Three teams in the Agile Release Train are working on the same Feature. Team A is a component team, and Team B and Team C are feature teams. During PI planning, Team B and C committed to delivering their part of the Feature by the end of Iteration five and plan to integrate with each other along with Team A’s piece in the first week of the IP Iteration. Why is this an anti-pattern.
Because the teams managed their dependencies and planned their integration timing during PI planning
Because work should not be planned for the IP iteration
Because Product Manager accepted each team’s final plan at the end of PI Planning Day 2.
Because each feature team needs to integrate with the component team
Because each feature team need to integrate with the component team