EOS-RSA AUTHENTICATION SERVER UPGRADE 1
EOS-RSA AUTHENTICATION SERVER UPGRADE 12
EOS-RSA Authentication Server Upgrade
Project Scope, Schedule, and Budget
PM 598 – PM Mgmt. Capstone - Week 2
May 23, 2016
Project Description
The project End Of Support RSA Authentication servers is a project by the Bank of Tokyo which has been started so that the bank client’s and customer can have authentication services which will enable them access the bank internet applications, the RSA Authentication will also enable remote access through a RSA securID token.
The project will also have a Helpdesk Administration Portal which will enable Administrators to efficiently perform support activities to internal users. Finally, the project will also have a Standard Operating Procedure which will be used in approving and deploying RSA securID Soft Tokens which will eliminate cost associated with mailing or replacement of Hard Tokens to Internal Users.
Problem & Result Statement
The current version of RSA comes to End-of-Support on 12/31/2016. In the event of an RSA failure that requires technical support, customers will not be able to access Bank's Internet-facing systems. Some of the remedy to the problem statement will be:
· Reduce the RSA SecurID maintenance and RSA Administration costs
· Enhance and automate the process of deploying RSA SecurID
· Building a RSA Architecture needed to support RSA SecurID soft and hard token distribution
Project Justification
The Bank End-of-Support upgrade of the RSA environment was done in order to leverage the Enterprise plus license so as to reduce the cost of maintenance. The EOS-RSA Authentication Server Upgrade Project is the best because it will lower the cost of maintenance and also it will be able complete the activities which were started by Alternate Web Hosting Project and it has a RSA Architecture that will allow remote access to the environment by internal and external customers. As compared to other alternatives the EOS-RSA Authentication Server Upgrade Project is the best one to minimize the cost and allow support services to be efficiently performed.
Project Scope Statement
IN SCOPE
The following items are considered to be in scope for this project:
· Complete the replacement and configurations of the RSA Authentication Servers so that RSA Enterprise Plus Licenses can be installed, which will reduce the overall RSA license annual maintenance cost
· Provide a Self-Service Portal for internal users of the RSA environment.
· Ensure that the portal can be accessed on all bank owned devices, and on all bank approved personal devices
· Ensure that the self-service portal can be accessed on all bank supported browsers and on all supported browser versions.
· Provide an Admin Portal for the Helpdesk to more efficiently perform remote Internal User support activities
· Create a test environment so that future updates and fixes can be tested without interrupting Production.
· Ensure no service interruption in the event of either a Component or Data Center failure
OUT OF SCOPE
The following items are not within scope of this project:
· Implementing RSA Enterprise Plus licenses and a self-service portal for MUB and ISA-West Coast users.
· Providing a self-service portal for external customers.
Out of scope items will be considered in future projects
Major Project Deliverables
· Install the remaining RSA Authentication Servers in both the Harborside and Sterling Forest Data Centers
· Purchase new hardware and software for hosting a Self-Service and Helpdesk Portal for Internal Users
· Leverage the Enterprise Plus License structure to reduce license maintenance costs
· Install new RSA Self-Service Portals to reduce ongoing administrative and overhead costs, and improve the end-user experience of Internal Users
· Deploy a Self-Service Portal so that Internal Users working remotely can reset their RSA Token PIN without having to call the Helpdesk.
