The project scope document is valuable for establishing

16/11/2020 Client: arwaabdullah Deadline: 24 Hours

Question 1

Expected benefits, which will result from implementation of the project and define success, establish:

Question options:

how quickly the project must be completed.

how much money the customer is willing to pay.

the reason the contractor proposes the solution.

why the project is being done.

Question 2

The contractor or project team needs to gain agreement from _____ on the project scope document.

Question options:

the sponsor or customer

only the contractor's chief financial officer

only the subcontractors

all the stakeholders

Question 3

The project scope document is valuable for establishing:

Question options:

a request for proposal for the project.

the risk management plan for the project.

the contact between the contractor and the customer.

a common understanding among project stakeholders regarding the scope of the project.

Question 4

In order to prevent poor quality and avoid quality problems, there needs to be a/an:

Question options:

work breakdown structure.

audit at the end of the project.

responsibility assignment matrix.

project quality plan.

Question 5

The __________ defines what the project team or contractor will do.

Question options:

statement of work

network diagram

work breakdown structure

project scope document

Question 6

It is important to plan for __________ in performing the project to assure that the work is done according to specifications and applicable standards and that deliverables meet acceptance criteria.

Question options:

time

scope creep

quality

resources

Question 7

A __________ emphasizes who is responsible for each work item and shows each individual's role in supporting the overall project.

Question options:

responsibility assignment matrix

project scope document

work breakdown structure

network diagram

Question 8

For each deliverable, the quantitative measures or references to __________ that will be used should be stated, as the criteria will be the basis for the customer agreeing that a deliverable is acceptable.

Question options:

quantitative and qualitative levels

audits and surveys

published articles

specifications, standards, and codes

Question 9

The project scope is all the work that must be done to do all of the following, EXCEPT:

Question options:

accomplish the project objective.

satisfy the sponsor or customer that all the work and deliverables meet the requirements or acceptance criteria.

produce all the project deliverables.

meet with every stakeholder.

Question 10

To help assure quality, the project quality plan should contain written procedures for:

Question options:

scope creep.

using various quality tools and techniques, such as audits, inspections, testing, checklists, and so on.

communicating with stakeholders about subcontractors.

assigning resources to tasks to be sure they meet the acceptance criteria.

Question 11

The major work elements defined in the statement of work section along with the detailed list of deliverables provide the basis for creating a:

Question options:

project scope document.

statement of work.

work breakdown structure.

network diagram.

Question 12

A __________ is a hierarchical decomposition of the project work scope into work packages that produce the project deliverables.

Question options:

network diagram

project scope document

work breakdown structure

statement of work

Question 13

Once the project scope document has been prepared and agreed on, the next step in the planning phase is to:

Question options:

begin work on the project.

monitor and control the quality to assure acceptance.

create a detailed work breakdown structure.

prepare and approve the contract.

Question 14

The __________ may include a high-level WBS in a graphic chart format or as an indentured list of the work elements and associated deliverables.

Question options:

network diagram

work breakdown structure

project scope document

statement of work

Question 15

Acceptance criteria for all project deliverables must be __________ than what is stated in the project charter or request for proposal.

Question options:

described in greater detail

listed in sequence with the responsible person or organization

stated at higher levels

repeated

Question 16

Quality standards that will be used should also be stated and referenced in other appropriate project documents, such as technical specifications and acceptance criteria, and communicated to members of the project team:

Question options:

after the work begins on the project.

at the outset of the project before the work begins.

at the end to check that the quality is met.

when the project team starts working on the specific tasks.

Question 17

The __________ is a communication tool for the project team because it shows who is responsible for each activity and how each person's work fits into the overall project.

Question options:

responsibility assignment matrix

project scope statement

network diagram

work breakdown structure

Question 18

Although major or key deliverables may be stated in the project charter or request for proposal, they need to be __________ in the project scope document.

Question options:

expanded on in greater detail

listed in sequence with the responsible person or organization

repeated

stated at higher levels

Question 19

It is easier to define the details for __________, but as the project progresses or moves from phase to phase, the project team or contractor can progressively elaborate the details as more information is known or becomes clear.

Question options:

only tasks that take a day to complete

tasks that require a small effort

the near-term efforts

tasks near the end of the project

Question 20

The __________ is the tangible end product that the project team or contractor must produce and deliver in order for the sponsor or customer to achieve the expected benefits from implementing the project.

Question options:

objective

project plan

network diagram

work breakdown structure

Homework is Completed By:

Writer Writer Name Amount Client Comments & Rating
Instant Homework Helper

ONLINE

Instant Homework Helper

$36

She helped me in last minute in a very reasonable price. She is a lifesaver, I got A+ grade in my homework, I will surely hire her again for my next assignments, Thumbs Up!

