Loading...

Messages

Proposals

Stuck in your homework and missing deadline? Get urgent help in $10/Page with 24 hours deadline

Get Urgent Writing Help In Your Essays, Assignments, Homeworks, Dissertation, Thesis Or Coursework & Achieve A+ Grades.

Privacy Guaranteed - 100% Plagiarism Free Writing - Free Turnitin Report - Professional And Experienced Writers - 24/7 Online Support

The most common circumstance for project closure is simply a

23/11/2021 Client: muhammad11 Deadline: 2 Day

1 A ________ Gantt chart is a simple and effective way to depict progress on a project.

Control

Tracking

Simple

Baseline

Variance

2 A project monitoring system involves all of the following EXCEPT

Determining what data to collect.

Adjusting the data.

Reporting current progress.

Analysis of the data.

Determining how, when, and who will collect the data.

3 An analysis carried out during and shortly after the project life cycle that attempts to capture positive and negative learning is represented in which of the following?

Performance evaluation

Lessons learned

Scenario analysis

Strategic objectives

Variance analyses

4 Jessica just received the following information on her project: PV = 200, EV = 300, AC = 250, BAC = 1500, EAC = 1208. In terms of cost at completion.

The project will currently finish under budget.

The project will currently finish on budget.

The project will currently finish over budget.

The project will currently finish behind schedule.

There is insufficient information to draw conclusions.

5 Jim receives the following information on his project: PV = 1000, EV = 1200, AC = 800, BAC = 2000, EAC = 1333. How is the project doing in terms of schedule?

The same amount of work has been done than planned

More work has been done than planned

The project has cost less than planned

Less work has been done than planned

There is not enough information to draw a conclusion

6 Nancy tells her supervisor that as of right now, $1.05 worth of work has been accomplished for each $1 worth of scheduled work. Nancy got this information from viewing the

TCPI.

CPI.

SPI.

SV.

PCIB.

7 The cost variance for a project is calculated by

EV - PV.

PV - EV.

AC - SV.

CV - EV.

EV - AC.

8 The earned value system starts with the time-phased costs that provide the project baseline, which is called the

Earned value of work scheduled.

Planned budgeted value of work scheduled.

Scheduled value of work completed.

Scheduled value of work scheduled.

Planned budgeted value of work completed.

9 The first step in the project control process for measuring and evaluating project performance is to

Review the project priority matrix.

Determine the project objectives.

Analyze the project budget.

Set a baseline plan.

Determine the project deliverables.

10 The following are general tips for conducting performance reviews EXCEPT

Be fair and consistent in your treatment of all team members.

Use other team members' performance as a method to compare and evaluate.

Begin the process by asking the individual to evaluate his or her own contributions to the project.

When you have to be critical, focus the criticism on specific examples of behavior and not on the individual personally.

Treat the review as only one point in an ongoing process.

11 The most common circumstance for project closure is simply a ________ project.

Successful

Completed

Over-budget

Underachieving

Overdue

12 The purpose of project evaluation is to assess how well

The project team and team members performed.

The project team, team members and project manager performed.

The project team performed.

The project manager performed.

The team members performed.

13 The schedule variance for a project is calculated by:

PV - EV

AC - SV

CV - EV

EV - PV

EV - AC

14 The third step in the project control process for measuring and evaluating project performance is to

Compare the plan against actual performance.

Analyze inputs to the control system.

Review spending with team members.

Review the baseline plan with top management.

Measure both progress and performance.

15 The typical mechanism for the evaluation of teams is normally

A survey completed by the team members.

A survey completed by the internal or external customers.

A survey completed by members of top management.

An analysis by an outside consultant.

A personal interview of each team member.

16 When someone familiar with each task estimates what percent of the task has been completed or how much of the task remains, they are creating a method for assigning costs to the baseline called the

0/100 percent rule.

Work complete rule.

Task complete rule.

Degree complete rule.

Percent complete rule.

17 Which of the following methods will measure the cost efficiency of the work accomplished to date?

AC/CV

SV/CV

EV/PV

EV/AC

AC/SV

18 Which of the following would NOT be appropriate to assess when evaluating team performance?

Effectiveness of group decisions

How well the team performed in terms of time, cost, and specifications

Individual strengths and weaknesses

Customer satisfaction with project deliverables

Trust among group members

19 Which performance index is the most potentially misleading?

EV

CV

EAC

CPI

SV

20 ________ of lessons learned are designed to improve performance on current and future projects.

Culminations

Retrospectives

Evolutions

Corrective action plans

Introspectives
1 A ________ Gantt chart is a simple and effective way to depict progress on a project.

Control

Tracking

Simple

Baseline

Variance

2 A project monitoring system involves all of the following EXCEPT

Determining what data to collect.

Adjusting the data.

Reporting current progress.

Analysis of the data.

Determining how, when, and who will collect the data.

3 An analysis carried out during and shortly after the project life cycle that attempts to capture positive and negative learning is represented in which of the following?

