Wedding project management assignment

28/12/2020 Client: saad24vbs Deadline: 7 Days

<Wedding planning


<Class Name>


<Student Name>


<Date>


2


8


Table of Contents


Wedding plan project charter 2


Project Purpose/Justification 2


Description 2


Objective 2


Project Stakeholders 2


Funding 3


Project Success Criteria 3


Major Deliverables 4


Constraints 5


Assumptions 5


Acceptance Criteria 5


Milestone Schedule 6


Risks 6


Summary Budget 6


Approval Requirements 7


References 8


Wedding plan project charter

Project Purpose/Justification

The purpose of this project is to plan the wedding so that quality is achieved while ensuring that all constrains and risks are kept in check. Therefore, the wedding ceremony will go on without any encounters or minimal if there will be any.


Description

The project charter is used for performing different tasks in various stages of project development. This document explains the processes that must be accomplished right from the moment the project commences to the end. Having a well-designed project charter ensures that every deliverable is done and completed in time; thus, avoiding the technical challenges occurring in the process.


Objective

Before the commencement of the project, it is important to detail every aspect and plan that will be implemented. The wedding function has some specific tasks that should be entirely completed correctly for the successful completion of the project. These details include the stakeholders involved, resources that are going to be used, project success criteria, project deliverables, constraints, and project success criteria among other tasks crucial in the project.


Project Stakeholders

Task Stakeholders – List all resources who have a part in the project success


Stakeholder


Description


· Project Manager


Responsible for the overall planning, execution and successful delivery of the project.


· Sponsor


The project sponsor is responsible for funding all the functions in the project.


· Project team


The team members perform the basic tasks in the process of project development.


· Wedding vendors


Responsible for making everything important at that particular date of the wedding.


· Family members


Organizing what is required at the wedding.


· Bride and groom


Are the real guest of the stakeholders


Funding

Most of the funds come from individuals with a mutual interest in colorful and successful weddings (Verzuh, 2005). For this wedding project, the funds will come from the friends and relative, but the large proportion come from the bride and groom who are the main stakeholders who have the resources that will sponsor the wedding project, and who is also interested in the overall success of the project as well. The wedding team members are given the task of determining the projected amount that will be spent on the overall wedding function. The amount suggested must go through the wedding panel to determine its feasibility. The wedding funds will not include other activities done after the day of the wedding ceremony.


Project Success Criteria

The project manager will be required to communicate the status of the project on the weekly bases the main sponsors (bride and groom). The following factors will determine project success.


1. Cost


The wedding and all other functions on the given date of the ceremony will be required to complete within $ 20, 000 dollars.


Also, the costs will further need some changes since the resources and estimates of costs are on a contract basis.


2. Quality


The quality of the functions shall be upheld and in order to be well-thought-out to have met that quality, the following requirements must be looked at. All the wedding plans will be done according to the requests and plans of the bride and the groom.


a. The bride and the groom will have to inspect all the requirements before they are booked into the reception.


b. All the risks management issue shall be done by the bride, groom, and the project manager.


c. The primary goal of the project is for the bride and groom to enjoy and create enjoyable memories.


Major Deliverables

The project deliverables include those items that must be delivered on the particular date of the function or even in the process of planning (Fangel, 2018). These deliverables will include:


i. The wedding location


ii. Reception site


iii. Preferred wedding colors


iv. The guest lists


v. The invitations


vi. Wardrobes


vii. Food catering


viii. Interior decoration


ix. Marriage license


x. Executive reception


Constraints

The project constraints provide factors that could affect the success of the overall project. The wedding plan project constraints are:


i. The key stakeholders, bride, and groom have no acceptable funds to obtain the project.


ii. The project must be completed immediately


iii. The estimated budget must not be more than $ 10,000


iv. The gust should be more than 175 participants


Assumptions

The assumption of the project are those factors that have a limited effect on the overall progress of the project and even its success (Project Management Institute, 2018). The assumptions of this particular wedding projects are:


i. The bride and groom have selected the date of the function that will never be altered or changed.


ii. The bride and the groom will not back out of the wedding


iii. The project will be completed on December 20th, 2019 which will be carried out within the estimated budget.


Acceptance Criteria

When dealing with the deliverables from the vendors, those deliverables must be within the quality, the budget and the requirements stated in the contract document ("Project Charter," 2016). The deliverables from other interested parties, family and friends, are appreciated and are expected to be beautiful and perfection guaranteed.


Milestone Schedule

Summary Milestone Schedule – List key project milestones relative to the project start.


Project Milestone


Target Date (2/20/6-20)


· Project Start


10/1/2019


· Deciding the number guest


12/20/2019


· Weeding Item shopping and Hotel Booking


2/20/2020


· Ordering wedding stationaries and transportation


4/20/2020


· Send wedding invitation and menu detail discussion


5/20/2020


· Buying a guest book, seating preparation plan, and guest plan confirmation


6/10/2020


· Project Complete


10/20/2020


Risks

High Level Rick – List high level project risk


Risk Factor


Project Impact


(High, Med, Low)


· Resource Contract Risk


high


· Budget Risk


high


· Sponsor Support Risk


low


· Schedule Risk


med


Summary Budget

The following table contains a summary budget based on the planned cost components and estimated costs required for the successful completion of the project.


Summary Budget – List component project costs


Project Component


Component Cost


· Venue


$500


· Attire (dress and suit)


$1000


· Flowers


$2000


· Photographer


$1000


· Meals


$3000


Total


$7500


Approval Requirements

The project will be required to meet some specific requirements for it to be used for planning the wedding event. The main stakeholders will have to approve the charter and allow the commencement of the preparation of the planning. Therefore, the project sponsor, bride, and groom must approve the project and check if it meets the requirements; if not the reject it or suggest the modification.