High level Milestones and significant event
The current high level milestones completion dates are as follows:
Planning
July 6, 2016
Design
August 7, 2016
Build & Configure Portals
September 18, 2016
Testing-Portals
November 13, 2016
Implementation: Portals
December 14, 2016
Build & Configure Soft Tokens
January 15, 2017
Testing: Soft Tokens
February 5, 2017
Implementation: Soft Tokens
February 22, 2017
ID
Milestone
Planned Completion
3
Project Initiation Request (PIR) Approved
4/17/2016
4
Kick-Off Security Risk Assessment
04/29/16
6
Obtain Initial Security Assessment Cost Estimations
05/08/16
8
Create BRD
05/04/16
11
BRD Sign-Off
05/15/16
13
Complete Initial Security Risk Assessment Spreadsheet
05/08/16
14
Review initial Security Risk Assessment (RSA)
05/15/16
15
Scope Pentest & Technical Security Standard Requirements
05/29/16
17
Provide Final Security Risk Assessment Cost Estimations and Quotes
06/05/16
25
Create Project Plan Document
06/12/16
26
Create WBS & Resource Plan
06/11/16
28
RINGI (Budget) Approval
07/22/16
30
EIS Planning Activities for Remaining Project Phases
07/06/16
36
Design Phase
07/06/16
85
Development Phase
07/06/16
146
Testing Phase
05/13/16
180
Pre-Implementation Phase
07/06/16
Items
Amount
Expected Semester Payment Term
2016/1
2016/2
2017/1
Investment
Hardware Purchase
$91,883.23
$91,883.23
S/W Development (Ext'l Consultant)
$140,215.00
$107,615.00
$32,600.00
S/W Purchase
$220,524.44
$220,524.44
Other
$16,597.10
$16,597.10
S/W Development (ISA Resources)
$75,446.82
$50,342.09
$25,104.73
S/W Development (ISA Resources Mark-Up)
$6,395.98
$4,262.08
$2,133.90
Sub Total
$551,062.57
$491,223.94
$59,838.63
Expense
Sales Tax
$21,372.49
$21,372.49
Sub Total
$21,372.49
$21,372.49
Grand Total
$572,435.06
$512,596.43
$59,838.63
$0.00
Project Schedule
Task Name
Duration
Start
Finish
Resource Names
EOS-RSA Authentication Server Upgrade
55.86 days?
Fri 5/20/16
Fri 8/5/16
Planning Phase
55.86 days?
Fri 5/20/16
Fri 8/5/16
Preview Milestones
10.29 days
Fri 5/20/16
Fri 6/3/16
PIR Approved
0 days
Fri 5/20/16
Fri 5/20/16
Kick-off Security
0 days
Sun 5/22/16
Sun 5/22/16
Complete EIS SRE Questionnaire
2 days
Sun 5/22/16
Mon 5/23/16
Kun Jiang
Obtain Initial Security Assessment Cost Estimations
0 days
Thu 6/2/16
Thu 6/2/16
Business & Infrastructure Requirements
10.29 days
Mon 5/30/16
Mon 6/13/16
Create BRD
5 days
Mon 5/30/16
Fri 6/3/16
Peter Tse (Koon Hing Tse)
Review BRD with SOE Management
0 days
Mon 5/30/16
Mon 5/30/16
Review BRD with QA and Obtain Approval
0 days
Wed 6/1/16
Wed 6/1/16
BRD Sign-off in ePLC
0 days
Thu 6/2/16
Thu 6/2/16
EIS Planning Phase Requirements & Activities
26.71 days
Mon 5/30/16
Tue 7/5/16
Complete Initial Security Risk Assessment Spreadsheet
5 days
Mon 5/30/16
Fri 6/3/16
Roger Brinkley, Kun Jiang
Review Initial Security Risk Assessment(SRA)
0 days
Thu 6/9/16
Thu 6/9/16
Scope Pentest and Technical Security Standard Requirements
10 days
Mon 6/13/16
Fri 6/24/16
Nikolay Belov
Scope BR and BCP Requirements
10 days
Mon 6/13/16
Fri 6/24/16
Peter Tse(Koon Hing Tse)
Provide Final Security Assessment Cost Estimations and quotes
5 days
Sat 6/25/16
Thu 6/30/16
Nikolay Belov
SME Reviews
10.29 days?
