Loading...

Messages

Proposals

Stuck in your homework and missing deadline? Get urgent help in $10/Page with 24 hours deadline

Get Urgent Writing Help In Your Essays, Assignments, Homeworks, Dissertation, Thesis Or Coursework & Achieve A+ Grades.

Privacy Guaranteed - 100% Plagiarism Free Writing - Free Turnitin Report - Professional And Experienced Writers - 24/7 Online Support

Post graduation adventure

29/12/2020 Client: saad24vbs Deadline: 7 Days

7/22/2017 University of Phoenix: Project Management: The Managerial Process


https://phoenix.vitalsource.com/#/books/1259822338/cfi/6/32!/4/354/4/2@0:50.9 1/44


Page 128


PRINTED BY: lttlemntate@email.phoenix.edu. Printing is for personal, private use only. No part of this book may be reproduced or transmitted without publisher's prior permission. Violators will be prosecuted.


CHAPTER FIVE


Estimating Project Times and Costs


Estimating Project Times and Costs Factors Influencing the Quality of Estimates Estimating Guidelines for Times, Costs, and Resources Top-Down versus Bottom-Up Estimating Methods for Estimating Project Times and Costs Level of Detail Types of Costs Refining Estimates Creating a Database for Estimating Summary Appendix 5.1: Learning Curves for Estimating


7/22/2017 University of Phoenix: Project Management: The Managerial Process


https://phoenix.vitalsource.com/#/books/1259822338/cfi/6/32!/4/354/4/2@0:50.9 2/44


Page 129


PRINTED BY: lttlemntate@email.phoenix.edu. Printing is for personal, private use only. No part of this book may be reproduced or transmitted without publisher's prior permission. Violators will be prosecuted.


Project estimation is indeed a yardstick for project cost control. And if the yardstick is faulty, you start on the “wrong foot.” … we exhort you not to underestimate the estimate.*


Given the urgency to start work on the project, managers sometimes minimize or avoid the effort to follow through on estimating project time and cost. This attitude is a huge mistake and costly. There are important reasons to make the effort and incur the cost of estimating for your project. Exhibit 5.1 summarizes some key reasons.


Estimating is the process of forecasting or approximating the time and cost of completing project deliverables. Estimating processes are frequently classified as top-down and bottom-up. Top-down estimates are usually done by senior management. Management will often derive estimates from analogy, group consensus, or mathematical relationships. Bottom-up estimates are typically performed by the people who are doing the work. Their estimates are based on estimates of elements found in the work breakdown structure.


All project stakeholders prefer accurate cost and time estimates, but they also understand the inherent uncertainty in all projects. Inaccurate estimates lead to false expectations and consumer dissatisfaction. Accuracy is improved with greater effort, but is it worth the time and cost—estimating costs money! Project estimating becomes a trade-off, balancing the benefits of better accuracy against the costs for securing increased accuracy.


Cost, time, and budget estimates are the lifeline for control; they serve as the standard for comparison of actual and plan throughout the life of the project. Project status reports depend on reliable estimates as the major input for measuring variances and taking corrective action. Ideally, the project manager, and in most cases the customer, would prefer to have a database of detailed schedule and cost estimates for every work package in the project. Regrettably, such detailed data gathering is not always possible or practical and other methods are used to develop project estimates.


EXHIBIT 5.1 Why Estimating Time and Cost Are Important


Estimates are needed to support good decisions. Estimates are needed to schedule work. Estimates are needed to determine how long the project should take and its cost. Estimates are needed to determine whether the project is worth doing. Estimates are needed to develop cash flow needs. Estimates are needed to determine how well the project is progressing. Estimates are needed to develop time-phased budgets and establish the project baseline.


7/22/2017 University of Phoenix: Project Management: The Managerial Process


https://phoenix.vitalsource.com/#/books/1259822338/cfi/6/32!/4/354/4/2@0:50.9 3/44


Page 130


PRINTED BY: lttlemntate@email.phoenix.edu. Printing is for personal, private use only. No part of this book may be reproduced or transmitted without publisher's prior permission. Violators will be prosecuted.