Performance evaluation

Lessons learned

Scenario analysis

Strategic objectives

Variance analyses

4 Jessica just received the following information on her project: PV = 200, EV = 300, AC = 250, BAC = 1500, EAC = 1208. In terms of cost at completion.

The project will currently finish under budget.

The project will currently finish on budget.

The project will currently finish over budget.

The project will currently finish behind schedule.

There is insufficient information to draw conclusions.

5 Jim receives the following information on his project: PV = 1000, EV = 1200, AC = 800, BAC = 2000, EAC = 1333. How is the project doing in terms of schedule?

The same amount of work has been done than planned

More work has been done than planned

The project has cost less than planned

Less work has been done than planned

There is not enough information to draw a conclusion

6 Nancy tells her supervisor that as of right now, $1.05 worth of work has been accomplished for each $1 worth of scheduled work. Nancy got this information from viewing the

TCPI.

CPI.

SPI.

SV.

PCIB.

7 The cost variance for a project is calculated by

EV - PV.

PV - EV.

AC - SV.

CV - EV.

EV - AC.

8 The earned value system starts with the time-phased costs that provide the project baseline, which is called the

Earned value of work scheduled.

Planned budgeted value of work scheduled.

Scheduled value of work completed.

Scheduled value of work scheduled.

Planned budgeted value of work completed.

9 The first step in the project control process for measuring and evaluating project performance is to

Review the project priority matrix.

Determine the project objectives.

Analyze the project budget.

Set a baseline plan.

Determine the project deliverables.

10 The following are general tips for conducting performance reviews EXCEPT

Be fair and consistent in your treatment of all team members.

Use other team members' performance as a method to compare and evaluate.

Begin the process by asking the individual to evaluate his or her own contributions to the project.

When you have to be critical, focus the criticism on specific examples of behavior and not on the individual personally.

Treat the review as only one point in an ongoing process.

11 The most common circumstance for project closure is simply a ________ project.

Successful

Completed

Over-budget

Underachieving

Overdue

12 The purpose of project evaluation is to assess how well

The project team and team members performed.

The project team, team members and project manager performed.

The project team performed.

The project manager performed.

The team members performed.

13 The schedule variance for a project is calculated by:

PV - EV

AC - SV

CV - EV

EV - PV

EV - AC

14 The third step in the project control process for measuring and evaluating project performance is to

Compare the plan against actual performance.

Analyze inputs to the control system.

Review spending with team members.

Review the baseline plan with top management.

Measure both progress and performance.

15 The typical mechanism for the evaluation of teams is normally

A survey completed by the team members.

A survey completed by the internal or external customers.

A survey completed by members of top management.

An analysis by an outside consultant.

A personal interview of each team member.

16 When someone familiar with each task estimates what percent of the task has been completed or how much of the task remains, they are creating a method for assigning costs to the baseline called the

0/100 percent rule.

Work complete rule.

Task complete rule.

Degree complete rule.

Percent complete rule.

17 Which of the following methods will measure the cost efficiency of the work accomplished to date?

AC/CV

SV/CV

EV/PV

EV/AC

AC/SV

18 Which of the following would NOT be appropriate to assess when evaluating team performance?

Effectiveness of group decisions

How well the team performed in terms of time, cost, and specifications

Individual strengths and weaknesses

Customer satisfaction with project deliverables

Trust among group members

19 Which performance index is the most potentially misleading?

EV

CV

EAC

CPI

SV

20 ________ of lessons learned are designed to improve performance on current and future projects.

Culminations

Retrospectives

Evolutions

Corrective action plans

Introspectives

Homework is Completed By:

Writer Writer Name Amount Client Comments & Rating
Instant Homework Helper

ONLINE

Instant Homework Helper

$36

She helped me in last minute in a very reasonable price. She is a lifesaver, I got A+ grade in my homework, I will surely hire her again for my next assignments, Thumbs Up!

Order & Get This Solution Within 3 Hours in $25/Page

Custom Original Solution And Get A+ Grades

  • 100% Plagiarism Free
  • Proper APA/MLA/Harvard Referencing
  • Delivery in 3 Hours After Placing Order
  • Free Turnitin Report
  • Unlimited Revisions
  • Privacy Guaranteed

Order & Get This Solution Within 6 Hours in $20/Page

Custom Original Solution And Get A+ Grades

  • 100% Plagiarism Free
  • Proper APA/MLA/Harvard Referencing
  • Delivery in 6 Hours After Placing Order
  • Free Turnitin Report
  • Unlimited Revisions
  • Privacy Guaranteed

Order & Get This Solution Within 12 Hours in $15/Page

Custom Original Solution And Get A+ Grades

  • 100% Plagiarism Free
  • Proper APA/MLA/Harvard Referencing
  • Delivery in 12 Hours After Placing Order
  • Free Turnitin Report
  • Unlimited Revisions
  • Privacy Guaranteed

6 writers have sent their proposals to do this homework:

Coursework Assignment Help
Pro Writer
Assignments Hut
Top Writing Guru
Professor Smith
Assignment Helper
Writer Writer Name Offer Chat
Coursework Assignment Help

ONLINE

Coursework Assignment Help

I find your project quite stimulating and related to my profession. I can surely contribute you with your project.

