Project Initiation, Planning And Execution
This material has been reproduced and communicated to you by or on behalf of
Kaplan Higher Education pursuant to Part VB of the Copyright Act 1968 (the Act).
The material in this communication may be subject to copyright under the Act. Any
further reproduction or communication of this material by you may be the subject of
copyright protection under the Act.
Do not remove this notice
Week 1 Review
Differences between PM managers
and PM leaders
Project champions
International PM
• Understand and apply key scheduling terminology
• Apply the logic used to create activity networks,
including predecessor and successor tasks
• Develop an activity network using the Activity-on-Node
(AON) technique
Week 2 Learning Objectives
What is Project Scheduling?
• Project scheduling – a complex undertaking involving a
number of related steps.
• Consider the analogy of a jigsaw puzzle
• Firstly, create the border and then think about how the
pieces should fit together.
• Clues would be patches of light/dark, distinctive
shapes/colours.
• Add more and more pieces until complete.
Project Scheduling
• Similarly, the methodologies in project scheduling build
upon each other.
• Project scheduling requires us to follow some carefully
laid-out steps, in order, for the schedule to take shape.
• Project scheduling techniques are fundamental to a project
• One of the most common is IPECC:
Initiation. Planning. Execution. Control. Closure.
Project Scheduling
• Project scheduling allows for project goals to be completed
through a specific methodology.
• A timetable is developed that shows the network logic that
relating project activities to each other.
• Because project management relies on completing a finite
set of goals in a specified timeframe, development of the
project schedule is vitally important to success.
Project Scheduling
• This week and next week, we will be looking at a number
of project scheduling components and demonstrating
how the project plan is developed from a simple set of
identified project activities into a graphical set of
sequential relationships.
• PMBOK Definition of Project Scheduling:
“An output of a schedule model that presents linked
activities with planned dates, durations, milestones, and
resources.”
Project Management Institute (2013). Project Management Body of Knowledge, 4th ed. Newtown Square, PA:PMI
Workshop Activity
• Suppose you and your fellow classmates were given an
assignment on project management. At the end of the
semester, you are expected to submit a paper and
deliver a presentation.
• In small groups of 3 or 4, consider what steps you may
identify in completing the task. Then make a concise list
of the 10 main steps.
• Share your findings with the rest of the class.
Project Scheduling
• Defining all the steps necessary to complete the
assignment is a vital first step in project scheduling.
• Why? Because it adds a sequential logic to the tasks
and enables you to create a coherent project plan from
start to finish.
• To ensure the best use of time and availability, you
should create a network of the activities listed above,
that is, the most likely order in which they must occur to
be done correctly.
Project Scheduling
• Once you have identified a possible sequential
logic for the network, you can construct a network
diagram.
• This is defined as a “schematic display of the
project’s sequential activities and the logical
relationships between them”.
• The following slides show two examples of a
network diagram for the project.
Network Diagram
Source: Pinto, JK 2016, Project Management, Achieving Competitive Advantage, 4th Edition, Pearson Education Inc., p300
Network Diagram
Source: Pinto, JK 2016, Project Management, Achieving Competitive Advantage, 4th Edition, Pearson Education Inc., p300
Workshop Activity
Scheduling Terminology
• Project Scheduling has its own nomenclature
(language peculiar to a particular specialist field) so
it is important that you understand and become
familiar with the terms used.
• Form 4 small groups.
• Using a mobile / laptop / tablet, search for definitions
for the terms that appear on the next slide.
• Be prepared to share the definitions with the rest of
the class.
• Complete the definitions table on the next slide
Workshop Activity
Group A
Path
Event
CPM
Group B
Predecessors
Successors
Merge Activity
Group C
Project Network Diagram
PERT
Node
Group D
Forward Pass
Backward Pass
Burst Activity
Scheduling Terminology
• The two most common methods for constructing activity networks involve
Activity-on-Arrow (AOA) and Activity-on-Node (AON) logic.
• AOA method – the arrow represents the task, or activity, and the node
signifies an event marker that marks the completion of one activity and
the potential start of the next.
• AON method – the node represents the task, or activity and the path
arrows demonstrate the logical sequencing from node to node through
the network.
AOA vs AOA
Source: https://www.slideshare.net/DrMahmoudAlNaimi1/aoa-and-aon-networks-69802018,
accessed 27th October 2020
https://www.slideshare.net/DrMahmoudAlNaimi1/aoa-and-aon-networks-69802018
Developing a Network
• Network diagramming – a logical, sequential process that requires
consideration of the order in which activities should occur so that
projects can be scheduled as efficiently as possible.
• There are two primary methods for developing activity networks, PERT
and CPM.
• PERT (Program Evaluation and Review Technique) was developed in
the late 1950s for the creation of the Polaris missile program.
• PERT was originally used in research and development (R&D), a field in
which activity duration estimates can be difficult to make, and resulted
from probability analysis.