Factors Influencing the Quality of Estimates A typical statement in the field is the desire to “have a 95 percent probability of meeting time and cost estimates.” Past experience is a good starting point for developing time and cost estimates. But past experience estimates must almost always be refined by other considerations to reach the 95 percent probability level. Factors related to the uniqueness of the project will have a strong influence on the accuracy of estimates. Project, people, and external factors all need to be considered to improve quality of estimates for project times and costs.


Planning Horizon The quality of the estimate depends on the planning horizon; estimates of current events are close to 100 percent accurate but are reduced for more distant events. For example, cost estimates for a party you are organizing this weekend should be much more accurate than the estimates for a wedding that will take place in three months. The accuracy of time and cost estimates should improve as you move from the conceptual phase to the point where individual work packages are defined. Long-duration projects increase the uncertainty in estimates.


Project Duration Time to implement new technology has a habit of expanding in an increasing, nonlinear fashion. Sometimes poorly written scope specifications for new technology result in errors in estimating times and costs.


People The people factor can influence the quality of time and cost estimates. For example, accuracy of estimates depends on the skills of the people making the estimates. How familiar are they with the task they are estimating?


Project Structure and Organization Which project structure is chosen to manage the project will influence time and cost estimates. One of the major advantages of a dedicated project team discussed earlier is the speed gained from concentrated focus and localized project decisions. This speed comes at an additional cost of tying up personnel full time. Conversely, projects operating in a matrix environment may reduce costs by more efficiently sharing personnel across projects but may take longer to complete since attention is divided and coordination demands are higher.


Padding Estimates In some cases people are inclined to pad estimates. For example, if you are asked how long it takes you to drive to the airport, you might give an average time of 30 minutes, assuming a 50/50 chance of getting there in 30 minutes. If you are asked the fastest you could possibly get there, you might reduce the driving time to 20 minutes. Finally, if you are asked how long the drive would take if you absolutely had to be there to meet with the president, it is likely you would increase the estimate to say 50 minutes to ensure not being late. In work situations where you are asked for time and cost estimates, most of us are inclined to add a little padding to increase the probability and reduce the risk of being late. If everyone at all levels of the project adds a little padding to reduce risk, the project duration and cost


7/22/2017 University of Phoenix: Project Management: The Managerial Process


https://phoenix.vitalsource.com/#/books/1259822338/cfi/6/32!/4/354/4/2@0:50.9 4/44


Page 131


PRINTED BY: lttlemntate@email.phoenix.edu. Printing is for personal, private use only. No part of this book may be reproduced or transmitted without publisher's prior permission. Violators will be prosecuted.


are seriously overstated. This phenomenon causes some managers or owners to call for a 10–15 percent cut in time and/or cost for the project. Of course the next time the game is played, the person estimating cost and/or time will pad the estimate to 20 percent or more. Clearly such games defeat chances for realistic estimates, which is what is needed to be competitive.


Organization Culture Organization culture can significantly influence project estimates. In some organizations padding estimates is tolerated and even privately encouraged. Other organizations place a premium on accuracy and strongly discourage estimating gamesmanship. Organizations vary in the importance they attach to estimates. The prevailing belief in some organizations is that detailed estimating takes too much time and is not worth the effort or that it's impossible to predict the future. Other organizations subscribe to the belief that accurate estimates are the bedrock of effective project management. Organization culture shapes every dimension of project management; estimating is not immune to this influence.


Other Factors Finally, nonproject factors can impact time and cost estimates. For example, equipment down-time can alter time estimates. National holidays, vacations, and legal limits can influence project estimates. Project priority can influence resource assignment and impact time and cost.


Project estimating is a complex process. The quality of time and cost estimates can be improved when these variables are considered in making the estimates. Estimates of time and cost together allow the manager to develop a time-phased budget, which is imperative for project control. Before discussing macro and micro estimating methods for times and costs, a review of estimating guidelines will remind us of some of the important “rules of the game” that can improve estimating.