$15 Chat With Writer
Pro Writer

ONLINE

Pro Writer

I am a professional and experienced writer and I have written research reports, proposals, essays, thesis and dissertations on a variety of topics.

$36 Chat With Writer
Assignments Hut

ONLINE

Assignments Hut

Being a Ph.D. in the Business field, I have been doing academic writing for the past 7 years and have a good command over writing research papers, essay, dissertations and all kinds of academic writing and proofreading.

$23 Chat With Writer
Top Writing Guru

ONLINE

Top Writing Guru

I am an academic and research writer with having an MBA degree in business and finance. I have written many business reports on several topics and am well aware of all academic referencing styles.

$48 Chat With Writer
Professor Smith

ONLINE

Professor Smith

This project is my strength and I can fulfill your requirements properly within your given deadline. I always give plagiarism-free work to my clients at very competitive prices.

$38 Chat With Writer
Assignment Helper

ONLINE

Assignment Helper

I can assist you in plagiarism free writing as I have already done several related projects of writing. I have a master qualification with 5 years’ experience in; Essay Writing, Case Study Writing, Report Writing.

$28 Chat With Writer

Let our expert academic writers to help you in achieving a+ grades in your homework, assignment, quiz or exam.

Similar Homework Questions

What are the four common uses of comparative data - Students in a high school statistics class were given data - School of rock mr schneebly - Ato aps 6 salary - Paragon internet group tsohost - Ethernet mac sublayer protocol ppt - Gpa calculator visual basic - Review Writing Assignment Peer Review - Tesla product life cycle analysis - Maximum benefit from independent internal verification is obtained when - Https m youtube com watch v ekhtsc9pu2a - Movie of metropolis reading answer - Excel guided project 3 3 - Www talentsmart com me welcome - Module 1 - SLP SIMULATION EXPERIENCE AND REVIEW - DISASTER - What was albert einsteins iq - Mass effect 3 kakliosaur location - Peter thieriot - God is here piano - Examples of symbolism in literature - Https serialpodcast org season one - Johnny rockabilly has just finished recording his latest cd - English essay - Thomas jefferson dbq - How to write a proposal for professional development - Taxonomy classification and dichotomous keys worksheet answers - Fdr's four freedoms speech analysis - Celf 5 sample report - Development is multidimensional multidirectional and pliable - Requirements for starting an ecd centre in south africa - Boeing west virginia - 2pages with out references no plagiarism - Celf 5 screener subtest descriptions - Invested cash and equipment journal entry - How to sharpen an axe with a belt sander - Address and postcode nz - Muslim Molvi 7340613399 OnLine No 1 FaMOUs VashIKaraN sPecIaLIsT IN Tirupati - Algebraic fractions multiplying and dividing - Bob tait's aviation theory school - Seven laws of training issa - Horizontal flower arrangement definition - Datex ohmeda aespire machine check - What are skew lines in geometry - Hcl sr oh 2 - Resource allocation in software project management ppt - Nim game smart computer java - Www cyborlink com besite china htm - Dulux linseed and woodland grey - What is a discourse community essay - Which type of variance causes operating income to be greater than the budgeted operating income? - Titration for acetic acid in vinegar lab report - Play therapy uk register - Discover psychology 2.0 a brief introductory text - How to fill fluid balance chart - 1000 word research proposal example - South australian surf life saving - Assignment 1: Combating Juvenile Delinquency - Contentious in to kill a mockingbird - Trevor noah colorblind - Data Mining Term Paper - Spotlight retail group abn - Drugged high on alcohol worksheet answers - Bioflix activity homeostasis low blood glucose - Guidance - Program Execution - Rbi ionic or covalent - Week 4 discussion - Action Plan Assignment - Member churches of the ncca - The major physiologic manifestation of anemia is - Quality Management - Ma lpc ncc meaning - Straw man definition and examples - Blanket overhead absorption rate formula - Power supply troubleshooting and repair - +91-8306951337 get your love back by vashikaran IN Erode - The hierarchical data model was developed in the _____. - Justin bieber proactiv ad - What are the four largest satellites discovered by galileo - F leadership development programs - What to do with a history degree besides teach - Should vaccines be mandatory essay - Discussion - Mass vs weight physics worksheet - One steel span tables - Writing activity 150-300 words - CU-SAPAnalyticsCloud_Fishbanks_Exercise - Discussion 8 - Tone colour words music - Asa24 login - Nucor big 11 success factors - Secondary school leaving certificate sample - Cube root of 35937 - One man brake bleeder autozone - Case study - Campmaster butane stove recall - Analysis of vinegar by titration pre lab - Ul listed pressure gauge - Discussion post (two) - Carina bus depot lost property