Order & Get This Solution Within 3 Hours in $25/Page

Custom Original Solution And Get A+ Grades

  • 100% Plagiarism Free
  • Proper APA/MLA/Harvard Referencing
  • Delivery in 3 Hours After Placing Order
  • Free Turnitin Report
  • Unlimited Revisions
  • Privacy Guaranteed

Order & Get This Solution Within 6 Hours in $20/Page

Custom Original Solution And Get A+ Grades

  • 100% Plagiarism Free
  • Proper APA/MLA/Harvard Referencing
  • Delivery in 6 Hours After Placing Order
  • Free Turnitin Report
  • Unlimited Revisions
  • Privacy Guaranteed

Order & Get This Solution Within 12 Hours in $15/Page

Custom Original Solution And Get A+ Grades

  • 100% Plagiarism Free
  • Proper APA/MLA/Harvard Referencing
  • Delivery in 12 Hours After Placing Order
  • Free Turnitin Report
  • Unlimited Revisions
  • Privacy Guaranteed

6 writers have sent their proposals to do this homework:

Buy Coursework Help
Quality Homework Helper
Writer Writer Name Offer Chat
Buy Coursework Help

ONLINE

Buy Coursework Help

Hi dear, I am ready to do your homework in a reasonable price.

$62 Chat With Writer
Quality Homework Helper

ONLINE

Quality Homework Helper

Hi dear, I am ready to do your homework in a reasonable price.

$62 Chat With Writer

Let our expert academic writers to help you in achieving a+ grades in your homework, assignment, quiz or exam.

Similar Homework Questions

Sunsuper binding death benefit nomination - Simple random sampling in excel - A bucket of water can be whirled - Rmit point cook open day - Consumer behavior by wayne d hoyer deborah j macinnis pdf - Guns on college campuses debate - Anxiety Disorders in the Media - Arlec pa1500 portable air conditioner - Charlie echo delta alphabet - Hrm 300 week 5 trends in hr management analysis - 12 week speed and agility program - Keith rn case studies - Intro to human communication - Enthalpy of anhydrous copper sulphate - Duane ludwig peanut butter - Melting temperature of gold and silver - Identity umd edu - Ransomware assignment - Which is larger kb or mb - Countermeasures used in a Crisis Response - Vincent owners club uk - Non Compete - Personhood chart materialism - College assesment quiz - Tomlinson harashima precoding matlab code - How can businesses choose the right logo design agency? - Low pass filter calculator excel - Or have we eaten on the insane root meaning - Nike supply and demand analysis - The rhythms of impressionist music often show ____________ influences - How to write action research project - Security architecture 2 - The Internet of Things and its impact on individual privacy and security - The locker problem worksheet - Skills required to work at starbucks - American GOV. DISCUSSION - Simile effect in poetry - Tp fastt poetry analysis chart - VBA Excel - Inventory information for part 311 - Which is a reactant in the calvin cycle - Leadership traits of martin luther king jr - Muslim Molvi 7340613399 OnLine No 1 FaMOUs VashIKaraN sPecIaLIsT IN Agartala - Risk assessment for office based activities - Unsw assignment cover sheet - Dissertation writing services - Logic and critical thinking ppt - All hail the king of glory vincent bohanan - Unisuper accumulation 2 pds - Need help in homework IOT - How many molecules in water - Styrofoam cup calorimeter lab report - Capgemini em foundation certification questions - Compound miter angle chart - M commerce infrastructure ppt - Aramark refreshment services locations - I will do it - Navitas compania maritima sa - University physics with modern physics 12e young - What is non productive time in healthcare - Flatworm and horseshoe crab symbiosis - Change assignment - What are the primary components of panera bread's value chain - Transition words mini lesson - Roof racks galore oxley - Nursing 590 - Freedom rides australia newspaper articles - Why do amides have higher boiling points than carboxylic acids - Philosophical problems an annotated anthology pdf - Item difficulty in psychological testing - Migrant worker student finance - Parking at sydney children's hospital - Organ Leader & Decision Making - See if i care answers - Optimizing Academic Success with Psychology Writing Services - Idexx learning center cornerstone - Metal pegs home depot - Transgenerational model of family therapy - Ursula burns personal and organizational values - Why america is self segregating they say i say - Trade off analysis decision making - Force displacement graph area - Cherry willingham cricket club - Words to use when analysing text - Sexual innuendo in disney movies - My johari window essay - Improve decision making - How to adjust nitrogen shocks - Bachelor of law monash atar - Organizational Theory - Running record observation example - Topics In Theory - Uae now and before - Criminal justice juvenile - Canvas quiz auto save - Discussion #2 - A man flies a small airplane from fargo to - How much yen per dollar - Australia's four main landform regions - Science spot forensic entomology