Estimating Guidelines for Times, Costs, and Resources Managers recognize time, cost, and resource estimates must be accurate if project planning, scheduling, and controlling are to be effective. However, there is substantial evidence suggesting poor estimates are a major contributor to projects that have failed. Therefore, every effort should be made to see that initial estimates are as accurate as possible since the choice of no estimates leaves a great deal to luck and is not palatable to serious project managers. Even though a project has never been done before, a manager can follow seven guidelines to develop useful work package estimates.


1. Responsibility. At the work package level, estimates should be made by the person(s) most familiar with the task. Draw on their expertise! Except for supertechnical tasks, those responsible for getting the job done on schedule and within budget are usually first-line supervisors or technicians who are experienced and familiar with the type of work involved. These people will not have some preconceived, imposed duration for a deliverable in mind. They will give an estimate based on experience and best judgment. A secondary benefit of using those responsible is the hope they will “buy in” to seeing that the estimate materializes when they implement the work package. If those involved are not consulted, it will be difficult to hold them responsible for failure to achieve the estimated time.


7/22/2017 University of Phoenix: Project Management: The Managerial Process


https://phoenix.vitalsource.com/#/books/1259822338/cfi/6/32!/4/354/4/2@0:50.9 5/44


Page 132


PRINTED BY: lttlemntate@email.phoenix.edu. Printing is for personal, private use only. No part of this book may be reproduced or transmitted without publisher's prior permission. Violators will be prosecuted.


Finally, drawing on the expertise of team members who will be responsible helps to build communication channels early.


2. Use several people to estimate. It is well known that a cost or time estimate usually has a better chance of being reasonable and realistic when several people with relevant experience and/or knowledge of the task are used (sometimes called “crowdsourcing”). True, people bring different biases based on their experience. But discussion of the individual differences in their estimate leads to consensus and tends to eliminate extreme estimate errors.


3. Normal conditions. When task time, cost, and resource estimates are determined, they are based on certain assumptions. Estimates should be based on normal conditions, efficient methods, and a normal level of resources. Normal conditions are sometimes difficult to discern, but it is necessary to have a consensus in the organization as to what normal conditions mean in this project. If the normal workday is eight hours, the time estimate should be based on an eight-hour day. Similarly, if the normal workday is two shifts, the time estimate should be based on a two-shift workday. Any time estimate should reflect efficient methods for the resources normally available. The time estimate should represent the normal level of resources—people or equipment. For example, if three programmers are available for coding or two road graders are available for road construction, time and cost estimates should be based on these normal levels of resources unless it is anticipated the project will change what is currently viewed as “normal.” In addition, possible conflicts in demand for resources on parallel or concurrent activities should not be considered at this stage. The need for adding resources will be examined when resource scheduling is discussed in a later chapter.


4. Time units. Specific time units to use should be selected early in the development phase of the project network. All task time estimates need consistent time units. Estimates of time must consider whether normal time is represented by calendar days, workdays, workweeks, person days, single shift, hours, minutes, etc. In practice the use of workdays is the dominant choice for expressing task duration. However, in projects such as a heart transplant operation, minutes probably would be more appropriate as a time unit. One such project that used minutes as the time unit was the movement of patients from an old hospital to an elegant new one across town. Since there were several life-endangering moves, minutes were used to ensure patient safety so proper emergency life-support systems would be available if needed. The point is, network analysis requires a standard unit of time. When computer programs allow more than one option, some notation should be made of any variance from the standard unit of time. If the standard unit of time is a five-day workweek and the estimated activity duration is in calendar days, it must be converted to the normal workweek.


5. Independence. Estimators should treat each task as independent of other tasks that might be integrated by the WBS. Use of first-line managers usually results in considering tasks independently; this is good. Top managers are prone to aggregate many tasks into one time estimate and then deductively make the individual task time estimates add to the total. If tasks are in a chain and performed by the same group or department, it is best not to ask for all the time estimates in the sequence at once to avoid the tendency for a planner or a supervisor to look at the whole path and try to adjust individual task times in the sequence to meet an arbitrary imposed schedule or some rough “guesstimate” of the total time for the whole path or segment of the project. This tendency does not reflect the uncertainties of individual activities and generally results in optimistic task time estimates. In summary, each task time estimate should be considered independently of other activities.


