What is merge activity in project management

23/10/2021 Client: muhammad11 Deadline: 2 Day

Chapter Six

Developing a Project Plan

6-1

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

6–2

Where We Are Now

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-2

Learning Objectives

Understand the linkage between WBS and the project network

Diagram a project network using AON methods

Calculate early, late, and slack activities times

Identify and understand the importance of managing the critical path

Distinguish free slack from total slack

Demonstrate understanding and application of lags in compressing projects or constraining the start or finish of an activity

6–3

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Chapter Outline

6.1 Developing the Project Network

6.2 From Work Package to Network

6.3 Constructing a Project Network

6.4 Activity-on-Node (AON) Fundamentals

6.5 Network Computation Process

6.6 Using the Forward and Backward Pass

Information

6.7 Level of Detail for Activities

6.8 Practical Considerations

6.9 Extended Network Techniques to Come

Closer to Reality

6–4

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

6–5

Developing the Project Network

The Project Network

A flow chart that graphically depicts the logical sequences, interdependencies, and start and finish times of the project activities along with the longest path(s) through the network—the critical path

Provides the basis for scheduling labor and equipment.

Enhances communication among project participants.

Provides an estimate of the project’s duration.

Provides a basis for budgeting cash flow.

Identifies activities that are critical.

Highlights activities that are “critical” and should not be delayed.

Help managers get and stay on plan.

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-5

6–6

From WBS/Work Package to Network

FIGURE 6.1

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-6

6–7

Constructing a Project Network

Terminology

Activity: an element of the project that requires time but may not require resources

Merge Activity: an activity that has two or more preceding activities on which it depends (more than one dependency arrow flowing into it)

Parallel Activities: Activities that can occur independently and, if desired, not at the same time

A

C

D

B

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-7

6–8

Constructing a Project Network (cont’d)

Terminology

Path: a sequence of connected, dependent activities

Critical Path:

The longest path through the activity network that allows for the completion of all project-related activities

The shortest expected time in which the entire project can be completed.

Delays on the critical path will delay completion of the entire project.

A

B

D

(Assumes that minimum of A + B > minimum of C in length of times to complete activities.)

C

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-8

6–9

Constructing a Project Network (cont’d)

Terminology

Burst Activity: an activity that has more than one activity immediately following it (more than one dependency arrow flowing from it)

Two Approaches

Activity-on-Node (AON)

Uses a node to depict an activity.

Activity-on-Arrow (AOA)

Uses an arrow to depict an activity.

B

D

A

C

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-9

6–10

Basic Rules to Follow in Developing Project Networks

Networks typically flow from left to right.

An activity cannot begin until all preceding connected activities are complete.

Arrows indicate precedence and flow and can cross over each other.

Each activity must have a unique identify number.

An activity identification number must be greater than that of any predecessor activities.

Looping is not allowed.

Conditional statements are not allowed.

Use common start and stop nodes.

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-10

6–11

Activity-on-Node Fundamentals

FIGURE 6.2

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-11

6–12

Activity-on-Node Fundamentals (cont’d)

FIGURE 6.2 (cont’d)

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-12

6–13

Network Information

TABLE 6.1

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-13

6–14

Automated Warehouse—Partial Network

FIGURE 6.3

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-14

6–15

Automated Warehouse—Complete Network

FIGURE 6.4

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-15

6–16

Network Computation Process

Forward Pass—Earliest Times

How soon can the activity start? (early start—ES)

How soon can the activity finish? (early finish—EF)

How soon can the project finish? (expected time—TE)

Backward Pass—Latest Times

How late can the activity start? (late start—LS)

How late can the activity finish? (late finish—LF)

Which activities represent the critical path?

How long can the activity be delayed? (slack or float—SL)

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-16

6–17

Network Information

TABLE 6.2

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-17

6–18

Activity-on-Node Network

FIGURE 6.5

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-18

6–19

Activity-on-Node Network Forward Pass

FIGURE 6.6

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-19

6–20

Forward Pass Computation

Add activity times along each path in the network (ES + Duration = EF).

Carry the early finish (EF) to the next activity where it becomes its early start (ES) unless…

The next succeeding activity is a merge activity, in which case the largest early finish (EF) number of all its immediate predecessor activities is selected.

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-20

6–21

Activity-on-Node Network Backward Pass

FIGURE 6.7

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-21

6–22

Backward Pass Computation

Subtract activity times along each path starting with the project end activity (LF - Duration = LS).

Carry the late start (LS) to the next preceding activity where it becomes its late finish (LF) unless…

The next succeeding activity is a burst activity, in which case the smallest late start (LS) number of all its immediate successor activities is selected.

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-22

6–23

Forward and Backward Passes Completed with Slack Times

FIGURE 6.8

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-23

6–24

Determining Total Slack (TS)

Total Slack (or Float)

Tells us the amount of time an activity can be delayed and not delayed the project.

Is how long an activity can exceed its early finish date without affecting the project end date or an imposed completion date.

