The project scope document is valuable for establishing

05/01/2021 Client: saad24vbs Deadline: 3 days

Question 1


Expected benefits, which will result from implementation of the project and define success, establish:


Question options:




how quickly the project must be completed.




how much money the customer is willing to pay.




the reason the contractor proposes the solution.




why the project is being done.


Question 2


The contractor or project team needs to gain agreement from _____ on the project scope document.


Question options:




the sponsor or customer




only the contractor's chief financial officer




only the subcontractors




all the stakeholders


Question 3


The project scope document is valuable for establishing:


Question options:




a request for proposal for the project.




the risk management plan for the project.




the contact between the contractor and the customer.




a common understanding among project stakeholders regarding the scope of the project.


Question 4


In order to prevent poor quality and avoid quality problems, there needs to be a/an:


Question options:




work breakdown structure.




audit at the end of the project.




responsibility assignment matrix.




project quality plan.


Question 5


The __________ defines what the project team or contractor will do.


Question options:




statement of work




network diagram




work breakdown structure




project scope document


Question 6


It is important to plan for __________ in performing the project to assure that the work is done according to specifications and applicable standards and that deliverables meet acceptance criteria.


Question options:




time




scope creep




quality




resources


Question 7


A __________ emphasizes who is responsible for each work item and shows each individual's role in supporting the overall project.


Question options:




responsibility assignment matrix




project scope document




work breakdown structure




network diagram


Question 8


For each deliverable, the quantitative measures or references to __________ that will be used should be stated, as the criteria will be the basis for the customer agreeing that a deliverable is acceptable.


Question options:




quantitative and qualitative levels




audits and surveys




published articles




specifications, standards, and codes


Question 9


The project scope is all the work that must be done to do all of the following, EXCEPT:


Question options:




accomplish the project objective.




satisfy the sponsor or customer that all the work and deliverables meet the requirements or acceptance criteria.




produce all the project deliverables.




meet with every stakeholder.


Question 10


To help assure quality, the project quality plan should contain written procedures for:


Question options:




scope creep.




using various quality tools and techniques, such as audits, inspections, testing, checklists, and so on.




communicating with stakeholders about subcontractors.




assigning resources to tasks to be sure they meet the acceptance criteria.


Question 11


The major work elements defined in the statement of work section along with the detailed list of deliverables provide the basis for creating a:


Question options:




project scope document.




statement of work.




work breakdown structure.




network diagram.


Question 12


A __________ is a hierarchical decomposition of the project work scope into work packages that produce the project deliverables.


Question options:




network diagram




project scope document




work breakdown structure




statement of work


Question 13


Once the project scope document has been prepared and agreed on, the next step in the planning phase is to:


Question options:




begin work on the project.




monitor and control the quality to assure acceptance.




create a detailed work breakdown structure.




prepare and approve the contract.


Question 14


The __________ may include a high-level WBS in a graphic chart format or as an indentured list of the work elements and associated deliverables.


Question options:




network diagram




work breakdown structure




project scope document




statement of work


Question 15


Acceptance criteria for all project deliverables must be __________ than what is stated in the project charter or request for proposal.


Question options:




described in greater detail




listed in sequence with the responsible person or organization




stated at higher levels




repeated


Question 16


Quality standards that will be used should also be stated and referenced in other appropriate project documents, such as technical specifications and acceptance criteria, and communicated to members of the project team:


Question options:




after the work begins on the project.




at the outset of the project before the work begins.




at the end to check that the quality is met.




when the project team starts working on the specific tasks.


Question 17


The __________ is a communication tool for the project team because it shows who is responsible for each activity and how each person's work fits into the overall project.


Question options:




responsibility assignment matrix




project scope statement




network diagram




work breakdown structure


Question 18


Although major or key deliverables may be stated in the project charter or request for proposal, they need to be __________ in the project scope document.


Question options:




expanded on in greater detail




listed in sequence with the responsible person or organization




repeated




stated at higher levels


Question 19


It is easier to define the details for __________, but as the project progresses or moves from phase to phase, the project team or contractor can progressively elaborate the details as more information is known or becomes clear.


Question options:




only tasks that take a day to complete




tasks that require a small effort




the near-term efforts




tasks near the end of the project


Question 20


The __________ is the tangible end product that the project team or contractor must produce and deliver in order for the sponsor or customer to achieve the expected benefits from implementing the project.


Question options:




objective




project plan




network diagram




work breakdown structure



Homework is Completed By:

Writer Writer Name Amount Client Comments & Rating
Instant Homework Helper

ONLINE

Instant Homework Helper

$36

She helped me in last minute in a very reasonable price. She is a lifesaver, I got A+ grade in my homework, I will surely hire her again for my next assignments, Thumbs Up!