7/22/2017 University of Phoenix: Project Management: The Managerial Process


https://phoenix.vitalsource.com/#/books/1259822338/cfi/6/32!/4/354/4/2@0:50.9 6/44


Page 133


PRINTED BY: lttlemntate@email.phoenix.edu. Printing is for personal, private use only. No part of this book may be reproduced or transmitted without publisher's prior permission. Violators will be prosecuted.


SNAPSHOT FROM PRACTICE Reducing Estimating Errors*


Complexity is the major source of estimating error, says Kerry Wills, Project Management Sr. Director at the healthcare services organization Cigna, in Hartford, Connecticut. “Project managers cannot possibly be experts in all areas and therefore need to rely on the stakeholders for their expertise when estimating,” Willis notes. To minimize errors he recommends treating estimating as a living process and not a one-time event.


He follows the same approach on all of his projects:


1. Identify all of the stakeholders based on the scope of the project and organizational history. 2. Involve the stakeholders when creating the estimates. “You can't hold people accountable for estimates they


didn't help create,” Willis says. 3. Aggregate the estimates by comparing several models (resource based, parametric, etc.). 4. Manage the project against the estimates. This includes making adjustments based on changes in project


scope. 5. Track projects closely using tools such as earned value to gauge progress toward estimates. 6. Track actual costs and time at a granular level to recalibrate the model for future projects.


“The initial estimate could be perfect, but if it is not managed, then the end result will be bad and people will point to the estimating process,” Wills argues.


* S. Swanson, “Estimating Errors,” PMNetwork, October 2011, pp. 62–66.


6. Contingencies. Work package estimates should not include allowances for contingencies. The estimate should assume normal or average conditions even though every work package will not materialize as planned. For this reason top management needs to create an extra fund for contingencies that can be used to cover unforeseen events.


7. Adding risk assessment to the estimate helps to avoid surprises to stakeholders. It is obvious some tasks carry more time and cost risks than others. For example, a new technology usually carries more time and cost risks than a proven process. Simply identifying the degree of risk lets stakeholders consider alternative methods and alter process decisions. A simple breakdown by optimistic, most likely, and pessimistic for task time could provide valuable information regarding time and cost. See Chapter 7 for further discussion of project risk.


Where applicable, these guidelines will greatly help to avoid many of the pitfalls found so often in practice. See Snapshot from Practice: Reducing Estimating Errors for a similar set of guidelines.


Top-Down versus Bottom-Up Estimating Since estimating efforts cost money, the time and detail devoted to estimating is an important decision. Yet, when estimating is considered, you as a project manager may hear statements such as these:


https://jigsaw.vitalsource.com/books/1259822338/epub/OEBPS/17_chapter07.xhtml#chap7

7/22/2017 University of Phoenix: Project Management: The Managerial Process


https://phoenix.vitalsource.com/#/books/1259822338/cfi/6/32!/4/354/4/2@0:50.9 7/44


Rough order of magnitude is good enough. Spending time on detailed estimating wastes money. Time is everything; our survival depends on getting there first! Time and cost accuracy is not an issue. The project is internal. We don't need to worry about cost. The project is so small, we don't need to bother with estimates. Just do it.


7/22/2017 University of Phoenix: Project Management: The Managerial Process


https://phoenix.vitalsource.com/#/books/1259822338/cfi/6/32!/4/354/4/2@0:50.9 8/44


Page 134


PRINTED BY: lttlemntate@email.phoenix.edu. Printing is for personal, private use only. No part of this book may be reproduced or transmitted without publisher's prior permission. Violators will be prosecuted.


TABLE 5.1 Conditions for Preferring Top-Down or Bottom-Up Time and Cost Estimates


However, there are sound reasons for using top-down or bottom-up estimates. Table 5.1 depicts conditions that suggest when one approach is preferred over another.


Top-down estimates usually are derived from someone who uses experience and/or information to determine the project duration and total cost. However, these estimates are sometimes made by top managers who have very little knowledge of the component activities used to complete the project. For example, a mayor of a major city making a speech noted that a new law building would be constructed at a cost of $23 million and would be ready for occupancy in two and one-half years. Although the mayor probably asked for an estimate from someone, the estimate could have come from a luncheon meeting with a local contractor who wrote an estimate (guesstimate) on a napkin. This is an extreme example, but in a relative sense this scenario is frequently played out in practice. See Snapshot from Practice: Council Fumes, for another example of this. The question actually is, do these estimates represent low-cost, efficient methods? Seldom. The fact that the estimate came from the top can influence people responsible to “do what it takes to make the estimate.”


If possible and practical, you want to push the estimating process down to the work package level for bottom- up estimates that establish low-cost, efficient methods. This process can take place after the project has been defined in detail. Good sense suggests project estimates should come from the people most knowledgeable about the estimate needed. The use of several people with relevant experience with the task can improve the time and cost estimate. The bottom-up approach at the work package level can serve as a check on cost elements in the WBS by rolling up the work packages and associated cost accounts to major deliverables. Similarly, resource requirements can be checked. Later, the time, resource, and cost estimates from the work packages can be consolidated into time-phased networks, resource schedules, and budgets that are used for control.


The bottom-up approach also provides the customer with an opportunity to compare the low-cost, efficient method approach with any imposed restrictions. For example, if the project completion duration is imposed at two years and your bottom-up analysis tells you the project will take two and one-half years, the client can now consider the trade-off of the low-cost method versus compressing the project to two years—or in rare cases canceling the project. Similar trade-offs can be compared for different levels of resources or increases in technical performance. The assumption is any movement away from the low-cost, efficient method will increase costs—e.g., overtime. The preferred approach in defining the project is to make rough top-down estimates, develop the WBS/OBS, make bottom-up estimates, develop schedules and budgets, and reconcile differences between top-down and bottom-up estimates. Hopefully, these steps will be done before final negotiation with either an internal or external customer. In conclusion, the ideal approach is for the project manager to allow enough time for both the top-down and bottom-up estimates to be worked out so a complete plan based on reliable estimates can be offered to the customer. In this way false expectations are minimized for all stakeholders and negotiation is reduced.

Homework is Completed By:

Writer Writer Name Amount Client Comments & Rating
Instant Homework Helper

ONLINE

Instant Homework Helper

$36

She helped me in last minute in a very reasonable price. She is a lifesaver, I got A+ grade in my homework, I will surely hire her again for my next assignments, Thumbs Up!

Order & Get This Solution Within 3 Hours in $25/Page

Custom Original Solution And Get A+ Grades

  • 100% Plagiarism Free
  • Proper APA/MLA/Harvard Referencing
  • Delivery in 3 Hours After Placing Order
  • Free Turnitin Report
  • Unlimited Revisions
  • Privacy Guaranteed

Order & Get This Solution Within 6 Hours in $20/Page

Custom Original Solution And Get A+ Grades

  • 100% Plagiarism Free
  • Proper APA/MLA/Harvard Referencing
  • Delivery in 6 Hours After Placing Order
  • Free Turnitin Report
  • Unlimited Revisions
  • Privacy Guaranteed

Order & Get This Solution Within 12 Hours in $15/Page

Custom Original Solution And Get A+ Grades

  • 100% Plagiarism Free
  • Proper APA/MLA/Harvard Referencing
  • Delivery in 12 Hours After Placing Order
  • Free Turnitin Report
  • Unlimited Revisions
  • Privacy Guaranteed

6 writers have sent their proposals to do this homework:

Helping Hand
Homework Guru
University Coursework Help
Best Coursework Help
Writer Writer Name Offer Chat
Helping Hand

ONLINE

Helping Hand

I am an Academic writer with 10 years of experience. As an Academic writer, my aim is to generate unique content without Plagiarism as per the client’s requirements.