References

Fangel, M. (2018). Proactive project management: How to make common sense common practice.


Project Charter. (2016). Project Management Simplified, 13-20.


Project Management Institute. (2018). A guide to the project management body of knowledge: (PMBOK® guide). Newtown Square, Pennsylvania: Author.


Verzuh, E. (2005). The fast forward MBA in project management (2nd ed.).


Applied Sciences

Architecture and Design

Biology

Business & Finance

Chemistry

Computer Science

Geography

Geology

Education

Engineering

English

Environmental science

Spanish

Government

History

Human Resource Management

Information Systems

Law

Literature

Mathematics

Nursing

Physics

Political Science

Psychology

Reading

Science

Social Science

Home

Blog

Archive

Contact

google+twitterfacebook

Copyright © 2019 HomeworkMarket.com

Homework is Completed By:

Writer Writer Name Amount Client Comments & Rating
Instant Homework Helper

ONLINE

Instant Homework Helper

$36

She helped me in last minute in a very reasonable price. She is a lifesaver, I got A+ grade in my homework, I will surely hire her again for my next assignments, Thumbs Up!

Order & Get This Solution Within 3 Hours in $25/Page

Custom Original Solution And Get A+ Grades

  • 100% Plagiarism Free
  • Proper APA/MLA/Harvard Referencing
  • Delivery in 3 Hours After Placing Order
  • Free Turnitin Report
  • Unlimited Revisions
  • Privacy Guaranteed

Order & Get This Solution Within 6 Hours in $20/Page

Custom Original Solution And Get A+ Grades

  • 100% Plagiarism Free
  • Proper APA/MLA/Harvard Referencing
  • Delivery in 6 Hours After Placing Order
  • Free Turnitin Report
  • Unlimited Revisions
  • Privacy Guaranteed

Order & Get This Solution Within 12 Hours in $15/Page

Custom Original Solution And Get A+ Grades

  • 100% Plagiarism Free
  • Proper APA/MLA/Harvard Referencing
  • Delivery in 12 Hours After Placing Order
  • Free Turnitin Report
  • Unlimited Revisions
  • Privacy Guaranteed

6 writers have sent their proposals to do this homework:

Writer Writer Name Offer Chat

Writers are writing their proposals. Just wait here to get the offers for your project...

Let our expert academic writers to help you in achieving a+ grades in your homework, assignment, quiz or exam.

Similar Homework Questions

Who does macbeth kill - 1001 and one nights - Mulga tree adaptations to the desert - Comparative analysis of financial statements project - Biochemical engineering an introductory textbook - Draw all constitutional isomers that have molecular formula - Cat 5 color code - Family reunion committee responsibilities - Cause and effect - I am presence decrees - Parkin economics 12th edition answers - London zoo educational visits - Assignment - Jeff savage book sidney crosby chapter 2 - Genesis account of creation powerpoint - Chuck close self portrait analysis - Part IV - Amazon ont9 redlands ca - Investing and Streaming Dreams - Nsw fire and rescue incidents - Holding tank assy c-250/260 - Mccormick international a6-1 cultivator drill - 24 hour shipping forecast - Cj industries and heavey pumps case study - Weather map assignment - How to make fake blood look more realistic - Newham guy fawkes night - Mcdonalds swot analysis weaknesses - Oxidation reduction lab report - Chemistry Exercises - MBA 599 - DISCUSSION #6 - Http www npr org series 4538138 this i believe - Easter show tickets discount - The nuclear membrane is allowing materials to pass through - Fish kill mystery case study answers - Social Process Theories - Advanced practice nursing an integrative approach 4th edition - The reaction of ethane gas with chlorine gas produces - Https://www.homeworkmarket.com/files/labreport-docx-4724911 - Vodafone 20 employee discount - Time series residual analysis - Threaded 4 - Discussion - Katherine mary knight husband - Strategies & Quality Practice - Molander corporation is a distributor of a sun umbrella - Rama's initiation from the ramayana summary - Dateline blind justice part 2 - Good to great chapter 7 summary - Inferential statistics project - News Source JRN - What determines the price and quantity of most goods - Goring and woodcote medical practice - Delta electronics singapore pte ltd - Discussion 3 - Which of the following budgetary accounts is typically used by a debt service fund? - Gth sedgemoor market reports - Queensland building and construction commission act 1991 schedule 1b - Persuasive speech problem solution outline sample - Two quality control technicians measure the surface finish - Ojala no sea demasiado tarde cuando te des cuenta - Discussion Question 4.1 - Zombie corp has a profit margin - Week 7 Discussion Board Assignment - Texas educator ethics training course answers - Ifsm 201 excel project 2 rental cars - Escape from planet soma case study answer key - Chapter 8 cellular reproduction cells from cells - Taxation - What was one cause of the great depression - Pick a topic - Counting hundreds in japanese - Adaptations of palisade cells - Respondo nano - Australian financial accounting 7e - Date of the census of quirinius - Numerically controlled oscillator ic - Ass1 - How many people did corrie ten boom save - Anova data analysis excel - Week 1 Discussion - 2 methyl 1 2 epoxypropane - A conducting loop in the shape of a square - Indicator Construction 8321 - Peptide bond formation in translation - Methoxy group electron donating or withdrawing - Khan academy piecewise functions - Fluke iv curve tracer - Food service management assignment - Freedom foods corn flakes woolworths - Carbon steel balls mm in diameter are annealed - What is the difference between a soliloquy and a monologue - Spying on miss muller - Talley and o'connor neurological examination - Change proposal - Function of thoracic cage - You can grow your brain article - Mat 510 week 8 case study 2 - Reflection: Academic Path - Frank rodriguez greenway automotive