Mon 6/13/16
Mon 6/27/16
Create High Level Design Document
7 days
Mon 6/13/16
Tue 6/21/16
Kun Jiang, Peter Tse(Koon Hing Tse)
Conduct SME High Level Design Review Meeting
3 days
Fri 6/17/16
Tue 6/21/16
Kun Jiang
Submit SME Summary Sheet in ePLC
0 days
Mon 6/20/16
Mon 6/20/16
Ringi
30.86 days
Mon 5/30/16
Mon 7/11/16
Document Approach, Testing and Migration Strategy for Project planning
10 days
Mon 5/30/16
Fri 6/10/16
Kun Jiang, Peter Tse(Koon Hing Tse)
Obtain Cost Estimations & Quotes/SOWs
0 days
Fri 6/17/16
Fri 6/17/16
Create Project Plan Document and ePLC Deliverables
11 days
Wed 6/8/16
Wed 6/22/16
Create WBS and Resource Plan for Phase 2 to Phase 5
10 days
Wed 6/8/16
Tue 6/21/16
Submit Project Ringi
0 days
Mon 6/20/16
Mon 6/20/16
Ringi Local Approval in ePLC
0 days
Sat 7/2/16
Sat 7/2/16
Planning Activities for Remaining Project Phases
17 days
Sat 6/25/16
Mon 7/18/16
Kun Jiang, Peter Tse(Koon Hing Tse)
EIS Planning Activities for Remaining Project Phases
17 days
Sat 6/25/16
Mon 7/18/16
Nikolay Belov, Philip Norman
End of Planning Phase
0 days
Sun 7/17/16
Sun 7/17/16
Design Phase
1 day
Tue 8/2/16
Tue 8/2/16
Development Phase
1 day
Tue 8/2/16
Tue 8/2/16
Testing Phase
1 day
Tue 8/2/16
Tue 8/2/16
Pre-Implementation
0
Tue 8/2/16
Tue 8/2/16
Time-Phase Budget
Planning phase
Design Phase
Implementation
May-16
Jun-16
Jul-16
Aug-16
TOTAL
DIRECT COST
Supplies
$ 5,000.00
$ 3,000.00
$ 1,000.00
$ 1,000.00
$ 10,000.00
Developers salaries
$ 40,000.00
$ 40,000.00
$ 20,000.00
$ 20,000.00
$ 120,000.00
Materials
$ 100,000.00
$ 80,000.00
$ 180,000.00
Equipment
$ 10,000.00
$ 10,000.00
$ 90,000.00
$ 110,000.00
Consultancy cost
$ 2,000.00
$ 3,000.00
$ 4,000.00
$ 9,000.00
Travel expenses
$ 1,000.00
$ 2,000.00
$ 1,000.00
$ 4,000.00
Communication cost
$ 1,000.00
$ 500.00
$ 750.00
$ 1,000.00
$ 3,250.00
INDIRECT COST
Administration expenses
$ 5,000.00
$ 5,000.00
$ 5,000.00
$ 5,000.00
$ 20,000.00
Stakeholders Salaries
$ 2,500.00
$ 2,000.00
$ 2,000.00
$ 2,000.00
$ 8,500.00
Legal cost
$ 1,000.00
$ 500.00
$ 500.00
$ 500.00
$ 2,500.00
CUMULATIVE COST
$ 55,500.00
$ 165,000.00
$ 122,250.00
$124,500.00
$ 467,250.00
Work Breakdown Structure (Howard, 2013)
image1.png image2.png
REFERENCES
Howard, B. (2013). Microsoft Project 2013. Sebastopol, California : O'Reilly Media.
Kerzner, H. (2001). Project management : a systems approach to planning, scheduling, and controlling. New York: John Wiley.
Mehta, R. C. (2007). Project management. Jaipur: Aavishkar Publishers.
Grading Guide
Content
Met
Partially Met
Not Met
Comments:
Project scope is refined from Week 1’s charter.
X
A work breakdown structure is created.
X
WBS looks great.
A project schedule and budget is created.
X
A schedule is created for the project lifecycle in Microsoft® Project®.
X
The schedule is a good start. There are multiple levels. The task durations appear to be reasonable. Predecessor information needs to be setup for all tasks. Resources are defined and assigned.
Specific tasks and milestones are included with time and resource estimates.
X
A time-phased budget is created using Microsoft® Excel®
Using Microsoft® Excel®, create a time-phased budget containing cost estimates. Include direct and indirect costs for labor, machinery, equipment, supplies, and other elements applicable to the project.
X
The budget is contained within Project.
Total Available
Total Earned
7
6.5
Writing Guidelines
Met
Partially Met
Not Met
Comments:
The paper—including tables and graphs, headings, title page, and reference page—is consistent with APA formatting guidelines and meets course-level requirements.
X
Intellectual property is recognized with in-text citations and a reference page.
X
.
Paragraph and sentence transitions are present, logical, and maintain the flow throughout the paper.
X
Sentences are complete, clear, and concise.
X
Rules of grammar and usage are followed including spelling and punctuation.
X
Total Available
Total Earned
3
3
Assignment Total
#
10
9.5