$100 Chat With Writer
Homework Guru

ONLINE

Homework Guru

Hi dear, I am ready to do your homework in a reasonable price and in a timely manner.

$102 Chat With Writer
University Coursework Help

ONLINE

University Coursework Help

Hi dear, I am ready to do your homework in a reasonable price.

$102 Chat With Writer
Best Coursework Help

ONLINE

Best Coursework Help

I am an Academic writer with 10 years of experience. As an Academic writer, my aim is to generate unique content without Plagiarism as per the client’s requirements.

$100 Chat With Writer

Let our expert academic writers to help you in achieving a+ grades in your homework, assignment, quiz or exam.

Similar Homework Questions

The future of nursing leading change advancing health - 200 WORD RESPONSE - Keith rn case studies - MBA 599 DISCUSSION #7 - Part 61 manual of standards - Module 01: Essential functions of law and ethics in business. 5-6 Pages - Burton v davies [1953] qsr 26 - Cultural web analysis of samsung - Figure 34.1 label this anterior view of the human heart - Unsw full time load - Project management network diagram questions and answers pdf - Is 79 a composite number - Moreton bay rubbish tip opening hours - Read article and answer questions in essay form - Www kidsastronomy com solar system htm - The trouble with the term art summary - Iubmb nicholson metabolic pathways chart - Apple inc risk analysis - Exam 70 768 practice test - Alliance trust withdrawal form - Pooled standard deviation calculator excel - Dr scott blair west - Safety what safety case study solution - Non Profit-Final Project Milestone One: Organizational Profile - Limiting and excess reactants worksheet answers race car - General mills case study solution - Science buddies paper roller coaster - Tenon saw and bench hook - Frank parsons matching theory - Break even sales under present and proposed conditions - Discovering human sexuality 4th edition baldwin ebook - Pastoral spiral - Wedding project management assignment - 2-3 page . criminal case study and analysis - Semester paper - Velmead junior school fleet - Childhood Obesity - Waiting for godot upheaval - Programming - Trends in business information systems - How to wire up driving lights diagram - Economists generally define the short run as being - Homegoing abena chapter summary - Social mobile and local marketing - Hp 34401a gpib commands - Diageo case study capital structure - A7 8k l4 5p sequence - Statistics symbol cheat sheet - The progressive movement drew its strength from - Five forces beer industry - Isbn 978 1 259 92766 9 - From where can i get customize patches? - System security plan ssp template - Indefinite shape and indefinite volume - The sarbanes oxley act was enacted to - I need help!!!!! - Questions on christmas carol with answers - Pi controller block diagram - What is bavarian sausage inc s operating cash flow - But if vast numbers of Muslims across the world believe.......... - The road not taken questions with answers - Altium via in pad - Ccg junction box catalogue - Article Assignment - Sir charles gairdner hospital diabetes clinic - Parts of a stage - Importance of Becoming a Global Citizen - Cite your sources using apa format week 5 assignment - Www macmillanmh com science - Lawrence z arabii cda - Kerry foods graduate scheme - Sims 4 successfully train out 2 misbehaviors - Java generics test questions - Fiber-optic cable transmits data as pulses of light through tiny tubes of glass. - Computer work science - Main protective bonding conductor - ICC - Pro engineer wildfire 5.0 windows 10 - The distance of uranus from the sun - Write a 2500 words essay - Lee mack 9 letter word - A diagram and 1 page single space summary - Study information system tartu - Australian unity wholesale healthcare property trust - How much does amara pay - Humanistic and existential personality theories - 8 steps decision making process example management - Asme viii division 1 - Carinya classic awning frame - Boom and bitner 1981 - The last dance understanding death and dying - Bridgewater park primary school - Australian tax tables weekly - Community And Public Health Nursing - Paper - The slope of a velocity vs time graph represents - Describe homo erectus's cranial and postcranial anatomical characteristics - What are the alternative methods for building information systems - 600 words statistics math questions. Due in 3hrs. Statistics for Nursing Research - What was jonathan kozol’s impression of the poorly funded schools he visited in urban chicago?