Is simply the difference between the LS and ES (LS – ES = SL) or between LF and EF (LF – EF = SL).

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-24

6–25

Determining Free Slack (FS)

Free Slack (or Float)

Is the amount of time an activity can be delayed after the start of a longer parallel activity or activities.

Is how long an activity can exceed its early finish date without affecting early start dates of any successor(s).

Allows flexibility in scheduling scarce resources.

Only activities that occur at the end of a chain of activities, where you have a merge activity, can have free slack.

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-25

6–26

The Critical Path

Is the network path(s) that has (have) the least slack in common.

Is the longest path through the activity network.

Is the shortest expected time in which the entire project can be completed.

Is important because it impacts completion time.

Is where you put best people on.

Is where you pay extra extension when doing risk assessment.

Is where you look when other managers asking to ‘borrow’ people or equipment.

Is where you look when you don’t have time to monitor all activities.

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-26

6–27

Network Sensitivity

The likelihood the original critical path(s) will change once the project is initiated.

A network schedule that has only one critical path and noncritical activities that enjoy significant slack would be labeled ‘insensitive’.

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-27

6–28

Practical Considerations

Network Logic Errors

Activity Numbering

Use of Computers to Develop Networks (and Gantt Chart)

Calendar Dates

Multiple Starts and Multiple Projects

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-28

6–29

Network Logic Errors: Illogical Loop

FIGURE 6.9

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-29

6–30

Automated Warehouse Order Picking System Network

FIGURE 6.10

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-30

6–31

Automated Order Warehouse Picking System Bar Chart

FIGURE 6.11

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-31

6–32

Extended Network Techniques to Come Close to Reality

Laddering

Activities are broken into segments so the following activity can begin sooner and not delay the work.

Lags

The minimum amount of time a dependent activity must be delayed to begin or end.

Lengthy activities are broken down to reduce the delay in the start of successor activities.

Lags can be used to constrain finish-to-start, start-to-start, finish-to-finish, start-to-finish, or combination relationships.

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-32

6–33

Example of Laddering Using Finish-to-Start Relationship

FIGURE 6.12

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-33

6–34

Use of Lags

FIGURE 6.13

FIGURE 6.14

Finish-to-Start Relationship

Start-to-Start Relationship

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-34

6–35

Use of Lags (cont’d)

FIGURE 6.15

Use of Lags to Reduce Schedule Detail and Project Duration

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-35

6–36

New Product Development Process

FIGURE 6.16

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-36

6–37

Use of Lags (cont’d)

FIGURE 6.17

FIGURE 6.18

FIGURE 6.19

Finish-to-Finish Relationship

Start-to-Finish Relationship

Combination Relationships

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-37

6–38

Network Using Lags

FIGURE 6.20

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-38

6–39

Hammock Activities

Hammock Activity

Spans over a segment of a project.

Has a duration that is determined after the network plan is drawn.

Is very useful in assigning and controlling indirect project costs.

Is used to aggregate sections of the project to facilitate getting the right level of detail for specific sections of a project.

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-39

6–40

Hammock Activity Example

FIGURE 6.21

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-40

6–41

Key Terms

Activity

Activity-on-arrow (AOA)

Activity-on-node (AON)

Burst activity

Concurrent engineering

Critical path

Early time

Free slack

Gantt chart

Hammock activity

Lag relationship

Late time

Merge activity

Parallel activity

Sensitivity

Total slack

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-41

6–42

Shoreline Stadium Case

TABLE 6.3

Copyright © 2018 McGraw-Hill Education. All rights reserved. No reproduction or distribution without the prior written consent of McGraw-Hill Education.

Project Management 6e.

6-42

Homework is Completed By:

Writer Writer Name Amount Client Comments & Rating
Instant Homework Helper

ONLINE

Instant Homework Helper

$36

She helped me in last minute in a very reasonable price. She is a lifesaver, I got A+ grade in my homework, I will surely hire her again for my next assignments, Thumbs Up!

Order & Get This Solution Within 3 Hours in $25/Page

Custom Original Solution And Get A+ Grades

  • 100% Plagiarism Free
  • Proper APA/MLA/Harvard Referencing
  • Delivery in 3 Hours After Placing Order
  • Free Turnitin Report
  • Unlimited Revisions
  • Privacy Guaranteed

Order & Get This Solution Within 6 Hours in $20/Page

Custom Original Solution And Get A+ Grades

  • 100% Plagiarism Free
  • Proper APA/MLA/Harvard Referencing
  • Delivery in 6 Hours After Placing Order
  • Free Turnitin Report
  • Unlimited Revisions
  • Privacy Guaranteed

Order & Get This Solution Within 12 Hours in $15/Page

Custom Original Solution And Get A+ Grades

  • 100% Plagiarism Free
  • Proper APA/MLA/Harvard Referencing
  • Delivery in 12 Hours After Placing Order
  • Free Turnitin Report
  • Unlimited Revisions
  • Privacy Guaranteed

6 writers have sent their proposals to do this homework:

Maths Master
Assignment Hub
Top Grade Tutor
Supreme Essay Writer
Custom Coursework Service
Coursework Helper
Writer Writer Name Offer Chat
Maths Master

ONLINE

Maths Master

I am a PhD writer with 10 years of experience. I will be delivering high-quality, plagiarism-free work to you in the minimum amount of time. Waiting for your message.

