Your team has been asked to test and document enhancements to a web application that allows buyers to purchase custom-printed canvas shoes. The tasks and dependencies are as follows:
Once the testing plan is ready, your team can:
- Test the user interfaces
 
- Test the database
 
- Test the network
 
- Write the documentation first draft
 
When the user interface tests are complete, you can:
- Perform user testing—enlist some users to test the user interface
 
When the database and network testing are complete, you can:
- Perform integration testing—network with the database
 
When the user testing of the user interface and the database testing are complete, you can:
- Perform integration testing—database, network, and user interface
 
When all integration testing and user testing are complete, you can:
Then you can:
- Review and revise documentation
 
After all other tasks are complete, you can:
- Obtain management approval
 
Duration estimates for the tasks:
 a.
 3 days
 b.
 10 days
 c.
 6 days
 d.
 7 days
 e.
 20 days
 f.
 5 days
 g.
 3 days
 h.
 2 days
 i.
 8 days
 j.
 4 days
k.
 5 days
- Create a network diagram and a Gantt chart for the project tasks. Ask your instructor if you are permitted to use software such as Microsoft Project to help you prepare your diagrams.
    
- What is the planned duration for the testing project?
 
- What is the critical path for the testing project?
 
- For each task NOT on the critical path, calculate the amount of slack available.
 
- If the user testing of the user interface takes 15 days, what will the impact be on the project duration?
 
 
Question 2
Wedding cost estimation: Given the following information, calculate the estimated costs for a wedding with 250 guests and a bridal party of six, using the methods indicated. Show your work.
Note that members of the bridal party are already counted as guests, you don’t need to add them twice.
- Parametric estimate
 
- Bottom-up estimate
 
- Analogous cost estimate
 
- You will probably notice some differences in the estimated values. Are these differences significant? What might cause the differences? If you were estimating a significant project in the future, which method(s) would you use and why?
 
Wedding Cost Estimates
Item
Dollars
Groom’s brother’s wedding, last year, 175 guests, similar venue and style
$20,300
Catering
$65 per person
Photographer
$1,500
Rental of hall
$500
Clothing, bride
$2,000
Clothing, groom
$750
Flowers
$800
Other décor items
$500
Cake
$500
Gifts for bridal party
$80 each
Wedding planner
$2,000
Wedding planner’s estimate of typical cost for this kind of wedding
$10,000 plus $75 per guest
Question 3
Cost reimbursable contract calculation.
- A contract calls for a total payment of $800,000 with a guarantee. Essentially the contractor is guaranteed to make at least $200,000 above his costs. If the contractor can demonstrate his costs exceed $600,000, the project will pay the difference, with a $50,000 ceiling on the overage. The contractor demonstrates he spent $623,000. How much (gross) must the project remit to the contractor?
 
- Another option for the same contract has the contractor guaranteed to be paid his costs plus 20%, for costs that exceed $600,000. With the same initial assumption—guarantee of $800,000 gross payment (no requirement to itemize costs), but if the contractor can show that costs exceed $600,000, the project will pay $800,000 plus the costs that exceed $600,000, plus 20% of those excess costs, with a ceiling of $900,000 gross. The contractor demonstrates he spent $623,000. How much (gross) must the project remit to the contractor?
 
- Under option 3.2, at what dollar amount of total costs would the contractor be assuming all of the excess costs beyond that point?
 
- In which option did the project assume more of the risk of a cost overrun? Explain.