Tony Prince Is The Project Manager For The Recreation And Wellness Intranet Project
Tony Prince is the project manager for the Recreation and Wellness Intranet Project. Team members include you, a programmer/analyst and aspiring project manager; Patrick, a network specialist; Nancy, a business analyst; and Bonnie, another programmer/analyst. Other people are supporting the project from other departments, including Yusaff from human resources and Cassandra from finance. Assume that these are the only people who can be assigned and charged to work on project activities. Recall that your schedule and cost goals are to complete the project in six months for under $200,000.
Tasks
1. Review the WBS and Gantt chart attached. Propose three to five additional activities that would help you estimate resources and durations. Describe these new activities.
2. Identify at least eight milestones for the Recreation and Wellness Intranet Project. Write a short description of each milestone using the SMART criteria. Discuss how determining these milestones might add activities or tasks to the Gantt chart. Remember that milestones normally have no duration, so you must have tasks that will lead to completing the milestone.
3. Using the Gantt chart attached and the new activities and milestones you proposed in Tasks 1 and 2 above, create a new Gantt chart using Project 2010. Estimate the task durations and enter dependencies as appropriate. Remember that your schedule goal for the project is six months. Print the Gantt chart and network diagram, each on one page.
4. Summarize how you would assign people to each activity from Tasks 1, 2, and 3. Include a table or matrix listing how many hours each person would work on each task. These resource assignments should make sense given the duration estimates made in Task 3 above. Remember that duration estimates are not the same as effort estimates because they include elapsed time.
1. The approach for collecting requirements for the project described in the Running Case is the formation of a requirements traceability matrix. This includes the following:
Requirement
Details
Budget
Working capital, Long term capital
Labor requirements
At different levels
Time and schedule
Work breakdown structure
Scope of the project
Strategic objective
Material
Material requirements
2.
Scope Statement
Project Title: Running case
Date: Prepared by:
Project Justification:
Required to implement the Recreation and Wellness Intranet Project
Product Characteristics and Requirements:
1. Technology based
2. Capital intensive
3. Long term and strategic benefits
4. Short deadlines
Summary of Project Deliverables
Project management-related deliverables: business case, charter, team contract, scope statement, WBS, schedule, cost baseline, status reports, final project presentation, final project report, lessons-learned report, and any other documents required to manage the project.
Product-related deliverables: research reports, design documents, software code, hardware, etc.
1. Project plan and scope statement
2. Design of the software
3. WBS and schedule
4. Budget and cost baseline
Project Success Criteria:
1. Completion on time and within budget
2. Improved intranet facilities in Recreation and Wellness Intranet Projects
3.
https://encrypted-tbn1.gstatic.com/images?q=tbn:ANd9GcShkLvYEBqsG2i79oPyhpLNK1ip26k8ufhiFtldXGAlJM5aKxZ70w
4.
http://2.bp.blogspot.com/-4z00ofFLy6k/TeY7nw4KBdI/AAAAAAAAABg/wMfrDV3F4Z0/s1600/pert_chart.jpg
http://4.bp.blogspot.com/-TmtDG4gWGAw/TeY73Rp2_6I/AAAAAAAAABk/9X3uzYhZjZ4/s1600/project_gantt_chart+%25281%2529.gif
Classification: //Dell SecureWorks/Confidential - Limited External Distribution:
Classification: //Dell SecureWorks/Confidential - Limited External Distribution:
Classification: //Dell SecureWorks/Confidential - Limited External Distribution: