I’m studying for my Management class and don’t understand how to answer this. Can you help me study?
ASSIGNMENT
Construct a network schedule (Gantt chart) in Microsoft® Project 2013 for the stadium project, using the information provided in the case.
Given the information provided in Table 6.3, (attached image) construct a network schedule for the stadium project and answer the following questions:
Will the project be able to be completed by the May 20 deadline? How long will it take?
What is the critical path for the project?
Based on the schedule would you recommend that G&E pursue this contact? Why? Include a one-page Gantt chart for the stadium schedule.
Greendale Stadium Case
The G&E Company is preparing a bid to build the new 47,000 seat Greendale baseball stadium. The construction must start July 1, 2011, and be completed in time for the start of the 2014 season. A penalty clause of $100,000 per day of delay beyond May 20, 2014, is written into the contract.