Order & Get This Solution Within 3 Hours in $25/Page

Custom Original Solution And Get A+ Grades

  • 100% Plagiarism Free
  • Proper APA/MLA/Harvard Referencing
  • Delivery in 3 Hours After Placing Order
  • Free Turnitin Report
  • Unlimited Revisions
  • Privacy Guaranteed

Order & Get This Solution Within 6 Hours in $20/Page

Custom Original Solution And Get A+ Grades

  • 100% Plagiarism Free
  • Proper APA/MLA/Harvard Referencing
  • Delivery in 6 Hours After Placing Order
  • Free Turnitin Report
  • Unlimited Revisions
  • Privacy Guaranteed

Order & Get This Solution Within 12 Hours in $15/Page

Custom Original Solution And Get A+ Grades

  • 100% Plagiarism Free
  • Proper APA/MLA/Harvard Referencing
  • Delivery in 12 Hours After Placing Order
  • Free Turnitin Report
  • Unlimited Revisions
  • Privacy Guaranteed

6 writers have sent their proposals to do this homework:

Helping Hand
University Coursework Help
Writer Writer Name Offer Chat
Helping Hand

ONLINE

Helping Hand

I am an Academic writer with 10 years of experience. As an Academic writer, my aim is to generate unique content without Plagiarism as per the client’s requirements.

$100 Chat With Writer
University Coursework Help

ONLINE

University Coursework Help

Hi dear, I am ready to do your homework in a reasonable price.

$102 Chat With Writer

Let our expert academic writers to help you in achieving a+ grades in your homework, assignment, quiz or exam.

Similar Homework Questions

Adlerian psychology birth order - Rangeview rangers netball club - Jade vine hotel manila - Advantages and disadvantages of authoritative parenting - Bettini v gye case summary - Falling from grace characters - Costco employee turnover rate 2012 - Hyundai trajet towing capacity - Segway distribution channels - Business Plan W6 - Maestro air 30cm mist fan - Nab small business plan template - Rose bush called deborah - Hhmi lizard evolution virtual lab - Pall hydrophobic vent filter - Available on or upon request - Child family and community 7th edition - Kay's rule for real gas mixtures - Langley sound and light - Advantages and disadvantages of different types of computers - Victoria transport policy institute - Vernier dissolved oxygen probe - A child called it online free - The trial balance of bellemy fashion center - 6-2 Application Assignment: Online Fraud - What is percent recovery in chemistry - All india association of industries - How to calculate bid ask spread percentage - Definition of malevolent phantom - Individual Written Analysis of the Case (WAC) “Chick-Fil-A: International Expansion Challenges” - What is midnight in 24 hour time - How much acetic acid is in vinegar lab - Los pronombres de objeto directo e indirecto en español - Electronics - River flows in you words - Knowledge of postal administrative procedures and mail classification - Designing adaptive organizations pdf - Average heart rate of daphnia - Standard form to general form circle - Gas metal arc welding ppt - Microsoft access reserved words - Statistics Exam - How to report greenhouse geisser - Sul ross del rio - The dangers of using slang in business writing include - 20 bps in percentage - Wanniassa high school senior campus - Gu10 light fitting instructions - Summary - Miller corporation has a premium bond making - Gridworld answer key - Example of a base word - Peoples first community bank tallahassee fl - Online Law Assignment Help Company - Call Mee+91-9829644411 LOVe VaShikarAn SpEcialist MolVI Ji - Sii4 lewis dot structure - Why are field lines perpendicular to equipotential lines - SOCW 6520 - Three stage model of interviewing - Differences between maslow's hierarchy of needs and erg theory - Introduction to criminal justice 9th edition - Industrial technology timber past papers - Carly fraser eye color change - ASQ poster presentation - Need help making a chart - Certified seed potatoes for sale tasmania - The large piston in a hydraulic lift - Discussion - Dessertion Paper - Define isoquant and isocost - Assignment - Uncle hubbas green lean elixir - Hostel database management system - Duvall 1977 family life cycle - Frankston council pergola permit - Columbus journal of the first voyage to america - Discussion Question 1 - Static electricity lab report - Core competencies of maruti suzuki - Algot pull out rail - Design consulting data series excel - Lee v lee's air farming ltd - Arizona brick corporation produces bricks in two - Most effective teacher (one page) - Community Nursing Research paper # 2 - Econ 545 final exam answers - How to do limiting reagent questions - Electric wheelchairs - How to do the tablecloth trick - A quilt of a country by anna quindlen - Society basics w out mysociologylab - simulation in public policy - Compound acinar gland example - John deere ac refrigerant capacities - Meta chart bar graph - St patrick's cathedral bunbury - Sweets dresser pocket camp - Explain how the discussion of moneyball - Australian counseling association code of ethics - Eat drink man woman cooking scene