select page orientation, adjust scaling, change margins, and add or change the headers and footers. You can also add page breaks to control the flow of information. You can also create a legend at the bottom of the Gantt chart to explain the symbols used in the chart. (With the exception of the Project Summary report, you must do this for each report/printout; it is NOT a universal page setup!)

1. On the File tab, Print, then Page Setup.

The Page Setup dialog box appears:

2. Click the Header tag. The top box is the Preview box and the bottom box is the Text box.

3. Select the Left tab next to Alignment. In the Text box, type Lesson #1A on the first line. (The left corner will always be the lab number, so make sure you change it in future labs!)

4. Select the Center tab. Next to the General box displaying the text, "Page Number", click the down arrow and select Project Title. Click Add.

Note: the project title is displayed in the Preview box (based upon the information you entered in the Project Information earlier). The text box shows the “&” sign or the "place marker" for this information. The nice thing here is that if you ever change the Project Information, the changes will automatically appear on any reports that contain this information in the header.

5. Press Enter. (The cursor should now be on the second line for your center header information). From the same drop-down tab, add Manager Name. Press Enter and add File name as your third line and add Report Name as your fourth and final line.

6. Select the Right tab. Notice the seven icons below the text box. Select the middle (or fourth icon) to insert the current date in this section of your header.

7. On your own, make sure Page Number is in your footer and it is center aligned and then press OK. Review the Print Preview to view the changes. What is missing? Notice that there is nothing displayed in the fourth line of the header for report name? Why??? This is a view and not a defined report so there is nothing to display in this field. In order to see the view name, the parameter in the fourth line of the header would have to be changed to View Name – we will NOT do this at this time. The fourth line will display as a blank line when we are in a view format and not a report format.

8. Click the File tab to return to the Gantt chart view.

Previewing and Printing Views and Reports

When submitting required printouts, if you are not bringing them to class, from the Print Preview Page, take a screen shot (in Windows ) of the report and paste the screen shot to a MS Word Document. Make sure to crop the screen to show only the report. After cropping, resize the image appropriately. If the printout is on more than 1 page, paste each page individually.

Save the Word document containing printouts as Week_1_Printouts_XXX.docx. Remember to replace "XXX" in the file names with your initials and ensure that all of your files are all clearly labeled and include your initials in the file name. In the second part of this lesson, there will be more printouts to add to the Week_1_Printout_XXX.docx file.

9. On the File tab, click the Print button. Place the mouse pointer over the preview page. The pointer changes to a magnifying glass.

10. Click the lower-left corner of the preview page. The view is zoomed in so you can see the legend to the Gantt chart. If you ever want to change the contents of this legend, you can go to the same Page Setup in our previous steps and select Legend.

11. Click on the magnifying glass again to return to normal view. Make sure the task names column and the duration column can be seen in their entirety and the Gantt chart also appears in your window.

12. Click Print and print this view. We have just printed the Gantt chart view.

13. To view and print reports: From the Project tab, click Reports in the Reports group.

14. The Reports box opens. Each icon represents a category of reports. The first five (Overview, Current Activities, Costs, Assignments and Workload) represent 22 predefined reports. The last category, Custom, allows you to create your own report.

15. Select Overview and then select Project Summary. The Project Summary report now opens in Print Preview.

16. Select Page Setup for this report. Notice something interesting? The header and footer (and legend and view) tabs are grayed out. For some reason, only known to Microsoft, this is the only report that you cannot change the header and footer. To that end, it is imperative that you enter all appropriate project information and project properties as discussed in the lab!

17. Print the Project Summary. This is a very important report. It lists all relevant summary information as to project progress and achievement of your project objective.

18. On your own, find the report, Unstarted Tasks. Before you print this report, make sure your header and footer contain the appropriate information! Print the report when all is well.