Developing a Network
• CPM (Critical Path Method) – developed independently at the same
time as PERT (Program Evaluation and Review Technique) by DuPont,
Inc.
• CPM used commonly in the construction industry, differs from PERT
primarily in the assumptions it makes about estimating activity
durations.
• CPM – assumes that durations are easier to ascertain and can be
assigned to activities with greater confidence.
• CPM also was designed to better link and control project activity time
and costs, particularly the time/cost trade-offs that lead to crashing
decisions (speeding up the project).
Developing a Network
1. Determination of activity precedence – i.e. All activities must be
logically linked to each other –those that precede others, as well
as successor activities (those that must follow others).
2. Network diagrams normally flow from left to right.
3. An activity cannot usually begin until all preceding connected
activities have been completed.
4. Arrows on networks indicate precedence and logical flow. Arrows
can cross over each other, although it is helpful to limit this effect
when possible.
Developing a Network
2. Each activity should have a unique identifier associated with it
(code, number, letter etc.). For simplicity, these identifiers should
occur in ascending order; each one should be larger than the
identifiers of preceding activities.
3. Looping, or recycling through activities, is not permitted.
4. Although not required, it is common to start a project from a single
beginning node, even when multiple start points are possible. A
single node point is typically used as a project start and end
indicator.
Labeling Nodes Nodes representing project activities should be clearly labeled with different information. It is useful if the nodes contain the following:
1. Identifier
2. Descriptive label
3. Activity duration
4. Early start time
5. Early finish time
6. Late start time
7. Late finish time
8. Activity float
Labels for Activity Node
Source: Pinto, JK 2016, Project Management, Achieving Competitive Advantage, 4th Edition, Pearson Education Inc., p303
Activity Node Labels Using MS Project 2013
Source: Pinto, JK 2016, Project Management, Achieving Competitive Advantage, 4th Edition, Pearson Education Inc., p303
Serial Activities • Serial activities are those that flow from
one to the next in sequence.
• Following the logic of the diagram below,
we cannot begin work on Activity B until
Activity A has been completed. Activity C
cannot begin until both Activities A and B
are finished.
Source: Pinto, JK 2016, Project Management, Achieving Competitive Advantage, 4th Edition, Pearson Education Inc., p303
Concurrent Activities • Often it is possible to begin work on more than
one activity simultaneously.
• The diagram below shows an example of how
concurrent project paths are represented in an
activity network.
Source: Pinto, JK 2016, Project Management, Achieving Competitive Advantage, 4th Edition, Pearson Education Inc., p304
Merge Activities • Merge activities are those with two or more immediate
predecessors (see diagram below).
• Merge activities – often at critical junction points (places
where two or more parallel project paths converge).
Source: Pinto, JK 2016, Project Management, Achieving Competitive Advantage, 4th Edition, Pearson Education Inc., p304
Burst Activities
• Burst activities are those with two or more immediate
successor activities.
• The diagram below graphically depicts a burst activity, with
Activities B, C, and D scheduled to follow the completion
of Activity A.
Source: Pinto, JK 2016, Project Management, Achieving Competitive Advantage, 4th Edition, Pearson Education Inc., p304
Merge and Burst Example
Source: http://facultyweb.kennesaw.edu/fwarner/chapter_student_handouts/mgmt_4135_chapter6.pd
f, slide 7, accessed 27th October 2020
http://facultyweb.kennesaw.edu/fwarner/chapter_student_handouts/mgmt_4135_chapter6.pdf
Workshop Activity
Activity Predecessors
A -
B A
C B
D B
E C,D
F C
G E,F
H D,G
Assuming the following information, create an activity network that
shows the sequential logic between the project tasks. Where are
the merge and burst activities?
Worked Example Constructing a Basic Activity Network
The table below identifies eight activities and their
predecessors in a simple example project:
Source: Pinto, JK 2016, Project Management, Achieving Competitive Advantage, 4th Edition, Pearson Education Inc., p305
Worked Example Constructing a Basic Activity Network
• The diagram below shows a partial network diagram
based on the information we have compiled to this point.
• Based on our definitions, Activity A is a burst activity and
Activity D is a merge activity.
Source: Pinto, JK 2016, Project Management, Achieving Competitive Advantage,
4th Edition, Pearson Education Inc., p306
contract survey
Worked Example Constructing a Basic Activity Network
• We can continue to create the network iteratively as we
add additional activity nodes to the diagram. The
diagram below shows the completed activity network.
Source: Pinto, JK 2016, Project Management, Achieving Competitive Advantage, 4th Edition, Pearson Education Inc., p306
Activity Networks Using
Software Applications • It should be noted that software applications are commonly
used to construct Activity Networks.
• We will be covering such applications in Week 7.
Summary
• Covered some of the key scheduling
terminology.
• Applied the logic used to create activity
networks.
• Developed an activity network using Activity-
on-Node (AON) techniques.
Next Week
Project scheduling:
duration estimation and critical path.