$17 Chat With Writer
Assignment Hub

ONLINE

Assignment Hub

I am an academic and research writer with having an MBA degree in business and finance. I have written many business reports on several topics and am well aware of all academic referencing styles.

$19 Chat With Writer
Top Grade Tutor

ONLINE

Top Grade Tutor

Being a Ph.D. in the Business field, I have been doing academic writing for the past 7 years and have a good command over writing research papers, essay, dissertations and all kinds of academic writing and proofreading.

$20 Chat With Writer
Supreme Essay Writer

ONLINE

Supreme Essay Writer

I have worked on wide variety of research papers including; Analytical research paper, Argumentative research paper, Interpretative research, experimental research etc.

$42 Chat With Writer
Custom Coursework Service

ONLINE

Custom Coursework Service

I have assisted scholars, business persons, startups, entrepreneurs, marketers, managers etc in their, pitches, presentations, market research, business plans etc.

$42 Chat With Writer
Coursework Helper

ONLINE

Coursework Helper

I have assisted scholars, business persons, startups, entrepreneurs, marketers, managers etc in their, pitches, presentations, market research, business plans etc.

$16 Chat With Writer

Let our expert academic writers to help you in achieving a+ grades in your homework, assignment, quiz or exam.

Similar Homework Questions

Visual basic 2012 6th edition pdf - Components of classroom management ppt - Citizen queen y chords - What is 101 f in celsius - Osram led superstar par16 50 36 advanced - Fundamentals of machine drawing - The company uses a perpetual inventory system - Network rail standards catalogue - Act form 16mc1 answer key - 3 page paper - Simplex company has the following estimated costs for next year - Https www irs gov pub irs pdf f1040sc pdf - Adventures of an it leader summary - Big Data Analytics - Paper and Powerpoint presentation - Tolerance definition in metrology - Code of ethics comparative chart - Wanna talk to menge or hands off - Advocating for social justice discussion - Excel change chart style 42 - Week 6 - Assignment 6 - 136 howe street miners rest - Passion flower adaptations in the rainforest - Wade davis ted talk endangered cultures - Case 3 Post-Negotiation Journal - ATF - Gsxr 750 rr 1989 - What zone is pakistan in cie - Curtin university academic calendar - Greenhouse geisser correction factor - Compensation Management - Battle of the cowshed - What residue is being prevented by cleaning floor surfaces - High spen primary school - Ganger farm housing development - No estudiar tú en la biblioteca hoy por qué - Cash budget with supporting cash collections and disbursements schedules - Customer interviews - Graph of ln x - Ctrl z vs ctrl c - Order 2626593: American Psycho - The 18th amendment modified answer key - Ethical dilemma examples in pediatric nursing - Community rules and regulations - A debit memorandum on a bank statement indicates: - Alternatives to swot analysis - Anne norton the signs of shopping - Operations Manager Toolkit 7 - Wk 5, IOP/470: DR 1 - The yellow wallpaper quotes about freedom - Brisbane wave rider buoy - Example of a character sketch bible study - James watson and francis crick wiki - Letter to king george iii from colonists - Literature Review - Experiment 20 balanced chemical equations - Please select the correct sentence from the options below - Happy days heart song lyrics - Discussion Topic-Ch 2,3 - Organic Chemistry 1 - DISCUSSION - Ibookstore suss - What do your results indicate about cell cycle control - Specialised movement skills in volleyball - Nrs 490 scholarly activity summary - Lewisham council housing benefit - Define segregation and integration - Terminate end event bpmn - How to make a codebook for content analysis - How to make a wayfarer tent - Bmj best practice pneumonia - One of hipaa's five overall objectives is - A computer system includes the system unit along with - Michael jordan's basketball hall of fame enshrinement speech - Research project II - 7.3 preterite of ser and ir - Complex number polar form exponential - The three princes of serendip read online - Engl 102 test 2 answers - Strategic Financial Analysis - Small Group Communication - The waltz dorothy parker - Work breakdown structure for coffee shop - Skate 3 funny stuff compilation part 6 - Successful writing at work online - Chapter 10 business in a global economy answer key - How to calculate mva power - 8 mile wasting my time - Law of attraction pick up line - Application presentation session transport network data link physical - EBW6A - Www greenwichcollege edu au goals - Assignment(Digital forensics) - Proof surrogates convey to an uncritical audience that: - In which part of the chloroplast does each stage occur - The case for short words - Module 5 Homework - Frankenstein chapter 3 summary - The railway car park padstow - Choose 2 questions (Instructions are attached)