19. Save your file and exit MS Project.

When submitting required printouts, if you are not bringing them to class, from the Print Preview Page, take a screen shot (in Windows ) of the report and paste the screen shot to a MS Word Document. Make sure to crop the screen to show only the report. After cropping, resize the image appropriately. If the printout is on more than 1 page, paste each page individually.

Save the Word document containing printouts as Week_1_Printouts_XXX.docx and submit this file to the Week 1 iLab Dropbox, along with the MyLab1B_XXX.mpp file and the completed Review Questions at the end of Lesson 1B. Remember to replace "XXX" in the file names with your initials and ensure that all of your files are all clearly labeled and include your initials in the file name.

In part 2 of this lesson we will continue working with task information by outline and linking these tasks and discussing interdependencies and constraints.

1. On the Project tab, click Project Information. In the Project Information dialog box, click Statistics. The following screen should appear. Use this to check your progress…

Homework is Completed By:

Writer Writer Name Amount Client Comments & Rating
Instant Homework Helper

ONLINE

Instant Homework Helper

$36

She helped me in last minute in a very reasonable price. She is a lifesaver, I got A+ grade in my homework, I will surely hire her again for my next assignments, Thumbs Up!

Order & Get This Solution Within 3 Hours in $25/Page

Custom Original Solution And Get A+ Grades

  • 100% Plagiarism Free
  • Proper APA/MLA/Harvard Referencing
  • Delivery in 3 Hours After Placing Order
  • Free Turnitin Report
  • Unlimited Revisions
  • Privacy Guaranteed

Order & Get This Solution Within 6 Hours in $20/Page

Custom Original Solution And Get A+ Grades

  • 100% Plagiarism Free
  • Proper APA/MLA/Harvard Referencing
  • Delivery in 6 Hours After Placing Order
  • Free Turnitin Report
  • Unlimited Revisions
  • Privacy Guaranteed

Order & Get This Solution Within 12 Hours in $15/Page

Custom Original Solution And Get A+ Grades

  • 100% Plagiarism Free
  • Proper APA/MLA/Harvard Referencing
  • Delivery in 12 Hours After Placing Order
  • Free Turnitin Report
  • Unlimited Revisions
  • Privacy Guaranteed

6 writers have sent their proposals to do this homework:

Solution Provider
Engineering Exam Guru
Accounting & Finance Specialist
Coursework Assignment Help
Phd Writer
Instant Homework Helper
Writer Writer Name Offer Chat
Solution Provider

ONLINE

Solution Provider

I have worked on wide variety of research papers including; Analytical research paper, Argumentative research paper, Interpretative research, experimental research etc.

$34 Chat With Writer
Engineering Exam Guru

ONLINE

Engineering Exam Guru

I have written research reports, assignments, thesis, research proposals, and dissertations for different level students and on different subjects.

$39 Chat With Writer
Accounting & Finance Specialist

ONLINE

Accounting & Finance Specialist

I have worked on wide variety of research papers including; Analytical research paper, Argumentative research paper, Interpretative research, experimental research etc.

$27 Chat With Writer
Coursework Assignment Help

ONLINE

Coursework Assignment Help

I have assisted scholars, business persons, startups, entrepreneurs, marketers, managers etc in their, pitches, presentations, market research, business plans etc.

$22 Chat With Writer
Phd Writer

ONLINE

Phd Writer

As an experienced writer, I have extensive experience in business writing, report writing, business profile writing, writing business reports and business plans for my clients.

$22 Chat With Writer
Instant Homework Helper

ONLINE

Instant Homework Helper

I can assist you in plagiarism free writing as I have already done several related projects of writing. I have a master qualification with 5 years’ experience in; Essay Writing, Case Study Writing, Report Writing.

$36 Chat With Writer

Let our expert academic writers to help you in achieving a+ grades in your homework, assignment, quiz or exam.

Similar Homework Questions

Management decision problem and marketing research problem - Forum: Week 2 Discussion - Calculate volume of water - Evo boiler fault codes - Glue boiler animal farm - H101 - V2 u2 2as proof - Decimal fraction to octal conversion - Ode on a distant prospect of eton college paraphrase - Jesus as a role model - Viscose definition brave new world - Statistical significance vs meaningfulness - Dc62 research server room - Hw - Discussion 2 - Ford supply chain strategy - Freedonia has a comparative advantage in the production of tea - I'll worship you my god - Trading account format pdf - Acc 250 week 1 assignment - Bald eagle excretory system - Week 5 assignment essay ideal citizen in a totalitarian government - Word list for persuasive writing - Two shuffleboard disks of equal mass - Software engineering sheffield hallam - Theorem 10.10 class 9 - 22 c to kelvin - Which situation indicates a weak internal control structure? - HRM530 Week6 Assignment 3 Dismissal Meeting - It system audit checklist - Co injection sandwich molding - Factoring quadratics sign rules - Severe burn injury case study answers - Nursing care plan for motor vehicle accident - Summary Unequal Democracy Chapter 4-6 - Lizard evolution virtual lab worksheet answers - Adam and eve albrecht durer function - Family reunion committee responsibilities - At&t strengths and weaknesses 2017 - Balloon circumference vs temperature experiment - Good sentence starters for essays - Honeywell mifare card reader - Helium safety data sheet - Mixer tap hose connector toolstation - A tensile test is performed on a metal specimen - Cfc yfl youth camp manual - What is p hat - What are the characteristics of hazardous manual tasks - John deere industrial revolution - Joint form of general conditions - Kipling and i by jesus colon summary - How to recognize plagiarism tutorials and tests answers 2019 - Writing a feature article - The happiness project journal - Biometrics ppt files - 46 danbury crescent girrawheen - Charge and discharge of a capacitor lab report - How many squares in the figure - Analysis and visual data_8/29 - You hear: alejandro llevó un suéter marrón. you choose: preterite - Kimberly clark annual report 2016 - Zoo swot analysis - Sorting task jovian planet properties - Kohler kdw1404 parts manual - What is an epic hero - LD5 - Lance h and wanda b dean - Deliverable 2 - Tutoring on the Normal Distribution - 26 l of the a - John fairfax publications v rivkin - Pick one of the following terms for your research: authority, competition, confrontation, dependency, empowerment, intergroup conflict, negotiation, organizational politics, power, or rational model. - Transformational leadership and knowledge and knowledge sharing within an organization. - Today by billy collins - Psychology & Law 2000words essay - Ensign amendment - Lexical categories in english - Occupational therapy evaluation form - Trinity guildhall speech and drama - CASES CASE 35 CIRQUE DU SOLEIL* The founder of Cirque du Soleil, Guy Laliberté, after see- ing the firm’s growth prospects wane in recent years, was thinking about expanding his firm in new directions. For three decades, the firm had reinvented and revolutionized the circus. From its beginning in 1984, Cirque de Soleil had thrilled over 150 million spectators with a novel show concept that was as original as it was nontraditional: an astonishing theatrical blend of circus acts and street enter- tainment, wrapped up in spectacular costumes and fairy- land sets and staged to spellbinding music and magical lighting. Cirque du Soleil’s business triumphs mirrored its high- flying aerial stunts, and it became a case study for business school journal articles on carving out unique markets. But following a recent bleak outlook report from a consultant, a spate of poorly received shows over the last few years, and a decline in profits, executives at Cirque said they were now restructuring a - The obligation to endure ethos pathos logos - Econ - Freezing point depression lab report - Brisbane city council mulch - Sylvia the truman show - Specific gas constant steam - 55 barrow road humpty doo - Deconstruct reconstruct 8 ways - Kohlberg moral dilemma examples - Idealist decision making style - Safer driver course act - Community teaching plan teaching experience paper gcu - Bus 475 week 5 final exam - The global security policy cmgt 400 - Scion hero character sheet - Uranus average distance from sun - Class One: Part One - Vocabulario mas usado en ingles - Buck-boost converter calculator excel - Questions about food webs - Assignment 2